Title: Governors Conference Helena, Montana 2005
1Governors ConferenceHelena, Montana2005
215-90 Corridor IC Project About The Presentation
- Project Overview
- Consortium Roadmap
- Possible Keys for Success
- Overriding Principle
315-90 Corridor IC Project OverviewA Four County
Consortium
- Anaconda Deer Lodge County
- Beaverhead County
- Butte Silver Bow County
- Granite County
415-90 Corridor IC Project Overview Consortium
Governing Board
- Buzzy Peterson, Anaconda Deer Lodge
- Larry Laknar, Beaverhead
- Wilma Puich, Butte Silver Bow
- Jim Minor, Granite
515-90 Corridor IC Project Overview Purpose
- Conduct Needs Assessment
- Write a Public Safety Mobile Radio Interoperable
Communications Implementation Strategy (Plan)
615-90 Corridor IC Project Overview Project
Specifications Highlights
- Addresses needs of counties individually and
collectively - System based on Federal and State communication
standards - Interoperable with existing projects (NTIP, SWIP,
Missoula) - Backward compatibility
- Allows for phased implementation
715-90 Corridor IC Project Overview Project
Specifications Highlights
- Improves radio communications coverage, relieves
channel congestion and provides interoperable
radio services - Accommodates voice and mobile data communications
- Leverages existing and new wireless communication
assets - Changes in user requirements over next 5 years
will be anticipated
815-90 Corridor IC Project Overview Project
Specifications Highlights
- Coverage goal will be developed with the
Consortium - Based on user needs
- Allows for migration to emerging wireless
technologies
915-90 Corridor IC Project Overview Cost
- 194,810 (Federal Engineering)
- 3,000 (Butte Silver Bow, Office)
- 760 (Project Director, Travel Phone)
- Total Cost 198,570.00
- Cost per County 49,642.50
1015-90 Corridor IC Project Overview Timeline
- Began January 7, 2005
- Ends on or about May 15, 2005
1115-90 Consortium Roadmap
- Started Today
- March February
- 2004 2005
1215-90 Consortium RoadmapOverview
- Defined the Problem
- Recognized the Bottom Line
- Defined the IC Strategy
- Defined the Alternatives
- Gathered Information
- Formed the Consortium
- Began Work
1315-90 Consortium RoadmapMarch, 2004
- Defined the Problem
- Significant cost to implement
- Effect of P25 on current system(s) in place
- Little to no idea of the problems to be resolved
- Effect of incremental introduction of new
equipment - To risky to proceed
1415-90 Consortium RoadmapMarch, 2004
- Recognized the Bottom Line
- We didnt know enough
- about interoperable communications
- to make an informed decision . . .
1515-90 Consortium RoadmapMarch, 2004
- Recognized the Bottom Line
- And, interoperable communications
- is more than buying equipment
- and putting it in place . . .
1615-90 Consortium RoadmapMarch, 2004
- Defined IC Strategy
- Needed assistance to define the problems
- Needed assistance to write a plan
- Needed money to attract a reputable firm
- Decided to set aside money from FY 2003 SHSGPII
War Supplemental Grant to conduct needs
assessment and write the implementation strategy
1715-90 Consortium RoadmapAugust to October, 2004
/ 3 Meetings
- Defined the Alternatives
- Each county do its own thing
- Hire contractor to write an RFP
- Enter into contract with Federal Engineering (FE)
- Enter into RFP contract with company
1815-90 Consortium RoadmapAugust to October, 2004
/ 3 Meetings
- Gathered Information
- RFP
- Current Projects
- Northern Tier Interoperability Project (NTIP)
- South West Interoperability Project (SWIP)
- South Central Montana Interoperability Consortium
(SCMIC) - Missoula
- Federal Engineering
1915-90 Consortium RoadmapAugust to October, 2004
/ 3 Meetings
- Formed Consortium
- Letter of Intent (LOI) written
- Example Letters of Support written for LOI
- LOI signed by LEPC County Government Officials
and Letters of Support submitted - Developed Form to Evaluate the Alternatives
- Memorandum of Understanding (MOU) written
- MOU signed by LEPC County Government Officials
2015-90 Consortium RoadmapAugust to October, 2004
/ 3 Meetings
- Formed Consortium (Continued)
- Consortium Project Director Job Description
written - Conducted Equipment Survey
- Solicited Proposal from FE
- Received Statement of Work (SOW) from FE
- Detailed Review of SOW from FE
- FE Presentation
2115-90 Consortium RoadmapAugust to October, 2004
/ 3 Meetings
- Formed Consortium (Continued)
- Offered contract to FE
- Appointed Consortium Project Director
- FE appoints Program Manager
- Submitted LOI and MOU to Montana DES
- Submitted CDP Proposal Abstract to SIEC
- SIEC Approves 15-90 CDP Proposal Abstract
2215-90 Consortium RoadmapAugust to October, 2004
/ 3 Meetings
- Formed Consortium (Continued)
- Money transferred from FY 2003 SHSGPII War
Supplemental money under MOU by Montana DES - Submitted FY 2004 HSGP Grant Application
- FY 2004 HSGP Grant Application approved by
Montana DES - Money transferred from FY 2004 HSGP War
Supplemental money under MOU by Montana DES - Billing Payment procedure defined
2315-90 Consortium RoadmapJanuary to February,
2005 / 2 Meetings
- Began Work
- Project Orientation Meeting
- Interviews with Agencies Stakeholders Completed
- Site Visits Completed
- Presentation at Governors Conference
24Possible Keys for Success
- Participation of Agencies and Stakeholders
- DES Coordinators
- First Responders
- Montana DES
- Montana Public Safety Services Bureau
- Manageable steps that can be accomplished
- Defined outcomes for measuring progress
- Willingness to consider options, alternatives and
make adjustments when necessary
25Possible Keys for Success
- Individuals who will take responsibility for work
- Organize meetings, prepare handouts and take
minutes - Obtain information for group
- Write draft documents for group
- Maintain project focus, i.e., interoperable
communications is all about saving the lives of
first responders and those they serve
26Possible Keys for Success
- Attend meetings
- Rely on state agencies for assistance
- Dont reinvent the wheel
- Attitude of we still have much to learn, e.g.,
- SWIP and NTIP are much further down the road
- and we can learn from them
- Own the project
- Role of facilitator
27Overriding Principle
- The project is about saving lives,
- the lives of first responders and others,
- and those they serve.
28- www.discoveringmontana.com/itsd/policy/councils/
- SIEC/cdprojects/15-90/15-90.asp