Title: Bioreactor Landfill Demonstration Project
1Bioreactor Landfill Demonstration Project
- Report to FCSHWM Advisory Board
- February 9, 2001
- Orlando, Florida
2Status Report
- Permit Status
- Design/Bid Package
- Construction Status
- Research Status
3Permit Status
4Bid Package
- Bid package completed
- Bid package being advertised February 10, 2001
5Construction Schedule
- Current Landfill Configuration
- Landfill Survey
- Well Installation
- Construction
6(No Transcript)
7Valley Before Filling 10/17/00
8Valley After Filling Began 10/27/00
9(No Transcript)
10View from Entrance Road
11Bioreactor Access Road
12(No Transcript)
13Global Positioning System
- GPS Rover Backpack
- Location/Elevation Collection
- GPS Base Station
- GPS Error Correction from Known Point
14Global Positioning System
- GPS Antenna
- white disk is the GPS satellite antenna receiving
signals - black wire antenna is the radio communicating
with Rover Backpack
- GPS receiver translates GPS satellite
information into a useable position and issues
correction to Rover
15- The red crosses are the points that were
surveyed. We did both sides of the road and then
a bit at the top of the landfill. The corners
(lowest elevations) are points we surveyed to
show the difference in height from the paved road
to the top. - Below are different views.
16(No Transcript)
17N
18Well Installation
- Two types of wells
- Injection wells
- Sensor pack wells
- Well locations are being field located next week
- Start drilling 2 3 weeks
19(No Transcript)
20Well Design
21Construction
- Bid package advertised Feb 10
- 30 day bid review period
- 15 day contract negotiation period
22Research Activities Since Last Board Meeting
- UCF/UF Sensor Investigation
- Monitoring of pressure transducers at NRRL Cell 2
and 3 and the Tomoka Falls Landfill - Alternative Sensor Investigation
- Leachate Analysis
23Tomoka Falls Landfill Data Logger Station
24Tomoka Falls Landfill Weather Station
25NRRL Cell 2 Head on the Liner
26NRRL Cell 3 Head on the Liner
27Tomoka Falls Landfill Head on the Liner
28Sensor Calibration Results
29Sensor Conclusions
- Sensors respond to wetting front arrival and
passage - Sensors are sensitive to changes in leachate
characteristics. - Use 0.5 mm diameter sand particles for optimum
response time and sensitivity - Provide wicking material external to sensor to
increase responsiveness
30(No Transcript)
31Example Earth Pressure Cell Readout
32Example Leachate Data
pH
TDS
33VOC Data
34Bioreactor Presentations
- Presentation at the GRI-14 Conference in Las
Vegas, Nevada, December 14, 2000. - Presentation at the Lulea Landfill Symposium,
December 12, 2000 - Participated in the USEPA Bioreactor Briefing in
Washington D.C., September 6 and 7, 2000, and - Presented at the Tennessee SWANA meeting
September 14, 2000.
35Questions