Title: EP 702 Unit 7
1EP 702Unit 7
Dr. J. Michael Bennett, P. Eng., PMP UNENE,
McMaster University, The University of Western
Ontario Version 2K6-X-10
2Revisions
- 2K6-X-10 Initial Creation
3EP 704 Road Map
- Unit 1 Introduction to Project Management
- Unit 2 The Project Management Context
- Unit 3 Project Management Processes
- Unit 4 Project Integration Management
- Unit 5 Project Scope Management
- Unit 6 Project Time Management
- Unit 7 Project Cost Management
- Unit 8 Project Quality Management
- Unit 9 Project Human Resource Management
- Unit 10 Project Communications Management
- Unit 11 Project Risk Management
- Unit 12 Project Procurement Management
4Unit 7
- Includes all of the processes necessary to plan,
estimate, budget and control costs - Normally this is one area in which the Org excels
- Main Areas are
- 7.1 Cost Estimating
- 7.2 Cost Budgeting
- 7.3 Cost Control
- 7.4 MCCP
- 7.5 Productivity Measures
- 7.6 Cost Overrun Causes
5PCM
- Primarily concerned with the cost of resources
necessary to get the work done. - Note that 6 and 7 are often combined as a single
activity. - Can also consider the effect of changes on the
final product (life cycle costing or TCO). - Note that the Cost Management Plan flows out of
the PMP development (again iterated elaboration)
6Cost Management Plan
- Precision Level of data (rounding for example)
- Units of measure
- Org Procedures linkages
- Control Thresholds
- Earned Value Rules
- Reporting Formats
- Process Descriptions
7History, Org Policies
Marketplace conditions Commercial databases
Project Scope Stmt
Project Management Plan
Cost Management Plan
Approved Change Reqs
WBS Dictionary
Activity Cost Estimates detail
Contract
CMP updates Requested Changes
Requested Changes, CMP UPs
Resource Calendar
Cost baseline Project funding reqs
Proj Schedule
Performance Reports
PMP UDs, Requested Changes
Work Performance Information
Cost Est UDs, Perf Measurements, Forecasted
Completion
OPA updates
8 PMI Project Cost Management
7.1 Cost Estimation .1 Inputs .1 EEF .2
OPA . 3 Scope Statement .4 WBS .5
WBS Dictionary .6 PMP .2 Tools and
Techniques .1 Analogous Estimating .2
Determine resource cost rate .3 Bottom-up
Estimating .4 Parametric Estimating .5
PMP Software .6 Vendor Bid Analysis .7
Reserve Analysis .8 Cost of Quality .3
Output . 1 Activity Cost Estimates
.2 ACE Supporting Detail . 3 Requested
Changes .4 Cost Man Plans UDs
7.3 Cost Control .1 Inputs .1 Cost Baseline
.2 Project Funding Requirements .3
Performance Reports .4 Work Performance
Information .5 Approved Change Requests
.6 PMP .2 Tools and Techniques . 1 Cost CCS
.2 Performance Measurement Ana .3
Forecasting .4 Project Performance Reviews
.5 PM Software .6 Variance Management .3
Output .1 Cost Estimates (UDs) .2
Cost Baseline (UDs) .3 Performance
Measurements .4 Forecasted Completion
.5 Requested Changes .6 Recommended
Corrective Actions .7 OPAs (UDs0 .8 PMP
(UDs)
7.2 Cost Budgeting .1 Inputs .1 Scope
Statement .2 WBS .3 WBD Dictionary
.4 ACEs .5 ACE Supporting Detail .6
Project Schedule .7 Resource Calendars
.8 Contract .9 Cost Management Plan .2 Tools
and Techniques .1 Cost Aggregation .2
Reserve Analysis .3 Parametric Estimating
.4 Funding Limit Reconciliation .3 Output
.1 Cost Baseline .2 Project Funding
Requirements .3 CMP (Updates) .4
Requested Changes
97.1 Cost Estimating
1 Analogous Esting 2 Resource Cost Rate 3
Bottom-up Esting 4 Parametric Esting 5 PMP
Software 6 Vendor Bid Analysis 7 Reserve
Analysis 8 Cost of Quality
1 EEF 2 OPA 3 Scope Statement 4 WBS 5 WBS
Dictionary 6 PMP
1 Activity Cost Ests 2 Supporting Detail 3
Requested Changes 4 Cost Man Plans uds
107.1.1 Inputs to Cost Estimating
- 1 EEF
- 2 OPA
- 3 Scope Statement
- 4 WBS
- 5 WBS Dictionary
- 6 PMP
111 EEF
- CEP considers
- Marketplace Conditions
- Commercial Databases
122 OPA
- Cost Estimating Policies
- Cost Estimation templates
- Historical Information
- Project Files
- Project Team Knowledge
- Lessons Learned
133 Scope Statement
- This hones the budget process
- A normal constraint is the fixed budget
- Assumptions may lead to legal ramifications
146 Schedule Management Plan
- Need this to cost out activities appropriately
- May have to worry about the cost of financing
- Materials may have seasonal cost variations
- Same with human resource costing (cf Alberta
right now)
15Cost Management
- Three main processes will occur at least once in
EACH phase - Note the better approach of using Life Cycle
Costing (aka TCO) - Need to separate controllable and
non-controllable costs if a reward system is in
place - Example of overtime costs
16Smallies
- Resource planning, cost estimating and cost
budgeting are often combined on small projects
(they are so tightly integrated)
17General Comments
- Ability to influence cost is highest earliest in
the project - Need scope and requirements done first and ASAP!
18Assumptions
- The 10 economy! If we had 0 for the 3 years, we
would have made 100K on our investment or 20 - The assumed income projections. Where did they
come from and how realistic are they?
197.1.2 TT for Cost Estimating
- 1 Analogous Estimating
- 2 Resource Cost Rate
- 3 Bottom-up Estimating
- 4 Parametric Estimating
- 5 PMP Software
- 6 Vendor Bid Analysis
- 7 Reserve Analysis
- 8 Cost of Quality
201 Analogous Estimating
- Also called top-down
- Compare against a similar project
- Is another form of Expert Judgment
- Used when we have little information to work
with, normally at the beginning of the project - Least costly of the 5 methods but least accurate
- Most accurate when the projects really are
similar and/or people really are experts
21Comparison (after Kerzner).
22Internal Rate of Return (IRR)
- What is the nominal percentage that this
investment will return? - Find the interest rate at which the
NPVProjectCost - Can be done with Excel and iteration
- Not so common now
23Return on Investment (ROI)
- measure of the efficiency of the investment
- calculated as(total benefits - total costs) x
100 / total costs
24Growing Importance of ROIIW 2001-VIII-08, survey
of 200 IT Professionals
25Measuring PaybackIW 2001-VIII-08, survey of 200
IT Professionals
Q Does your company have formal ROI or informal
payback scenarios?
26ROI vs. IntangiblesIW 2001-VIII-08, survey of
200 IT Professionals
27Is ROI Targeted?IW 2001-VIII-08, survey of 200
IT Professionals
28Breakeven-Payback
- date when cumulative benefit flow exceeds
cumulative costs flow - normally expressed in months
29Traditional Cost Reduction Approaches
- Cost displacement - cost avoidance
- Work Value Analysis
- Cost of quality
30Cost Displacement - Cost Avoidance
- compares the cost for the proposed system against
the replaced one - most common way to justify IT projects
- used for CPUs for years
31Work Value Analysis
- permits white collar workers to do more
profitable work - increases efficiency of doing same work
- permits higher valued work to be done
- Sassone estimates 15 can be saved by such
recalibration and increase of intellectual
specialization
322 Determine Resource Cost Rate
- Must know the unit cost rates (staff cost per
hour, FPPM, cost per cubic meter etc) - Get quotes from vendors
- Normally for stock items, there are standard
rates plus inflation factors. - Can use commercial sources
- If not, you must estimate and justify the
estimates
333 Bottom Up Estimating
- Start at the bottom of the WBS and roll up
- Normally we can estimate very accurately in the
small - Assumes that we have done sufficient breakdown so
that we can so estimate
342 Parametric Estimating
- Uses a mathematical (arithmetical?) model to
estimate - FPs are a PE method
- Works best when the method has been used for a
long time (construction) - Great if the model is scalable
356 Vendor Bid Analysis
- Check out the various bids. Are they consistent?
- If we are bidding and get a contract, may have to
do additional work to justify the final project
cost.
367 Reserve Analysis
- Many cost estimators add in the reserve (or
contingency fund) as part of the project cost
which of course make it higher. - This is the known unknown (risks anticipated but
not known for certain). - Sometimes, all of the K-Us are aggregated into a
single activity item with zero time duration.
378 Cost of Quality
- Based on observation that organizational
resources can be split into value-added
services and cost-of-quality activities. - CoQ include costs associated with LACK of quality
- Reducing quality costs can save a bundle. Good
justifier!
387.1.3 Cost Estimating Outputs
- 1 Activity Cost Estimates
- 2 Activity Cost Supporting Detail
- 3 Requested Changes
- 4 Cost Management Plans updates
391 Activity Cost Estimates
- A quantitative assessment of the likely costs of
the resources to complete the work activity - Can be in summary or detailed form
- Can include
- Labour
- Materials
- Equipment
- Services
- Facilities
- IT
- Inflation allowance
- Contingency reserve
402 Activity Cost Supporting Detail
- Catch-all to include all information necessary to
understand, the costing of the scheduled activity - Description of the activitys scope of work
- Documentation of how the estimate was developed
- Documentation of all assumptions made
- Documentation of all constraints
- Indication of the range of the estimates ()
417.2 Cost Budgeting
- Involves aggregating the estimated costs of all
the work packages to establish a cost baseline. - The Scope Statement provides the summary budget.
- But these are necessary before detailed budget
requests and work authorization can occur.
427.2 Cost Budgeting
1 Scope Statement 2 WBS 3 WBD Dictionary 4 ACEs 5
Supping Detail 6 Project Schedule 7 Res
Calendars 8 Contract 9 Cost Man Plan
1 Cost Aggregn 2 Reserve Analysis 3 Parametric
Estg 4 Funding Limit Reconciliation
1 Cost Baseline 2 Project Funding Rs 3 CMP
(Updates) 4 Requested Changes
437.2.1 Cost Budgeting Inputs
- 1 Scope Statement
- 2 WBS
- 3 WBD Dictionary
- 4 ACEs
- 5 ACE Supporting Detail
- 6 Project Schedule
- 7 Resource Calendars
- 8 Contract
- 9 Cost Man Plan
447.2.2 Cost Budgeting Tools Techniques
- 1 Cost Aggregation
- 2 Reserve Analysis
- 3 Parametric Estimating
- 4 Funding Limit Reconciliation
45.5 Methods of Costing
- 5.1 Time-based Measures
- 5.2 New Strategic (non-) Initiatives
46Time-based Cost Approaches
- Net Present Value (NPV)
- Internal Rate-of-Return (IRR)
- Return on Investment (ROI)
- Breakeven/Payback
47Net Present Value
- the value today of a future payment discounted at
an assumed rate - if that rate is positive, will make money
- also called the Discounted Cash Flow
48NPV Example
- We will make 100K in a year
- That amount today must be discounted by 10
- For example, if we invested 100K at 10, in a
year it would be worth 110K - Therefore the NPV of 100K in a year at 10 is
100,000/(10.1) 90,909. - The NPV of 100K in 2 years at 10 is
100,000/(10.1)2 84,645. -
49NPV Example
- Suppose that a project will cost 500K and take a
year to build - In years 2,3 and 4, it will return 100K, 200K and
300K - Assume a 10 economy (that is, the cost of living
is estimated to be 10 per year) - Question should we do the project?
50Example cont
- NPV 100000/1.1 200000/(1.1)2 300000/(1.1)3
909,090 165,289 225,394 481,593 - Project costs 500K and will only earn 482K
- CAN IT
51.5.2 New Strategic (non-) Approaches
- Options Values
- Technological Values
- Business Objectives
- Competitive Advantage
- Research and Development
52Options Values
- assigns values to options
- think of it as a tree of decisions
- very hard to do but necessary for long-termed
decisions such as data bases, communications,
etc. - OV are rejected by NPV approaches
53Technological Values
- needed to provide infrastructure
- hard to justify economic payback but mandatory
for survival - installation of a LAN, for example
- WAN for decentralization
- e.g..., installing fiber-optics backbone for
client-server Business Line
54Business Objectives
- justifying IT expenditure against business
alignment (as we have seen)
55Competitive Advantages
- Can the project build in switching costs?
- Can the project change the basis of competition?
- Can the project change the balance of power in
supplier relationships? - Can the project generate new products?
- Can we do it cheaper?
- Can we delight our clients?
56Examples
- Canada Trust
- Bell Mobility
57Competitive Advantages cont.
- Some suggestions for positioning the project for
competitive advantage - target the project to core business drivers
- examine core drivers from the customers
perspective - look for advantage to come from infrastructure
initiatives rather than individual Business Lines - assess options in terms of the time for an
opportunity to become a necessity
587.2.3 Outputs from Cost Estimating
- 1 Cost estimates
- 2 Supporting detail
- 3 Cost management plan
591 Cost Estimates
- are quantitative estimates normally expressed in
- Every cost must be estimated
- If there are guidelines, follow them
60Classes of Estimates (after Kerzner)
61Classes of Estimates (AACE)
621 Cost Aggregation
- These begin at the WP level and are rolled up to
higher levels of the WBS to be assigned to
Control Accounts (and ultimately for the whole
project)
63.7 Chart of Accounts
- Coding structure by which we group expenses
- Can be per phase
- Per step of development process
- will be defined by the bean counters but VIP
642 Reserve Analysis
- Must calculate the management reserves (for
unknown unknowns). - Not part of the project cost baseline but are
included in the budget. - Not used for EV calculations.
- PM must get approval to apply these from the PHB.
653 Parametric Estimating
- Used to build a mathematical model
- Simple cost per square meter for house
construction - Complex software model that used 13 factors, 5
sub factors for each) - Most likely reliable is
- Historical data is accurate
- Parameters are reliably quantifiable
- Model can be scaled (look out!)
664 Funding Limit Reconciliation
- A Quandary
- You do not want to allocate all the resources
(waterfall) - BUUUT, you want to allocate smoothly so that the
work will not be stalled. - FLR tries to find the optimal solution here.
677.2.3 Cost Budgeting Outputs
- 1 Cost Baseline
- 2 Project Funding Requirements
- 3 CMP (Updates)
- 4 Requested Changes
681 Cost Baseline
- The time-phased budget that is used for EV
control - Normally S-based curve
- Can have many sub cost baselines in large
projects (for contractors, etc)
69Risks
- Need to consider risks at this point too
- Risks can have a significant impact of cost if
they raise their hydra heads
702 Project Funding Requirements
- These flow from the Cost Baseline in an orderly
fashion, to ensure enough money is available to
continue the work
71Committed versus Spent (typical)Visualizing PM
Forsberg et al
Funding Requirements
85
70
04
10
40
727.3 Cost Control
1 Cost Ests (UDs) 2 Cost BL (UDs) 3 Perf
Meass 4 Forecast Finish 5 Reqd Changes 6 Recd
Corr Actions 7 OPAs (UDs) 8 PMP (UDs)
1 Cost CCS 2 Perf Meas Ana 3 Forecasting 4 Proj
Perf Revs 5 PM Software 6 Variance Man
1 Cost Baseline 2 Proj Funding Reqs 3 Performance
Reports 4 Work Perf. Info. 5 Approved CRs 6 PMP
73Purpose of Cost Control
- Influencing the factors that create changes to
the cost baseline to make sure the changes are
acceptable - Determine that the cost baseline has changed
- Make the changes in a controlled manner
74Cost Control includes
- Influencing factors that can change the BL
- Ensuring requested changes are agreed on
- Managing the actual changes
- Assuring that cost overruns do not exceed
authorized funding - Monitoring and understanding cost variances
- Recording all changes against the BL.
- Informing all stakeholders of changes
- Acting to be sure cost overruns are contained
75Activities of Cost Control
- Monitoring the cost performance (EV)
- Ensuring that all approved changes are reported
in the Cost Baseline - Pre venting unauthorized, incorrect,
inappropriate costs from being incurred - Informing stakeholders (as appropriate) about the
changes - Keeping expected costs within limits
763 Work Performance Reports
- Data collected includes at least
- Deliverables done and undone
- Costs authorized and incurred
- Estimates to complete the schedule activities
- complete of the schedule activities
777.3.2 Cost Control Tools Techniques
- 1 Cost Change Control System
- 2 Performance Measurement Analysis
- 3 Forecasting
- 4 Project Performance Reviews
- 5 PM Software
- 6 Variance Management
781 Cost Change Control System
- Defines the procedures under which the BL is to
be changed (comes from CMP). - Includes all forms, authorizations, tracking
systems
792 Performance Measurement Analysis
- Must collect
- PV planned value
- EV Earned value
- AC Actual Cost
- ETC Estimate to Complete
- CV Cost Variance (CVEV-AC)
- SV - Schedule Variance (SVEV-PV)
- CPI Cost Performance Index EV/AC SPIEV/PV
- Cumulative CPI (CPIC) S (EVC/ACC)
C1,N
803 Forecasting
- Trickery trickery trickery
- ETC based on atypicals BAC-EVC
- ETC based on typicals (BAC-EVC)/CPIC
- Also use EAC ACC ETC
- Or EAC ACC (BAC EV)
- Or EAC ACC (BAC EV)/CPIC
814 Project Performance Reviews
- Variance Analysis
- Trend Analysis
- Earned Value Technique
825 PM Software
- This automatically tracks variance and EV
836 Variance Management
- Describes how we will manage variances
- Note that they are larger at the beginning than
at the end
847.3.3 Cost Controls Outputs
- 1 Cost Estimates (UDs)
- 2 Cost Baseline (UDs)
- 3 Performance Measurements
- 4 Forecast Finish
- 5 Required Changes
- 6 Recommended Corrective Actions
- 7 OPAs (UDs)
- 8 PMP (UDs)
857.4 Management Cost and Control System (MCCS)
Cost Data Collection and Reporting
Planning
Customer Manment Reporting
Cost Accountg
Work Auth and Release
Planning cycle
Operating Cycle
86The MCCS Planning Tool must be able to
- Plan and schedule the work
- ID metrics
- Establish direct labour budgets
- Establish overhead budgets
- ID Management Reserve
87Operational Requirements
- Measure resources consumed
- Measure status and accomplishments
- Compare metrics to projections, standards
- Provide basis for diagnosis and replanning
88MCCS Requirements
- Common framework to integrate time, cost,
technical performance - Ability to track important metrics
- Quick response
- Capability of end-value prediction
- Accurate, appropriate data for decision-making
- Full exception reporting with probability
analysis - Immediate quantitative evaluation of alternate
solutions
89Cost Reduction Analysis
Possible Reductions
Cost of change
Project Life Cycle Phases
90Operational Issues
- Cost account codes
- Common to organization
- Should be hierarchical
- EV as we have seen
91 7.5 Measuring Productivity Current Darlings
- Economic Value Added
- Activity-Based Costing
- Options Analysis
- Performance-based Budgeting
92Economic Value Added
- Measures benefit by applying productivity gains
- ROI, NPV, Break-even
93Activity-Based Costing
- Determines the cost of supplying a service
- How much should I charge for X.500?
94Performance-based Budgeting
- Set up performance metrics
- Tie budget to those goals to evaluate the
effectiveness of the technology
95Options Analysis
- As we have seen
- Justify evolving to a client-server environment
96Ways of Measuring Profitability IW 2001-VIII-08,
survey of 200 IT Professionals
97Tracking Business Line Demands
- Whos doing what?
- Are trends developing?
- Can we measure Business Line profitability?
- Can we apportion network costs to Business Line?
- Are we making it pay?
118
98Do You Know Where Your BLs Are?
- Need to understand the business case first
- Then the Business Lines that drive the biz
- Then the data that the BLs need
- Then the network to support that
- Then the technology model
- Lastly, the bits and bytes
119
99Track Those Business Lines!
- Tie profitability back to Each BL
- The IT Infrastructure is the means to the end,
NOT the end - That end is PROFITABILITY
- Is the BL activity increasing, steady decreasing?
120
100Need to Cost Business Lines
- Can munge up ROI
- ROI not only good for projects, but for running
costs too - Economic Value Added (EVA...note overloading) is
new measure - Note there is NO measurable proof that IT is
correlated with profitability!!!!
121
101BL EVA (or at least TCO)
- Total Cost of Ownership is first step
- Done on PCs. Aberdeen Group found that the TCO is
about 10K US/year! - But you also need to know the EVA of the app.
What does it add to the bottom line?
122
102Positives and Negatives
- SHOW ME THE MONEY
- Strassmann bah humbug
- no relationship between IT investment and
profitability - Brynjolffson now starting to see it as we
understand the the economic
103TCO (LCC) for PCs (Gartner Group)
123
104How to Increase TCO (LCC)
- Make Business Lines more complex
- Costly maintenance
- Cost of upgrades
- Lack of Internal Standards
- Hardware and software costs
105How to Lower TCO
- Standardize on a Platform
- Purchase cheaper H/W
- Provide end-user training
- Use management tools (esp app mans)
106Can Measure Software
- Get its Function Point count
- Can size the software
- Charge off costs, profits against the FP size
- Same with all IT costs
124
107EVA (economic value added) is
- Companys net operating profit after deducting
taxes and cost of capital - Is the company makin er pay?
125
108(snooze time)
- Need to know the true cost of capital and how
much capital is tied up - Capital borrowed and equity
- loans out plus interest rate
- equity - 6 points more than prime (14 plus more
if you are in a risky business) - () Cost of capital is weighted average of both
126
109Tied Up Capital
- Add up worth of buildings, computers, networks,
etc etc etc - If you have a 20M budget for new products, add
that to your capital base. If it has a 5 year
life expectancy, deduct 5M per year from capital
127
110And the Envelope Please
- EVA Pretax-earnings - Capital x Cost-of-capital
- If it is positive, you are adding shareholder
value BUY - If negative, SELL
128
111So How Are Doing, EVA-wise?
129
Network World Master Series - June 11, 1998
112Benchmark Your Organization
- How is your spending relative to the rest of the
world? - Useful in making business cases
113Common Metrics
- Benefit/Cost Ratio
- ROI
- NPV
- IRR
- PM Scorecard
1147.6 Common Cost Problems
- Poor estimating
- Out-of-sequence starting of events
- Inadequate WBS
- No Management policy on reporting/control
- Poor work definition at low levels
- PHB crashing to make the bid
- Inadequate formal planning
115Mo Probs
- Poor comparison of actuals/planned costs
- Unforeseen technical problems
- Schedule delays requiring overtime/idle time
- Unforeseen material escalation factors
- Inflation
116Cost Overrun Causes
- Proposal Phase
- Failure to understand requirements
- Unrealistic appraisal of in-house abilities
- Underestimating time requirements
117Cost Overrun Causes
- Planning Phase
- Omissions
- Inaccuracy of WBS
- Misinterpretation of information
- Use of wrong estimating techniques
- Failure to identify major cost elements
- Failure to to Risk Assessment
118Cost Overrun Causes
- Negotiation Phase
- Settling too quickly
- Procurement ceiling costs
- Negotiation team that must win
119Cost Overrun Causes
- Contractual Phase
- Contractual discrepancies
- SOW different from RFP
- Proposal team different from project team
120Cost Overrun Causes
- Design Phase
- Accepting customer requests without man approval
- Problems in customer communications
- Problems in design review meetings
121Cost Overrun Causes
- Production Phase
- Excessive material costs
- Specifications not acceptable
- Manufacturing and engineering disagreement
122Chapter Seven Cost Management
- 2000 Edition
- 7.1 Resource Planning
- 7.2 Cost Estimating
- 7.3 Cost Budgeting
- 7.4 Cost Control
- Third Edition
- 7.1 Cost Estimating
- 7.2 Cost Budgeting
- 7.3 Cost Control