Title: Joint Implementation
1Joint Implementation Gas Flaring Reduction
Projects
- Alexandrina Platonova-Oquab
- Carbon Finance Unit, World Bank
2Presentation outline
- JI fundamentals
- Project cycle and methodologies
- Baselines Monitoring
- Flaring reduction under JI
- Opportunities Barriers in Russia
- Uncertainty on post-2012 period
3Joint Implementation fundamentals (1)
- Joint Implementation
- Generate emission reductions (ERUs) from
investments in developed (Annex B) countries - Two Tracks for JI
- JI Track 1
- Simplified procedure for fully eligible
countries - JI Track 2
- International verification of projects
4Joint Implementation fundamentals
(2)Participants
- Governments of investing and host countries
- Eligibility national rules
- Project approval by the Designated Focal Point
- Private Public companies
- Must be authorized by the government
- and for JI Track 2
- JI Supervisory Committee (JISC)
- International rules / verification
- Independent validators
- Determine conformity of projects with JI
requirements
5Joint Implementation fundamentals (3)Status
Rules
- JI Track 2
- Launched in October 2006
- JISC Track 2 guidelines available
- Baseline setting monitoring rules (incl.
guidance on additionality) - JI Project Design Document (PDD) forms approved
by COP/MOP2 - JISC administrative fees approved by COP/MOP2
- JI Track 1
- No rules available yet from Host Parties
- More relaxed rules ? / Adoption of Track 2
guidelines?
6JI Track 2 Project cycle
Preparation and review of the project
Project completion
Transfer of ERUs
Carbon asset due diligence
Eligibility requirements
Negotiation of project agreements
Possible review by JISC
- Determination by AIE
- PDD forms established by JISC
- Letter of Approval
- Baseline setting
- Publication of PDD
15 days
30 days
45 days
Periodic verification by AIE
Determination report by AIE
Possible review by JISC
7JI Track 2 Methodologies Baseline setting
monitoring (1)
- Key objective of JI (CDM) methodologies
- determine GHG emission reductions from a project
activity over time - Key elements of JI (CDM) methodologies
- determination of emissions in the relevant
reference scenario (baseline) and in the project
scenario - procedures to collect and use the relevant data
to calculate emission reductions (monitoring) - demonstration that the project reduces emissions
and is not the most likely scenario
(additionality) - JI projects may use approved CDM methodologies or
a new appropriated approach
8JI Track 2 Methodologies Baseline setting
monitoring (2)
Baseline (gas flaring)
- Main challenges
- Baselines are counterfactual/ hypothetical
- Additionality / environmental integrity
- Reasonable conservativeness
- Monitoring methodology
- Procedures to measure or to estimate project
emissions (incl. leakage) - Procedures to determine baseline emissions
(context data) - Data sources, quality control
Emission reductions
GHG emissions
Project emissions
Time
In addition to CO2 price, baseline is key for
determining financial impact of JI
9Examples of baseline methodologies for gas
flaring reduction projects
- Economic or financial analysis
- Baseline is the (time dependent) investment
alternative (incl. no investment) with the
highest IRR or the highest NPV or the lowest
costs (all risk adjusted) - Example Rang Dong project (Vietnam) - CDM
methodology AM0009 - Scenario or barrier analysis
- Baseline is the option facing the least amount of
barriers - Example Gas-to-Market project facing low prices
limited access to the transmission system - Control groups
- Baseline is common practice
- Example No incentive to reduce gas flaring leads
to the continuation of the current situation in
the country/region - Technology benchmark
- Baselines for specific circumstances
- Example Widespread non-compliance with legal or
regulatory requirements
10Flaring Reduction ProjectsRussias JI market
segment (1)
- Large opportunities in Russia
- 15 bcm of associated gas flared per year,
officially - Projects do not overcome the hurdle rate of
return - Regulatory institutional barriers for better
utilization of associated gas - Carbon finance could bring additional revenues
- Achievable annual reductions up to 2 MtCO2e per
project - Priced at 7/tCO2 the ERUs bring up to 70 M for
a project in 5 years for GHG-friendly projects
11Flaring Reduction ProjectsRussias JI market
segment (2)
- Barriers for JI projects in Russia
- Currently JI Track 2 procedure expected to be
used - National rules approval procedure for JI Track
2 not available yet - However, 3 from 9 submitted JI Track 2 projects
are in Russia - Uncertainty on forthcoming JI rules in Russia
- Any limitations on possible activities /sectors?
- Clear procedures for approval?
12Post-2012 uncertainties Timing for current JI
opportunities
- Carbon finance flow is now limited by 2008-2012
period - Progress of the international negotiations is key
- Opportunity window is narrowing
- Particularly, in the absence of national
procedures - Possible uncertainty mitigation
- Faster move on setting national JI rules in
Russia - Possible use of Green Investment Schemes
- On the project level
- Develop projects start operations in 2007-2008
13Useful References
- Websites on JI and CDM
- Website of the UNFCCC
- JI Track 2 Modalities Guidelines
http//ji.unfccc.int - CDM Gas Flaring Reduction Projects
http//cdm.unfccc.int/Projects (search by AM0009
AM0037) - Websites on oil and gas climate activities
- Methane emissions from oil and gas industry (US
EPA Natural Gas STAR) http//www.epa.gov/gasstar/
index.htm - GHG Protocol Initiative www.ghgprotocol.org
- GGFR Report 6 on gas flaring reductions under
the CDM www.worldbank.org/ggfr - API Compendium on GHG emissions
http//www.api.org/ehs/climate/
14www.carbonfinance.org aplatonova_at_worldbank.org