Uninterruptible Power Source UPS Status January 20, 2004 - PowerPoint PPT Presentation

1 / 11
About This Presentation
Title:

Uninterruptible Power Source UPS Status January 20, 2004

Description:

Cells, Bricks, and BMS. Yardney/Lithion R. Gitzendanner ... Yardney has a space-rated monitor equalizer board, but not a rad-hard version of ... – PowerPoint PPT presentation

Number of Views:50
Avg rating:3.0/5.0
Slides: 12
Provided by: Lockheed7
Category:

less

Transcript and Presenter's Notes

Title: Uninterruptible Power Source UPS Status January 20, 2004


1
Uninterruptible Power Source (UPS)
StatusJanuary 20, 2004
  • P. Nemeth/LM

2
Responsibilities
  • Cells, Bricks, and BMS
  • Yardney/Lithion R. Gitzendanner
  • Battery Casing, Electrical/Mechanical Integration
  • CSIST Jong-Ren Lee
  • Battery Charger
  • CRISA A. Posada
  • Customer/Subcontract Management
  • MIT F. Eppling and S. Ting
  • Technical Management M. Capell/MIT and G.
    Viertel/ETH
  • Subcontract Technical Monitor P. Nemeth/LM

3
CSP Functional Block Diagram
4
Battery Specifications
  • Consists of eight cells, Yardney NCP25-3
  • Nominal Voltage 8 X 3.6 V 28.8 V
  • Capacity 28 Ah
  • Operational Temperature Range -30 degC to 50
    degC
  • Capable of supplying 45A pulse at required
    voltage throughout mission profile
  • Battery will provide control power to CSP in
    event of loss of ISS power or communication
  • Watch-dog timer/control circuit
  • Normal Ramp down function
  • Quench monitoring
  • Initiation of quench, 45A pulse

5
Brick Layout
Mass estimate for brick 9kg Total weight budget
for UPS 212.5kg Additional weight savings from
Cutout on side panel Decrease flange width
6
Battery Management System
7
Progress
  • UPS Statement of Work baselined 5 March, 2003
  • Sole-Source Justification completed May 2003
  • Contract Awarded 23 June, 2003 to Yardney/Lithion
    for Cells, Bricks, and Battery Management System
    (BMS)
  • Cell/BMS Preliminary Design Review (PDR) - 25
    August, 2003 at Yardney/Lithion
  • Cell/BMS Critical Design Review (CDR) 13
    October 2003 at Yardney/Lithion

8
Milestone Schedule
  • Cell Qual Testing March to May 2004
  • Flight Cell Screening May to June 2004
  • BMS Qual/Screening April to May 2004
  • Delivery July 2004
  • PDR for Battery Casing _at_ CSIST December 2003 -
    Complete
  • CDR for Battery Casing _at_ CSIST March 2004
  • EDU required for support of Magnet Integration
    and Testing at SCL beginning February 2005

9
Complications from Cell/BMS CDR
  • Several components within the BMS were not
    Rad-hardened
  • Yardney has a space-rated monitor equalizer
    board, but not a rad-hard version of the
    Protection Board
  • Negotiations with Yardney have led to an
    agreement for a simplified protection board to
    include Short circuit protection, overcharge/
    discharge protection, and over-temperature
    protection
  • State of Charge function will be deleted (not
    required)

10
Overcharge Protection
  • The electronics will monitor individual cell
    voltages against a reference, when the voltage of
    any one cell exceeds a pre-set limit (currently
    4.29V 0.040V) a signal will be sent to the
    charger supply to terminate charging
  • This function will be implemented using the same
    signal wire that was originally designated for
    the PWM signal.
  • Signal is now a true over-voltage, safety
    warning, signal.
  • CRISA will have to adjust their charger supply to
    either
  • Maintain a maximum voltage of 32.8V 0.40V, or
  • Monitor the battery voltage independently and
    self-regulate the charge current to maintain a
    maximum battery voltage of 32.8V 0.40V.

11
Forward Work
  • Changes to BMS will likely result in a decrease
    in the size of the footprint
  • Existing BMS was longer than brick
  • Decrease in size of BMS should result in decrease
    of UPS package size
  • Weight savings
  • UPS package development on hold
  • Brick development will not be held up, BMS and
    bricks are now independent
  • Yardney to develop functional block diagram,
    schedule and parts list by 6 February
  • EDU required for magnet testing February 2005
Write a Comment
User Comments (0)
About PowerShow.com