Title: RICH Status as of April 5, 2000


1
RICH Status as of April 5, 2000
  • year-1 (CO2) gas system installed, calibrated and
    tested
  • replacement of a (non-critical) defective
    solenoid valve in mixing house on order
  • CO2 supply from gas pad close to complete
  • test rack in IR to be removed
  • cooling water plumbing finished and tested
  • all cabling done except on SE corner
  • SE waiting for LV crate
  • parts arrived for HP LV PS for FEE
  • 2 modified and tested by M.VanLith
  • 6 more to be assembled outside
  • 8 filter boards also to be modified
  • still waiting for parts for LP LV PS for pre-amps
    on East
  • due in mid-April