Title: DEX Publication Project
1- DEX Publication Project
- OASIS PLCS Telecon
- 27 November 2007
- Trine Hansen
2Status report
- This status report refers to DEX Publication
Project Status Report 28 October 2007
DEX_Publ_Proj_Status_Report_30_September_07_v2.do
c
3Overall Status (period August 07 October 07)
- The project has made good progress last period,
although progress is less than planned - The commitments of resources are still critical
for some activities re-commitment is needed - The funding situation is still un-clear for some
activities - Because of the resource situation the last
period, it looks unrealistic to meet the first
December milestone
4Overall Progress
- In total the project is estimated to be
approximately 10 weeks behind schedule - October status report
- Without any further delay and sufficient access
to resources the project may be completed this
year - November
- Final Task DEX WS 17-18 Dec. ? Ready for project
review 4 January 08 ? Ready for ballot Feb 08 - How to reduce/stop the delay
- Access to committed resources
5Resource situation Phasing deliverables
Resource situation There is an urgent need to
have a final commitment from all contributors of
the projects with respect to requested tasks and
resources Phasing deliverables Phasing of
deliverables was concluded last period
Completion of capabilities will be postponed to a
later phase.
6Events Sept Nov 07
- August 07 October 07
- 27 August 07 Steering Group telecon (Status)
- 30 August 07 OASIS TC telecon
- 7 September 07 Telecon. Agenda Phasing
deliverables. - 11 September 07 Steering Group telecon
(Proposing phasing of deliverables) - 14 September 07 Core team telecon
- 27 September 07 Steering Group telecon
- 1 October Face-to-face TC meeting in Oslo
- 2-3 October Task DEX harmonization workshop
(Oslo). - 12 October Core Team telecon. Agenda Status,
with focus on Templates - 15 October Core Team Telecon. Agenda DEXLib
Help section - November 07
- 12 Nov Core Team telecon. Agree issue resolution
process - 15 Nov Steering Group telecon
- 21 Nov Core Team Issue resolution telecon
- 21-23 Nov Task DEX harmonization WS
- 26 Nov Accetance Test DEXLib tool
7Project main activities
- The following slides report status and progress
for each main activity
8Activity 1 - Management
- Publication package sent to OASIS for comments
(this week) - Request for re-commitments
- Request sent out 17 Oct
- Replies
- LOGSA (25 Oct) Review completed
- DNV (14 Nov) Template review completed by 1st
Dec - FMV Replied today
- UK
- Aviation Maintenance DEX Verbally confirmed (by
Eurstep) resources for completion - Template updates List from TLSS project received
- BAE Systems No reply
- EPMT No reply
- Next Steering Group telecon 6 December 07
- Project Manager on vacation from 8 Dec 07 to 3
Jan 08
9Activity 2 - Core Team Activities
- This activity runs according to plan
10Activity 3 TOG Support Management
- Identifies OASIS requirements for having the DEXs
ready for publication - Completed
- Discuss procedures for handling request for
external support such as training and consultancy
services - Not started
- Requirements for tool support of future TOG
management activities will also be identified - Not started
11Activity 4 Check lists and Processes
- Completed checklists
- Templates
- Checklists not completed
- Reference data on-going
- DEX on-going
- Capabilities (established, but has to be updated)
- PLCS Information Pages in DEXLib
- Established but not completed
12Activity 5 DEXLib infrastructure
- This activity runs according to plan
- Consists of sub-activities
- Templates
- Acceptance test plan
- Longform generation
- Part 28 generation
- Business DEXs
- Business Objects
- Release environment
- Usage reporting tool
- General maintenance
- Configuration change management
- Configuration management of reference data
- Publication as standards
Acceptance test 26 Nov 07
13Activity 6 - DEXlib Help section
- PLCS Information pages in DEXLib
- Good progress in October
14Activity 7 Develop, review and update
templates
- Development of templates is on-going, but
progress is less than planned - Review of templates is on-going, but progress is
less than planned - There is still a lack of commitments for update
of templates - It seems unrealistic to have all templates
reviewed and updated by 1st December 07
15Activity 8 Develop, review and update
capabilities
16Activity 9 - Develop and harmonize DEXs
- Sept-Oct 07
- Good progress last period, but less than planned
(due to illness and access to key resources) - Approx. 1,5 month behind plan
- Nov 07
- Workshop 21-23 November
- Harmonization of mapping solutions finished
- Way forward
- Next (and last) workshop 17-18 Dec 07
- Output Checklists and recommendations
- Task DEX ready for project review 4 Jan 08
- Task DEX probably ready for ballot Feb 08
17Activity 10 - Review and update DEXs
- Task DEXs
- Sept-Oct 07
- Review part of harmonization activities
- Nov 07
- Updates of DEX starts, draft completed by 17 Dec
07 - Aviation Maintenance DEX
- Ready for review December 07
18Activity 11 Preparations for establishing
Implementers Forum
- This activity is not started.
19Activity 12 Final report
- This activity is not started.