Title: Track and manage
1Track and manage
2Track and manage progress
- When you manage a project, you need to monitor
the elements of the project triangle time,
money, and scope. Adjusting one of these elements
affects the other two. Events such as unexpected
delays, cost overruns, and resource changes can
cause problems in your schedule. - If you keep your project information up to date,
you can always see the latest status of the
project. That way, you can identify problems
early that might affect your project's success
and use Microsoft Project to find solutions. - The lessons in this section will show you how to
track and manage work on your project. Click
Begin lessons to get started.
3Lesson How do you track the actual progress on
tasks?
- Once you've set up your project and work has
begun, you can keep track of actual start and
finish dates, tasks' percentage of completion,
and actual work. Tracking actuals shows you how
changes affect other tasks and, ultimately, the
project's finish date. - When you've completed this lesson, you'll know
how to enter actual task information and see its
effects on the schedule.
4Check if tasks are progressing according to plan
- To keep your project on schedule, make sure that
tasks start and finish on schedule. The Tracking
Gantt view helps find trouble spots, tasks that
vary from the baseline plan. You can then adjust
task dependencies, reassign resources, or delete
some tasks to meet your deadlines. - The Tracking Gantt view pairs the current
schedule with the original schedule for each
task. When you've saved the project with a
baseline, but before you've entered actual data
on progress, the Tracking Gantt view shows tasks
with the baseline bars and the scheduled or
actual bars synchronized. -
- As you enter actuals, the top bar may move to
show a departure from plan. For example, if the
start date of "Inventory artifacts" moves by two
days and is over half complete at 55, the red
scheduled bar extends two days beyond the lower
baseline bar.
5How
- 1 On the View menu, click Tracking Gantt.
- 2 To view the variance fields, on the View menu,
point to Table, and then click Variance. - 3 If necessary, press TAB to see the variance
fields. - 4 On the View menu, point to Toolbars, and then
click Tracking. - 5 Update the progress of the tasks in your
project. - If the task has started as scheduled, click the
task, and then click Update as Scheduled . - If the task is not progressing as scheduled, in
the next lessons you'll learn how to enter actual
start and finish dates, enter the actual duration
of the task, or update a task's progress as a
percentage.
6(No Transcript)
7(No Transcript)
8Note
- You must have saved a baseline in order to
have variance information.
9Enter actual start and finish dates for a task
- Tasks that start or finish late can throw an
entire project off schedule by delaying the start
or finish dates of related tasks. Tasks that
start or finish early can free resources to work
on other tasks that are behind schedule.
Microsoft Project uses the actual values you
enter to reschedule the remaining portions of
your project.
10How
- 1 On the View menu, click Gantt Chart.
- 2 On the View menu, point to Toolbars, and then
click Tracking if it is not already selected. - 3 In the Task Name field, select the tasks you
want to update. To select nonadjacent tasks, hold
down CTRL, and then click the tasks. To select
adjacent tasks, hold down SHIFT, and then click
the first and last task to update. - 4 Click Update Tasks .
- 5 Under Actual, type or select a date in the
Start or Finish box. - If you enter a finish date, make sure that the
task is 100 complete Microsoft Project will
assume the date is correct and reschedule tasks
accordingly. - 6 Click OK.
- Note Entering an actual start date or actual
finish date for a task changes the corresponding
scheduled date for that task. Baseline dates,
however, are not affected.
11Enter the actual duration of a task
- If you know the number of days a task has been in
progress and if it is progressing as planned, you
can track progress by entering the duration that
the resource has been working on the task. - When you enter the actual duration of a task,
Microsoft Project updates the actual start date,
the task's percentage of completion, and the
duration of the task remaining in the schedule.
12How
- 1 On the View menu, click Gantt Chart.
- 2 In the Task Name field, click the task for
which you want to enter the actual duration. - 3 On the Tools menu, point to Tracking, and then
click Update Tasks. - 4 In the Actual dur box, type the actual duration
of the task. - 5 Click OK.
13- Tip If you think the task is going to be
finished sooner or later than originally
scheduled, you can enter a new value in the
Remaining dur box. - Note If you enter an actual duration longer
than or equal to the scheduled duration, the task
becomes 100 complete, and the scheduled duration
then equals the actual duration.
14Update a task's progress as a percentage
- You can indicate how much progress has been made
on a task by entering the percentage of the task
duration that is complete. For relatively short
tasks, it may not be worthwhile to track progress
in such detail but for long tasks, indicating
the percentage of completion for the task helps
you track actual progress against the baseline
plan.
15How
- 1 On the View menu, click Gantt Chart
- 2In the Task Name field, click the task for which
you want to update progress. - 3Click Task Information , and then click the
General tab. - 4In the Percent complete box, type a whole number
between 0 and 100. - 5Click OK.
16- Notes
- Microsoft Project calculates the summary task's
percentage of completion based on the progress of
its subtasks. You can also manually enter the
summary task's percentage of completion, which
Microsoft Project will use to calculate the
percentage of completion for its subtasks. - By default, Microsoft Project indicates the
task's percentage of completion as a thin, black
line drawn horizontally through the middle of
each Gantt bar on the Gantt Chart. - When you mark a task as 100 complete, Microsoft
Project displays a check mark in the Indicators
field. - Tip
- You can use the buttons on the Tracking toolbar
to update progress on a task and to perform other
tracking activities. To view the Tracking
toolbar, point to Toolbars on the View menu, and
then click Tracking.
17Update actual work by time period
- You can track actual work using the timephased
fields in Microsoft Project. Tracking using the
timephased fields helps you keep your project up
to date periodically because you can enter
information for a particular day in your
schedule. - 1 On the View menu, click Task Usage.
- 2 On the Format menu, point to Details, and then
click Actual Work. - 3 In the timephased portion of the view, in the
Actual Work field, type the actual work of each
assigned resource.
18Tips
- If it makes no difference which of the resources
assigned to a task performs the work, in the
Actual Work field for the task, type a value for
the combined work done on the task by all the
resources. Microsoft Project divides the actual
and remaining work among the resources based on
when they are scheduled on the task and the
remaining work for each assignment. - You can also type actual work for a week at a
time. On the View menu, click Zoom, and click 1
month to display the timescale in weekly
increments. Then, type actual work for the week
in the Actual Work field.
19See if tasks have more or less work than planned
- If you're managing resource assignments in your
project, you need to make sure resources complete
tasks in the time scheduled. If you've saved a
baseline for your project, you can check the
variance information. - Variances in your schedule can be good as well as
bad, depending on the type and severity of the
variance. A task with less work than planned, for
example, is usually good news but may indicate
that your resources are not allocated efficiently.
20How
- 1 On the View menu, click Gantt Chart.
- 2 On the View menu, point to Table, and then
click Work. If necessary, press TAB to view the
Actual field. - 3 Compare the values in the Work, Baseline, and
Actual fields. The values in the Variance field
show the difference between the work scheduled
and the originally planned amount of work saved
in the baseline.
21Compare actual task information to the baseline
- When you save a baseline plan and then update
your schedule, you can compare the baseline plan
to your actual progress to identify variances.
Variances alert you to the areas of the project
that are not going as planned. - To keep your project on schedule, make sure that
tasks start and finish on time as much as
possible. Every project has variances, but it is
important to find tasks that vary from the
baseline plan as soon as possible so you can
adjust task dependencies, reassign resources, or
delete some tasks to meet your deadlines.
22How
- 1 On the View menu, click Tracking Gantt. The
Tracking Gantt view shows task variances
graphically, making it easier to see variances in
your schedule. - 2 On the View menu, point to Table, and then
click Variance. If necessary, press TAB to view
the variance fields. - Note You must update tasks' actual start and
finish dates, actual work values, or actual
durations before variances will appear. Microsoft
Project calculates the other task information
based on the information you enter.
23Track Work
24Enter the total actual work done by a resource
- If you schedule tasks based on the availability
of resources, track the progress of your tasks by
updating the work completed on a task. Using this
approach, you can track the work that each
resource is performing. - When you update the actual work a resource has
done on a task, Microsoft Project automatically
calculates the work remaining by subtracting the
actual work done by the resource from the total
work the resource is scheduled to do.
25How
- 1 On the View menu, click Task Usage.
- 2 On the View menu, point to Table, and then
click Work. In the Task Name field, both task and
resource names are listed. If necessary, press
TAB to view the Actual field. - 3 In the Actual field for each resource, type the
updated work value and the duration abbreviation
for the actual work of each assigned resource. - Tip If it makes no difference which resource
assigned to a task performs the work, then type a
value for the combined work done on the task by
all the resources in the Actual field for the
task. Microsoft Project divides the actual and
remaining work among the resources based on when
they are scheduled on the task and the remaining
work for each assignment.
26Update a resource's actual work by time period
- You can track actual work for individual
resources using the timephased fields in
Microsoft Project. Tracking resources' actual
work by using the timephased fields can help you
keep your project up to date by time period
because you can enter information for a
particular day (or other time period) in your
schedule. - 1 On the View menu, click Resource Usage.
- 2 On the View menu, point to Table, and then
click Work. - 3 On the Format menu, point to Details, and then
click Actual Work. - 4 In the Act. Work field for the resource, type
the actual work value.
27See the variance between a resource's planned and
actual work
- If you schedule tasks based on the availability
of resources and you track actual work, you can
analyze how much total work a resource is
accomplishing by looking at the variance between
the baseline work and actual work. You can also
compare those figures to the baseline work and
actual work over time to see how the resource's
work is progressing in greater detail.
28How
- 1 On the View menu, click Resource Usage.
- 2 On the View menu, point to Table, and then
click Work. If necessary, press TAB to view the
Baseline and Actual fields. - 3 Compare the values in the Baseline and Actual
fields for each resource. - 4 Make sure the Work and Act. Work fields are
displayed in the the timescaled portion of the
view. On the Format menu, point to Details, and
then click Work if it's not already selected. On
the Format menu, point to Details, and then click
Actual Work, if it's not already selected, to
display it as well. - 5 In the timescale portion of the view, compare
the Work and Act. Work fields for a daily summary
of each resource's work.
29Track Cost
30Enter actual task costs manually
- Microsoft Project automatically updates actual
costs as a task progresses based on the task's
accrual method and the rates of the resources.
But if you want to track actual costs separately
from the actual work on a task, you can enter
costs manually instead. - To update costs manually you must first turn off
the automatic updating of actual costs and then
enter your own actual cost for an assignment
after the remaining work is zero.
31How
- 1 On the Tools menu, click Options, and then
click the Calculation tab. - 2 Clear the Actual costs are always calculated by
Microsoft Project check box. - 3 Click OK.
- 4 On the View menu, click Task Usage.
- 5 On the View menu, point to Table, and then
click Tracking. - 6 If necessary, press TAB to view the Act. Cost
field. - 7 In the Act. Cost field, type the actual cost
for the assignment whose costs you are updating.
32Tips
- You can set the fixed cost for a task to accrue
at the beginning or the completion of a task or
to be prorated for the length of the task. Click
Gantt Chart on the View menu. On the View menu,
point to Table, and then click Cost. In the Fixed
Cost Accrual field, type or select the accrual
method you want. - In addition to a standard rate, sometimes
assignment costs include a fixed amount charged
for a resource each time the resource is assigned
to a task, such as equipment costs, setup
charges, delivery, or rental fees. You can enter
this per-use cost by clicking Resource Sheet on
the View menu, and then typing a new cost in the
Cost/Use field for the resource whose per-use
cost you want to change.
33Update actual costs by time period
- You can track actual costs using the timephased
fields in Microsoft Project. Tracking actual
costs using the timephased fields can help you
keep your project up to date by time period
because you can enter information for a
particular day or other time period in your
schedule.
34Balance Workload
35Find overallocated resources and their task
assignments
- People and equipment are overallocated when they
are assigned more work than they can complete in
their scheduled working hours. Before you can
resolve overallocations, you must determine which
resources are overallocated, when they are
overallocated, and what tasks they are assigned
to at those times. To resolve the problem, the
people and equipment must be allocated
differently or the task must be rescheduled to a
time when the resource is available.
36How
- 1 On the View menu, click Resource Usage. The
Resource Usage view shows the total hours the
resource is working, the total hours the resource
is working on each task, and the hours worked per
time period on the timescale. - Resources with no tasks yet assigned do not have
tasks listed under their names. - Tasks with no resources assigned are listed under
Unassigned in the Resource Name field. - 2 On the Project menu, point to Filtered for and
then click Overallocated Resources. Any work
resources that are overallocated are displayed
and highlighted.
37Tips
- If you see number signs () in the timescale
portion of the Resource Usage view, the columns
in the timescale are not wide enough to display
the information. To change the width of the
columns, click Timescale on the Format menu, and
then increase the value in the Size box. - You can see how much of a resource's work is
allocated to particular tasks and per time
period. On the Format menu, click Detail Styles.
Click the Usage Details tab and in the Available
fields list, click Percent Allocation, and then
click Show.
38Reduce a resource's work
- After you've assigned a resource to a task, you
can change the total work values for the
resource's work on the task or change work values
for a specific time period when the resource
works on the task. Tailoring work values this way
can make your schedule more accurate at a finer
level of detail. - 1 On the View menu, click Task Usage. Resources
are grouped under the tasks they are assigned to. - 2 In the table (left) portion of the view, enter
a new value in the Work field to change the total
work value for an assignment. - Tip
- You can also use the Resource Usage view to see
and edit work values for tasks grouped under the
resources are assigned to them. On the View menu,
click Resource Usage. - Note You can also change the individual work
values (or hours) for the assigned resources on
the timescale portion of the view. -
39Reassign work to another resource
- If you have tried to resolve a resource
overallocation using other methods and the
overallocation persists, it may be time to
reassign the task to another resource with more
time. This is an alternate method of manually
leveling your schedule by reassigning work rather
than delaying work.
40How
- 1 On the View menu, click Resource Usage.
- 2 On the Format menu, point to Details, and then
click Overallocation. - 3 Look at the timescale on the right and, for
each highlighted overallocation, examine the
availability of other resources on that day. - 4 Click the ID field to select the entire row of
the task you need to reassign. - 5 Drag the task to the resource that you want to
reassign it to.
41Delay a task
- A simple way to resolve a resource overallocation
is to delay a task assigned to the resource until
the resource has time to work on it. You can add
delay to a task, check the effect on the
resource's allocation, and then adjust the delay
further if necessary. - Delaying a task also delays the start dates of
its successors and can affect the finish date of
your schedule. To avoid this, delay tasks with
free slack first (noncritical tasks) and only
delay them up to the amount of slack that is
available for each task. Experiment with adding
delay to different tasks to see the effect on
your schedule.
42How
- 1 On the View menu, click More Views.
- 2 In the Views list, click Resource Allocation,
and then click Apply. - In the timephased portion on the top right,
overallocation for a resource is displayed in
red. - In the bar chart below, slack for tasks to which
the resource is assigned appears graphically as a
thin slack bar adjoining the regular Gantt bar. - 3 In the Resource Name field in the top left
portion of the view, click the resource name for
the overallocated resource with a task you want
to delay. - 4 In the Leveling Delay field (bottom left
portion of the view) for the task you want to
delay, type the amount of time that you want the
task to be delayed. To ensure that successor
tasks are not affected, do not enter more lag
than the amount of free slack for that task. - 5 To return to a single view, on the Window menu,
click Remove Split.
43Change a resource's working days and hours
- The project calendar designates the default work
schedule for the project, but you can create a
resource calendar to indicate work hours,
vacations, leaves of absence, and sick time for
individual resources.
44How
- 1 On the Tools menu, click Change Working Time.
- 2 In the For box, click the resource whose
calendar you want to change. - 3 On the calendar, select the days you want to
change. To change a day of the week for the
entire calendar, select the day at the top of the
calendar. - 4 Click Use default, Nonworking time, or
Nondefault working time. - 5 If you clicked Nondefault working time in step
4, type the times you want work to start in the
From boxes and the times you want work to end in
the To boxes. - 6 Click OK.
45(No Transcript)
46How
- 1 Microsoft Project automatically updates actual
costs as a task progresses based on the accrual
method you set. You must first turn off the
automatic updating of actual costs to edit actual
costs. On the Tools menu, click Options, and then
click the Calculation tab. - 2 Clear the Actual costs are always calculated by
Microsoft Project check box. - 3 Click OK.
- 4 On the View menu, click Task Usage.
- 5 On the View menu, point to Table, and then
click Cost. - 6 On the Format menu, point to Details, and then
click Cost. - 7 On the Format menu, point to Details, and then
click Actual Cost. - 8 To enter actual cost values for a task, select
a day or other time period in the timescale
portion of the view, and then type a value into
the Act. cost field for the task. - To enter actual values for a resource, select a
day or other time period in the timescale portion
of the view, and then type a value into the Act.
cost field for the resource.
47Tip
- You can enter actuals in other time increments,
such as weeks. On the View menu, click Zoom, and
click the increment you want.
48See if tasks cost more or less than budgeted
- If you assign fixed costs to tasks or specify
wages for resources, you may want to see tasks
that cost more than budgeted. By creating a
budget using a baseline plan and closely tracking
your project costs, you can catch cost overruns
early and adjust either your schedule or your
budget accordingly. - Microsoft Project calculates the cost of each
resource's work, the total cost for each task and
resource, and the total project cost. These costs
are considered scheduled or projected costs,
which reflect the latest cost picture as the
project progresses.
49How
- 1 On the View menu, click Gantt Chart.
- 2 On the View menu, point to Table, and then
click Cost. If necessary, press TAB to view the
Total Cost and Baseline fields. - 3 Compare the values in the Total Cost and
Baseline fields. For the cost variance, look at
the value in the Variance field.
50Tips
- To see the total cost, baseline, and variance
information for the entire project, you can
display the project summary task. On the Tools
menu, click Options, and then click the View tab.
Under Outline options, select the Project summary
task check box, and then click OK. - You can view the resources assigned to a task and
the resource costs related to that task. On the
View menu, click Task Usage. On the View menu,
point to Table, and then click Cost. Drag the
divider bar to the right and compare the values
in the Total Cost, Baseline, Actual, and
Remaining fields for the resources assigned to
that task.
51See the total project costs
- You can view your project's current, baseline,
actual, and remaining costs to see whether you're
staying within your budget. These costs are
updated each time Microsoft Project recalculates
your project. - 1On the Project menu, click Project
Information.2Click Statistics. The current,
baseline, actual, and remaining costs are
displayed in the Costs column.
52Analyze costs with the Earned Value table
- When you want to compare your expected progress
with the actual progress to date, you can use the
Earned Value table. It compares, in terms of
costs, each task's baseline schedule with the
actual schedule. - You can also use the Earned Value table to
forecast whether the task will finish under or
over budget based on the cost incurred while the
task is in progress. For example, if a task is
50 complete and the actual cost incurred to date
is 200, you can see if 200 is more than, less
than, or equal to 50 of the baseline (or
budgeted) cost. The VAC field displays the
variance at completion between baseline cost and
scheduled cost for a task.
53How
- 1 On the View menu, click Gantt Chart.
- 2 On the View menu, point to Table, and then
click More Tables. - 3 In the Tables list, click Earned Value, and
then click Apply. - 4 Drag the divider bar to the right to display
all of the Earned Value table fields. The values
are calculated based on the actual work and costs
up through and including the current date. To
change the calculation date, on the Project menu,
click Project Information. In the Status date
box, type the date you want to use, and then
click OK.
54Tips
- Move the mouse pointer over a field name to get a
description of the field for example, position
the pointer over the VAC field and click Help on
VAC for a description of the field. - In the Task Usage view, you can view earned value
data over time periods such as daily, weekly,
monthly, quarterly, or yearly. On the Format
menu, click Detail Styles, and then click the
Usage Details tab. In the Available fields list,
hold down CTRL, click the earned value fields you
want to display (such as ACWP, BCWP, CV, or SV),
and then click Show. Double-click the timescale
to change the time periods that you see. - To see cost variances for the entire project, you
can display the project summary task. On the
Tools menu, click Options. Click the View tab and
under Outline options, select the Project summary
task check box.