Track and manage - PowerPoint PPT Presentation

1 / 54
About This Presentation
Title:

Track and manage

Description:

... If you think the task is going to be finished sooner or later ... position the pointer over the VAC field and click Help on VAC for a description of the field. ... – PowerPoint PPT presentation

Number of Views:28
Avg rating:3.0/5.0
Slides: 55
Provided by: perdanaFs
Category:

less

Transcript and Presenter's Notes

Title: Track and manage


1
Track and manage
2
Track and manage progress
  • When you manage a project, you need to monitor
    the elements of the project triangle time,
    money, and scope. Adjusting one of these elements
    affects the other two. Events such as unexpected
    delays, cost overruns, and resource changes can
    cause problems in your schedule.
  • If you keep your project information up to date,
    you can always see the latest status of the
    project. That way, you can identify problems
    early that might affect your project's success
    and use Microsoft Project to find solutions.
  • The lessons in this section will show you how to
    track and manage work on your project. Click
    Begin lessons to get started.

3
Lesson How do you track the actual progress on
tasks?
  • Once you've set up your project and work has
    begun, you can keep track of actual start and
    finish dates, tasks' percentage of completion,
    and actual work. Tracking actuals shows you how
    changes affect other tasks and, ultimately, the
    project's finish date.
  • When you've completed this lesson, you'll know
    how to enter actual task information and see its
    effects on the schedule.

4
Check if tasks are progressing according to plan
  • To keep your project on schedule, make sure that
    tasks start and finish on schedule. The Tracking
    Gantt view helps find trouble spots, tasks that
    vary from the baseline plan. You can then adjust
    task dependencies, reassign resources, or delete
    some tasks to meet your deadlines.
  • The Tracking Gantt view pairs the current
    schedule with the original schedule for each
    task. When you've saved the project with a
    baseline, but before you've entered actual data
    on progress, the Tracking Gantt view shows tasks
    with the baseline bars and the scheduled or
    actual bars synchronized.
  • As you enter actuals, the top bar may move to
    show a departure from plan. For example, if the
    start date of "Inventory artifacts" moves by two
    days and is over half complete at 55, the red
    scheduled bar extends two days beyond the lower
    baseline bar.

5
How
  • 1 On the View menu, click Tracking Gantt.
  • 2 To view the variance fields, on the View menu,
    point to Table, and then click Variance.
  • 3 If necessary, press TAB to see the variance
    fields.
  • 4 On the View menu, point to Toolbars, and then
    click Tracking.
  • 5 Update the progress of the tasks in your
    project.
  • If the task has started as scheduled, click the
    task, and then click Update as Scheduled .
  • If the task is not progressing as scheduled, in
    the next lessons you'll learn how to enter actual
    start and finish dates, enter the actual duration
    of the task, or update a task's progress as a
    percentage.

6
(No Transcript)
7
(No Transcript)
8
Note
  •    You must have saved a baseline in order to
    have variance information.

9
Enter actual start and finish dates for a task
  • Tasks that start or finish late can throw an
    entire project off schedule by delaying the start
    or finish dates of related tasks. Tasks that
    start or finish early can free resources to work
    on other tasks that are behind schedule.
    Microsoft Project uses the actual values you
    enter to reschedule the remaining portions of
    your project.

10
How
  • 1 On the View menu, click Gantt Chart.
  • 2 On the View menu, point to Toolbars, and then
    click Tracking if it is not already selected.
  • 3 In the Task Name field, select the tasks you
    want to update. To select nonadjacent tasks, hold
    down CTRL, and then click the tasks. To select
    adjacent tasks, hold down SHIFT, and then click
    the first and last task to update.
  • 4 Click Update Tasks .
  • 5 Under Actual, type or select a date in the
    Start or Finish box.
  • If you enter a finish date, make sure that the
    task is 100 complete Microsoft Project will
    assume the date is correct and reschedule tasks
    accordingly.
  • 6 Click OK.
  • Note   Entering an actual start date or actual
    finish date for a task changes the corresponding
    scheduled date for that task. Baseline dates,
    however, are not affected.

11
Enter the actual duration of a task
  • If you know the number of days a task has been in
    progress and if it is progressing as planned, you
    can track progress by entering the duration that
    the resource has been working on the task.
  • When you enter the actual duration of a task,
    Microsoft Project updates the actual start date,
    the task's percentage of completion, and the
    duration of the task remaining in the schedule.

12
How
  • 1 On the View menu, click Gantt Chart.
  • 2 In the Task Name field, click the task for
    which you want to enter the actual duration.
  • 3 On the Tools menu, point to Tracking, and then
    click Update Tasks.
  • 4 In the Actual dur box, type the actual duration
    of the task.
  • 5 Click OK.

13
  • Tip   If you think the task is going to be
    finished sooner or later than originally
    scheduled, you can enter a new value in the
    Remaining dur box.
  • Note   If you enter an actual duration longer
    than or equal to the scheduled duration, the task
    becomes 100 complete, and the scheduled duration
    then equals the actual duration.

14
Update a task's progress as a percentage
  • You can indicate how much progress has been made
    on a task by entering the percentage of the task
    duration that is complete. For relatively short
    tasks, it may not be worthwhile to track progress
    in such detail but for long tasks, indicating
    the percentage of completion for the task helps
    you track actual progress against the baseline
    plan.

15
How
  • 1 On the View menu, click Gantt Chart
  • 2In the Task Name field, click the task for which
    you want to update progress.
  • 3Click Task Information , and then click the
    General tab.
  • 4In the Percent complete box, type a whole number
    between 0 and 100.
  • 5Click OK.

16
  • Notes
  • Microsoft Project calculates the summary task's
    percentage of completion based on the progress of
    its subtasks. You can also manually enter the
    summary task's percentage of completion, which
    Microsoft Project will use to calculate the
    percentage of completion for its subtasks.
  • By default, Microsoft Project indicates the
    task's percentage of completion as a thin, black
    line drawn horizontally through the middle of
    each Gantt bar on the Gantt Chart.
  • When you mark a task as 100 complete, Microsoft
    Project displays a check mark in the Indicators
    field.
  • Tip  
  • You can use the buttons on the Tracking toolbar
    to update progress on a task and to perform other
    tracking activities. To view the Tracking
    toolbar, point to Toolbars on the View menu, and
    then click Tracking.

17
Update actual work by time period
  • You can track actual work using the timephased
    fields in Microsoft Project. Tracking using the
    timephased fields helps you keep your project up
    to date periodically because you can enter
    information for a particular day in your
    schedule.
  • 1 On the View menu, click Task Usage.
  • 2 On the Format menu, point to Details, and then
    click Actual Work.
  • 3 In the timephased portion of the view, in the
    Actual Work field, type the actual work of each
    assigned resource.

18
Tips
  • If it makes no difference which of the resources
    assigned to a task performs the work, in the
    Actual Work field for the task, type a value for
    the combined work done on the task by all the
    resources. Microsoft Project divides the actual
    and remaining work among the resources based on
    when they are scheduled on the task and the
    remaining work for each assignment.
  • You can also type actual work for a week at a
    time. On the View menu, click Zoom, and click 1
    month to display the timescale in weekly
    increments. Then, type actual work for the week
    in the Actual Work field.

19
See if tasks have more or less work than planned
  • If you're managing resource assignments in your
    project, you need to make sure resources complete
    tasks in the time scheduled. If you've saved a
    baseline for your project, you can check the
    variance information.
  • Variances in your schedule can be good as well as
    bad, depending on the type and severity of the
    variance. A task with less work than planned, for
    example, is usually good news but may indicate
    that your resources are not allocated efficiently.

20
How
  • 1 On the View menu, click Gantt Chart.
  • 2 On the View menu, point to Table, and then
    click Work. If necessary, press TAB to view the
    Actual field.
  • 3 Compare the values in the Work, Baseline, and
    Actual fields. The values in the Variance field
    show the difference between the work scheduled
    and the originally planned amount of work saved
    in the baseline.

21
Compare actual task information to the baseline
  • When you save a baseline plan and then update
    your schedule, you can compare the baseline plan
    to your actual progress to identify variances.
    Variances alert you to the areas of the project
    that are not going as planned.
  • To keep your project on schedule, make sure that
    tasks start and finish on time as much as
    possible. Every project has variances, but it is
    important to find tasks that vary from the
    baseline plan as soon as possible so you can
    adjust task dependencies, reassign resources, or
    delete some tasks to meet your deadlines.

22
How
  • 1 On the View menu, click Tracking Gantt. The
    Tracking Gantt view shows task variances
    graphically, making it easier to see variances in
    your schedule.
  • 2 On the View menu, point to Table, and then
    click Variance. If necessary, press TAB to view
    the variance fields.
  • Note   You must update tasks' actual start and
    finish dates, actual work values, or actual
    durations before variances will appear. Microsoft
    Project calculates the other task information
    based on the information you enter.

23
Track Work
24
Enter the total actual work done by a resource
  • If you schedule tasks based on the availability
    of resources, track the progress of your tasks by
    updating the work completed on a task. Using this
    approach, you can track the work that each
    resource is performing.
  • When you update the actual work a resource has
    done on a task, Microsoft Project automatically
    calculates the work remaining by subtracting the
    actual work done by the resource from the total
    work the resource is scheduled to do.

25
How
  • 1 On the View menu, click Task Usage.
  • 2 On the View menu, point to Table, and then
    click Work. In the Task Name field, both task and
    resource names are listed. If necessary, press
    TAB to view the Actual field.
  • 3 In the Actual field for each resource, type the
    updated work value and the duration abbreviation
    for the actual work of each assigned resource.
  • Tip   If it makes no difference which resource
    assigned to a task performs the work, then type a
    value for the combined work done on the task by
    all the resources in the Actual field for the
    task. Microsoft Project divides the actual and
    remaining work among the resources based on when
    they are scheduled on the task and the remaining
    work for each assignment.

26
Update a resource's actual work by time period
  • You can track actual work for individual
    resources using the timephased fields in
    Microsoft Project. Tracking resources' actual
    work by using the timephased fields can help you
    keep your project up to date by time period
    because you can enter information for a
    particular day (or other time period) in your
    schedule.
  • 1 On the View menu, click Resource Usage.
  • 2 On the View menu, point to Table, and then
    click Work.
  • 3 On the Format menu, point to Details, and then
    click Actual Work.
  • 4 In the Act. Work field for the resource, type
    the actual work value.

27
See the variance between a resource's planned and
actual work
  • If you schedule tasks based on the availability
    of resources and you track actual work, you can
    analyze how much total work a resource is
    accomplishing by looking at the variance between
    the baseline work and actual work. You can also
    compare those figures to the baseline work and
    actual work over time to see how the resource's
    work is progressing in greater detail.

28
How
  • 1 On the View menu, click Resource Usage.
  • 2 On the View menu, point to Table, and then
    click Work. If necessary, press TAB to view the
    Baseline and Actual fields.
  • 3 Compare the values in the Baseline and Actual
    fields for each resource.
  • 4 Make sure the Work and Act. Work fields are
    displayed in the the timescaled portion of the
    view. On the Format menu, point to Details, and
    then click Work if it's not already selected. On
    the Format menu, point to Details, and then click
    Actual Work, if it's not already selected, to
    display it as well.
  • 5 In the timescale portion of the view, compare
    the Work and Act. Work fields for a daily summary
    of each resource's work.

29
Track Cost
30
Enter actual task costs manually
  • Microsoft Project automatically updates actual
    costs as a task progresses based on the task's
    accrual method and the rates of the resources.
    But if you want to track actual costs separately
    from the actual work on a task, you can enter
    costs manually instead.
  • To update costs manually you must first turn off
    the automatic updating of actual costs and then
    enter your own actual cost for an assignment
    after the remaining work is zero.

31
How
  • 1 On the Tools menu, click Options, and then
    click the Calculation tab.
  • 2 Clear the Actual costs are always calculated by
    Microsoft Project check box.
  • 3 Click OK.
  • 4 On the View menu, click Task Usage.
  • 5 On the View menu, point to Table, and then
    click Tracking.
  • 6 If necessary, press TAB to view the Act. Cost
    field.
  • 7 In the Act. Cost field, type the actual cost
    for the assignment whose costs you are updating.

32
Tips
  • You can set the fixed cost for a task to accrue
    at the beginning or the completion of a task or
    to be prorated for the length of the task. Click
    Gantt Chart on the View menu. On the View menu,
    point to Table, and then click Cost. In the Fixed
    Cost Accrual field, type or select the accrual
    method you want.
  • In addition to a standard rate, sometimes
    assignment costs include a fixed amount charged
    for a resource each time the resource is assigned
    to a task, such as equipment costs, setup
    charges, delivery, or rental fees. You can enter
    this per-use cost by clicking Resource Sheet on
    the View menu, and then typing a new cost in the
    Cost/Use field for the resource whose per-use
    cost you want to change.

33
Update actual costs by time period
  • You can track actual costs using the timephased
    fields in Microsoft Project. Tracking actual
    costs using the timephased fields can help you
    keep your project up to date by time period
    because you can enter information for a
    particular day or other time period in your
    schedule.

34
Balance Workload
35
Find overallocated resources and their task
assignments
  • People and equipment are overallocated when they
    are assigned more work than they can complete in
    their scheduled working hours. Before you can
    resolve overallocations, you must determine which
    resources are overallocated, when they are
    overallocated, and what tasks they are assigned
    to at those times. To resolve the problem, the
    people and equipment must be allocated
    differently or the task must be rescheduled to a
    time when the resource is available.

36
How
  • 1 On the View menu, click Resource Usage. The
    Resource Usage view shows the total hours the
    resource is working, the total hours the resource
    is working on each task, and the hours worked per
    time period on the timescale.
  • Resources with no tasks yet assigned do not have
    tasks listed under their names.
  • Tasks with no resources assigned are listed under
    Unassigned in the Resource Name field.
  • 2 On the Project menu, point to Filtered for and
    then click Overallocated Resources. Any work
    resources that are overallocated are displayed
    and highlighted.

37
Tips
  • If you see number signs () in the timescale
    portion of the Resource Usage view, the columns
    in the timescale are not wide enough to display
    the information. To change the width of the
    columns, click Timescale on the Format menu, and
    then increase the value in the Size box.
  • You can see how much of a resource's work is
    allocated to particular tasks and per time
    period. On the Format menu, click Detail Styles.
    Click the Usage Details tab and in the Available
    fields list, click Percent Allocation, and then
    click Show.

38
Reduce a resource's work
  • After you've assigned a resource to a task, you
    can change the total work values for the
    resource's work on the task or change work values
    for a specific time period when the resource
    works on the task. Tailoring work values this way
    can make your schedule more accurate at a finer
    level of detail.
  • 1 On the View menu, click Task Usage. Resources
    are grouped under the tasks they are assigned to.
  • 2 In the table (left) portion of the view, enter
    a new value in the Work field to change the total
    work value for an assignment.
  • Tip  
  • You can also use the Resource Usage view to see
    and edit work values for tasks grouped under the
    resources are assigned to them. On the View menu,
    click Resource Usage.
  • Note   You can also change the individual work
    values (or hours) for the assigned resources on
    the timescale portion of the view.
  •  

39
Reassign work to another resource
  • If you have tried to resolve a resource
    overallocation using other methods and the
    overallocation persists, it may be time to
    reassign the task to another resource with more
    time. This is an alternate method of manually
    leveling your schedule by reassigning work rather
    than delaying work.

40
How
  • 1 On the View menu, click Resource Usage.
  • 2 On the Format menu, point to Details, and then
    click Overallocation.
  • 3 Look at the timescale on the right and, for
    each highlighted overallocation, examine the
    availability of other resources on that day.
  • 4 Click the ID field to select the entire row of
    the task you need to reassign.
  • 5 Drag the task to the resource that you want to
    reassign it to.

41
Delay a task
  • A simple way to resolve a resource overallocation
    is to delay a task assigned to the resource until
    the resource has time to work on it. You can add
    delay to a task, check the effect on the
    resource's allocation, and then adjust the delay
    further if necessary.
  • Delaying a task also delays the start dates of
    its successors and can affect the finish date of
    your schedule. To avoid this, delay tasks with
    free slack first (noncritical tasks) and only
    delay them up to the amount of slack that is
    available for each task. Experiment with adding
    delay to different tasks to see the effect on
    your schedule.

42
How
  • 1 On the View menu, click More Views.
  • 2 In the Views list, click Resource Allocation,
    and then click Apply.
  • In the timephased portion on the top right,
    overallocation for a resource is displayed in
    red.
  • In the bar chart below, slack for tasks to which
    the resource is assigned appears graphically as a
    thin slack bar adjoining the regular Gantt bar.
  • 3 In the Resource Name field in the top left
    portion of the view, click the resource name for
    the overallocated resource with a task you want
    to delay.
  • 4 In the Leveling Delay field (bottom left
    portion of the view) for the task you want to
    delay, type the amount of time that you want the
    task to be delayed. To ensure that successor
    tasks are not affected, do not enter more lag
    than the amount of free slack for that task.
  • 5 To return to a single view, on the Window menu,
    click Remove Split.

43
Change a resource's working days and hours
  • The project calendar designates the default work
    schedule for the project, but you can create a
    resource calendar to indicate work hours,
    vacations, leaves of absence, and sick time for
    individual resources.

44
How
  • 1 On the Tools menu, click Change Working Time.
  • 2 In the For box, click the resource whose
    calendar you want to change.
  • 3 On the calendar, select the days you want to
    change. To change a day of the week for the
    entire calendar, select the day at the top of the
    calendar.
  • 4 Click Use default, Nonworking time, or
    Nondefault working time.
  • 5 If you clicked Nondefault working time in step
    4, type the times you want work to start in the
    From boxes and the times you want work to end in
    the To boxes.
  • 6 Click OK.

45
(No Transcript)
46
How
  • 1 Microsoft Project automatically updates actual
    costs as a task progresses based on the accrual
    method you set. You must first turn off the
    automatic updating of actual costs to edit actual
    costs. On the Tools menu, click Options, and then
    click the Calculation tab.
  • 2 Clear the Actual costs are always calculated by
    Microsoft Project check box.
  • 3 Click OK.
  • 4 On the View menu, click Task Usage.
  • 5 On the View menu, point to Table, and then
    click Cost.
  • 6 On the Format menu, point to Details, and then
    click Cost.
  • 7 On the Format menu, point to Details, and then
    click Actual Cost.
  • 8 To enter actual cost values for a task, select
    a day or other time period in the timescale
    portion of the view, and then type a value into
    the Act. cost field for the task.
  • To enter actual values for a resource, select a
    day or other time period in the timescale portion
    of the view, and then type a value into the Act.
    cost field for the resource.

47
Tip 
  •   You can enter actuals in other time increments,
    such as weeks. On the View menu, click Zoom, and
    click the increment you want.

48
See if tasks cost more or less than budgeted
  • If you assign fixed costs to tasks or specify
    wages for resources, you may want to see tasks
    that cost more than budgeted. By creating a
    budget using a baseline plan and closely tracking
    your project costs, you can catch cost overruns
    early and adjust either your schedule or your
    budget accordingly.
  • Microsoft Project calculates the cost of each
    resource's work, the total cost for each task and
    resource, and the total project cost. These costs
    are considered scheduled or projected costs,
    which reflect the latest cost picture as the
    project progresses.

49
How
  • 1 On the View menu, click Gantt Chart.
  • 2 On the View menu, point to Table, and then
    click Cost. If necessary, press TAB to view the
    Total Cost and Baseline fields.
  • 3 Compare the values in the Total Cost and
    Baseline fields. For the cost variance, look at
    the value in the Variance field.

50
Tips
  • To see the total cost, baseline, and variance
    information for the entire project, you can
    display the project summary task. On the Tools
    menu, click Options, and then click the View tab.
    Under Outline options, select the Project summary
    task check box, and then click OK.
  • You can view the resources assigned to a task and
    the resource costs related to that task. On the
    View menu, click Task Usage. On the View menu,
    point to Table, and then click Cost. Drag the
    divider bar to the right and compare the values
    in the Total Cost, Baseline, Actual, and
    Remaining fields for the resources assigned to
    that task.

51
See the total project costs
  • You can view your project's current, baseline,
    actual, and remaining costs to see whether you're
    staying within your budget. These costs are
    updated each time Microsoft Project recalculates
    your project.
  • 1On the Project menu, click Project
    Information.2Click Statistics. The current,
    baseline, actual, and remaining costs are
    displayed in the Costs column.

52
Analyze costs with the Earned Value table
  • When you want to compare your expected progress
    with the actual progress to date, you can use the
    Earned Value table. It compares, in terms of
    costs, each task's baseline schedule with the
    actual schedule.
  • You can also use the Earned Value table to
    forecast whether the task will finish under or
    over budget based on the cost incurred while the
    task is in progress. For example, if a task is
    50 complete and the actual cost incurred to date
    is 200, you can see if 200 is more than, less
    than, or equal to 50 of the baseline (or
    budgeted) cost. The VAC field displays the
    variance at completion between baseline cost and
    scheduled cost for a task.

53
How
  • 1 On the View menu, click Gantt Chart.
  • 2 On the View menu, point to Table, and then
    click More Tables.
  • 3 In the Tables list, click Earned Value, and
    then click Apply.
  • 4 Drag the divider bar to the right to display
    all of the Earned Value table fields. The values
    are calculated based on the actual work and costs
    up through and including the current date. To
    change the calculation date, on the Project menu,
    click Project Information. In the Status date
    box, type the date you want to use, and then
    click OK.

54
Tips
  • Move the mouse pointer over a field name to get a
    description of the field for example, position
    the pointer over the VAC field and click Help on
    VAC for a description of the field.
  • In the Task Usage view, you can view earned value
    data over time periods such as daily, weekly,
    monthly, quarterly, or yearly. On the Format
    menu, click Detail Styles, and then click the
    Usage Details tab. In the Available fields list,
    hold down CTRL, click the earned value fields you
    want to display (such as ACWP, BCWP, CV, or SV),
    and then click Show. Double-click the timescale
    to change the time periods that you see.
  • To see cost variances for the entire project, you
    can display the project summary task. On the
    Tools menu, click Options. Click the View tab and
    under Outline options, select the Project summary
    task check box.
Write a Comment
User Comments (0)
About PowerShow.com