Title: School District of Osceola County Facilities, Planning, Maintenance
1School District of Osceola CountyFacilities,
Planning, Maintenance Construction
- Monthly Update September 2007
- Construction Workshop
- 25 September 2007
2Report Contents
- Planning Services Division Update
- Property Acquisition Summary
- General Issues Update
- Permitting Services Division Update
- Activity Report Permits, Inspections, C.O.s
- General Administrative Issues
- Design and Construction Services Division Update
- 2006-2007 Goals
- Capital Outlay Planned Projects Update
- Major Projects Highlight Reports
- Projects in Design Bidding
- Tax Savings Summary New Schools
- General Issues Update
- Maintenance
- School Opening
- Portable Update
3Planning Property Acquisitions
- Elementary I (Anthem Park)
- Property acquisition has been closed. School is
scheduled to open in August 07. - Annexation into City of St. Cloud pending.
- Elementary J (Harmony)
- Closing for site acquisition is completed.
- Comprehensive Development Plan Application has
been submitted to Osceola County for Approval. - 3. Elementary K (Flora Ridge)
- Ownership of school site to be transferred from
EFBD to SDOC after construction of school. - Elementary L (Poinciana)
- Contract with Avatar Properties for acquisition
of the school site pending. - Staff working to determine scope and budget for
adjacent intersection improvements required by
Osceola County. - Comprehensive Development Plan Application has
been submitted to Osceola County for Approval. - Middle CC (Westside DRI)
- Developer will convey the property to the SDOC
through their EFBD in July 2007. Assessments
will be used to fund the site acquisition at no
cost to SDOC. - Site Due Diligence is completed.
4Planning Developments of Regional Impact (DRI)
- Lake Toho DRIs includes Anthem Park, Westlake
Cove, Mariners Cove, Edgewater, Bella Tara,
Friars Cove, and Green Island. - Projects consists of approx. 38,000 residential
units. - Anticipated need for an additional 9 elementary,
3 middle, and 3 high schools. - Development order language regarding schools has
been finalized. - Staff meeting regularly with Lake Toho Assoc.
consultants to discuss school siting and timing
of residential development and school
construction. - Tranquility DRI located north of Southport Rd
east of Pleasant Hill. - Project consists of 1,800 mixed residential
units. - Identified need and requested property for 2
future elementary schools. - 3. Sundance DRI located east of Poinciana
north of PHS. - Project consists of up to 1,500 mixed residential
units. - Identified need and requested property within
proposed development for future middle school. - 4. Centerlake DRI located northwest of Nova Rd.
east of Narcoossee. - Project consists of 6,600 mixed residential
units. - Identified need for an elementary, middle, and
high school in the area. Staff working with
developer representatives to secure property for
future school site(s) within development.
5Planning DRI (cont.)
- Rolling Oaks DRI located west of Formosa
Gardens Blvd. north of Funie Steed Rd. - Project consists of 1,800 multi-family
residential units. - Identified need for an elementary and middle
school in the area. Staff is working with
developer to secure property within development
boundary for one of future schools. - Stoneybrook South DRI located west of Champions
Gate DRI. - Developer agreed to donate property for future
elementary school site within development as
recorded in their approved, project development
order. - Staff working with developer to finalize site
acquisition and determine timing for development
and school construction. - Westside DRI located along Westside Blvd.
- Developer had dedicated an elementary school site
as recorded in their approved, development order. - Staff working with developer to finalize site
acquisition for future Middle School CC
project.
6Planning Concurrency
- Refer to the package of information
7Planning Long Range Planning Committee
August meetings update will be presented.
8Permitting Activity Report
- July August 20, 2007
-
- YTD
- Inspections Performed 84
1287 - Inspection Hours 86
1298 - Certificates of Occupancy 23
122 - Portable Units Certified 123 N/A
- Certificates of Completion 20
130 - Permits Issued 24
137
9Permitting
- General Issues
- All summer portables are installed and inspected
100 occupancy. - Administrative Issues
- Occupancy certificates have been issued for
Neptune Elementary School and Liberty High School.
10Design Construction Services Goals
- Completion/Start of all Capital Outlay Planned
Projects within the fiscal year. - Completion/Start of 90 of 06-07 projects by
July Workshop. - Construction complete and open new schools for
August 07. - Substantially Complete HS EEE July 07.
- Substantially Complete ES I July 07.
- 3. Design and start construction for new schools
opening in 08. - Start construction on ES J by July 07.
- Start construction on ES L by end of 1st
quarter of 07/08, pending site acquisition and
approvals. - Substantially Complete ES K October 07.
- Start construction on Sports Authority Conversion
by end of 1st Quarter 07/08, pending resolution
on City of Kissimmee conditions and requirements. - 4. Implement Management Initiatives.
- Publish a Process Procedures Manual 50 1st
draft copy for January 07. - Development implementation of programs to
assist in department operations and project
administration.
11Capital Outlay Program Status 07-08
- The data provided reflects Capital Outlay amounts
based on Board approved budgets for planned
projects for renovation, remodeling, and other
cyclical renewal projects only. - 99 of the Planned Project Capital Program is
either completed or started. - Started/Completed Goal of 90 was exceeded by
July 07.
12Project Highlight Elementary K
13Project Highlight Elementary K
14Project Highlight Elementary K
15Project Highlight Elementary I
16Project Highlight Elementary I
17Project Highlight High School EEE
18Project Highlight High School EEE
19Project Highlight High School EEE
20Project Highlight Elementary J
21Design Construction Request for Services
- 1. RFQs under development to Purchasing
September/October 2007 . - A/E Services for Schools Master Plan
- CM _at_ Risk for Schools Master Plan
- Student Enrollment Projections
- Flooring Bid
- 2. Advertised RFQs October/November 2007.
- CM _at_ Risk for Middle School CC
- Roofing and Building Envelope Consultant
- 3. In Review/Selection Process
- Geotechnical Materials Testing for OCSA and
Middle School CC - HVAC Test Balance for OCSA and Middle School
CC
22Design Construction Owner Direct Purchase
Program
- Tax Savings Summary New Schools
23Wrap Up