1Province of the Eastern Cape
DEPARTMENT OF AGRICULTURE CONDITIONAL GRANT
AND CAPITAL EXPENDITURE THIRD TERM REPORT
2TABLE OF CONTENTS
- Situation Analysis - CASP
- Situation analysis Land Care
- Agricultural Disaster Management Grant
- Capital spending third term report
3SITUATION ANALYSIS - CASP
- Budget
- CASP was allocated a budget of R57 061 000 for
the year under review. A rollover of R5 986 000
is awaiting approval by the provincial
legislature. - Cash flow from National
- R45 649 000 has been transferred to the
province. - Expenditure
- R32 025 030 has been spent as at 31 December 2006
- _R33 938 000 has been spent as at 6 February 2007
4SITUATION ANALYSIS - CASP
- CASP funded Projects
- 170 projects have been approved across the six
District Offices and Head Office. - Split per project type
- Type of project Budget
Expenditure Committed - Fencing R 11,159,266 R 6,684,550 R 3,762,425
- Stock Water Dams R 2,057,021 R 891,440 R 785,714
- Dip Tanks R 2,090,261 R 160,447 R 168,116
- Hydroponics R 1,767,451 R 315,754 R 1,357,955
- Production Inputs R 900,000 R364,630 R 418 400
5SITUATION ANALYSIS - CASP
- Split per project type
- Type of project Budget Expenditure
Committed - Poultry House R 4,030,098 R 2,311,302 R
1,216,781 - Dairies R 1,403,812 R 96,378 R 532,785
- Handling Facilities R 150,000 R 87,982 R
83,991 - Storage Sheds R 593,220 R 177,737 R 315,483
- Shearing Sheds R 5,190,558 R 2,292,695 R
2,897,8646 - Irrigation Schemes R 15,744,000 R 15,744,000 R 0
- Mechanization R 14,130,766 R 1,586,552 R
12,586,552
6ANALYSIS OF CASP CATEGORIES
- The analysis shows more budget allocation for
fencing, shearing sheds ,irrigation schemes and
mechanization.The thrust of the province is on
food security, which requires fencing of arable
lands and gardens,livestock improvement through
introduction of better rams for wool improvement,
which requires shearing sheds for wool classing
and baling. The province has started
resuscitation of six large irrigation
schemes.Provision of small and large tractors
assists farmers on LRAD and communal areas to be
productive both under irrigation and dry land
food production.
7SITUATION ANALYSIS - CASP
- Challenges
- Lack of financial capacity from the developing
contractors - Socio-political problems within the communities
retard the implementation of Social conflicts,
political differences, etc. - Lack of project management capacity from the
developing contractors resulting in projects
being not finished on time.
8SITUATION ANALYSIS - CASP
- Remedial Measures
- Financial Institutions are in agreement to
provide start-up capital to the developing
companies at the presentation of approved orders
from the provincial department of agriculture. - Social Mobilisation is being done to facilitate
community involvement, participation and
ownership where and when necessary to speed
implementation and reduce social conflicts. - Emerging Contractors are being capacitated on
project and financial management through the
Extended Public Works Programmes of the
department of Public Works.
9SITUATION ANALYSIS LAND CARE
- Budget
- LandCare has been allocated a budget of R6 675
000 for the 2006/07 financial year. - R737 000 rollover from the provincial treasury is
awaiting approval by the provincial legislature. - An additional R4 375 000 for the implementation
of a Land Care project in the Umzimvubu Catchment
was approved the National Department of
Agriculture. This amount is also awaiting
approval by the provincial legislature.
10SITUATION ANALYSIS LAND CARE
- Cash Flow
- R5 340 000 has already been transferred to the
province. - Expenditure
- R5 277 000 has been spent as at 31 December 2006.
11SITUATION ANALYSIS LAND CARE
- Land Care funded projects
- 6 projects are funded by this Conditional.
- All these projects focus on the following
objectives - Resource planning Capacity building
- Infrastructure to enable resource planning e.g.
Fencing - Rehabilitation and protection resources, e.g.
soil conservation works
12SITUATION ANALYSIS LAND CARE
- Land Care funded projects
- Split by project
- Project Budget Expenditure
- Mthatha Dam Catchment 2 000 000 1 606 000
- Dlula Bedlala 50 000 50
000 - Camdeboo 70 000 8 000
- Sterkpruit Ward 4 2 500 000 1 780
000 - Sidindi 2 025 000 1 806 000
- Ntseshe 30 000 27 000
- 6 675 000 5 277 000
-
13SITUATION ANALYSIS LAND CARE
- Challenges
- The fact that the rollovers has not been approved
yet poses a serious threat of under spending. - Capacity constraints to implement Land Care
- The Extension Officers of the department who are
in constant touch with the communities are
falling short when it come to broader capacity
building in communities. - The shortage of Resource Planners reduces the
capacity of the department to effectively
implement Land Care projects. - The department has a serious problem to recruit
and retain engineering staff to design the
infrastructure and supervise construction.
14SITUATION ANALYSIS LANDCARE
- Remedial Measures
- The training of Extension Officers needs to
extended to include community capacity building
skills - The department is looking to apply some
incentives to lure the scarce skilled personnel
to the department
15AGRIC. DISASTER MANAGEMENT GRANT
- Budget
- R12 403 000 was received as an additional funding
from the National Department of Agriculture
during the time of preparing for the 1st
Adjustment Estimates - Cash flow
- There were no cash flows for the period under
review - Expenditure
- No expenditure yet as this funding is caught up
with the delayed Adjustment Estimates which are
yet to be approved by the provincial legislature.
16CAPITAL EXPENDITURE THIRD TERM
- Item Allocation Spent Variance
Commitments - R000 R000 R000
R000 - Assets 13 417 2 481 10 936
7 109 - The capital budget of R13.417million,which is
for computers, office furniture, office equipment
and cabling of our offices, has experienced
delays due to the lengthy process of procuring
expensive capital equipment. However to date
R9.590m has been spent and formally committed. .