Title: Undulator Week Issues


1
Undulator Week Issues
  • C.E. Rago
  • System Integration

2
Integration Issues
  • SLAC Earthquake Updates
  • Written Report under review prior to SLAC-EC
    presentation.
  • DeBarger / Dormiani
  • Difficulties
  • SLAC Procedural Adjustments / Pending Upgrades
  • Design Style, Complete Integrated Procedures
  • Uniformity / Efficiency of Installation

3
Summary
  • Magnet, Girder, Pedestal System is in compliance
    with current SLAC Earthquake standards in
    regards to preservation of functionality.
  • SLAC-1-720-0A24E-002 with slight modifications
  • 1997 Uniform Building Code
  • Caveats
  • Formal Earthquake Committee Approval
  • Installation procedures must support the current
    ANL design and all manufacturer installation
    procedures.
  • Earthquake preloads must be applied, equal to and
    or greater than the ANL design.
  • ANL to load tests to failure are run on
    positioning slides.
  • Hard Shims, between pedestal and concrete, needs
    to be analyzed.

4
Pre-Loads/ Stresses
  • Foot Plate Connection 1300 in-lbs
  • Support Plate to Transition 380 in-lbs
  • Transition Plate to Slide 330 in-lbs
  • Slide to Girder 300 in-lbs
  • Girder to Interface 70 Yield

5
Slide Test
  • No manufacturing data available on seismic and or
    similar loads.
  • M/Mp 81 (Seismic M / Static Mp)
  • Mp is about the Z axis.

6
Hard Shims
  • Current Assumption
  • There is no stand-off between anchor plate and
    the concrete floor.
  • ANL design
  • Shims at 6/6 anchors
  • Grouted Base Plate
  • Sand filled Pedestal

7
Concrete Anchors
  • Assumed Hilti HIT-RE-500-SD Adhesive Anchors.
  • Current calculation was simplified to use only 4
    outer anchors.
  • Must calculate the effect of 6 anchors per
    pedestal.

8
Integration Issues
  • Integrated Assembly Procedure
  • Zurawel to Lundahl to Poling
  • Start from existing ANL procedures.
  • Zurawel is expanding to cover all field tasks.
  • Lundahl coordinating alignment.
  • Metrology dominates assembly-LeCocq Wolf
  • Poling will control vacuum, handling, and
    anything else we need.