EARNED VALUE MANAGEMENT SYSTEM A Project Performance Tool - PowerPoint PPT Presentation

1 / 47
About This Presentation
Title:

EARNED VALUE MANAGEMENT SYSTEM A Project Performance Tool

Description:

The Work Breakdown Structure (WBS) identifies and groups major deliverables ... SV (Schedule Variance) The difference between the value of work ... – PowerPoint PPT presentation

Number of Views:87
Avg rating:3.0/5.0
Slides: 48
Provided by: roytu5
Category:

less

Transcript and Presenter's Notes

Title: EARNED VALUE MANAGEMENT SYSTEM A Project Performance Tool


1
EARNED VALUE MANAGEMENT SYSTEMAProject
Performance Tool
  • By
  • Roy T. Uemura, PMP, P.E., MBA
  • Project Management Consultant
  • Project Professionals, LLC

2
How Is Your Project Doing?
  • Ahead of schedule?
  • Within your approved Budget?

3
How Is Your Project Doing?
  • What is your cost estimate at completion?
  • Will you be ahead or behind the scheduled
    completion date?

4
Agenda
  • Explanation of Earned Value Management (EVM)
  • The traditional Two Dimensional System of
    Evaluation
  • EVM Three Dimensional System of Evaluation
  • Critical Variables in EVM
  • EVM Formulas
  • Applying EVM on projects
  • Example

5
Earned Value Management
  • Method for integrating scope, schedule, and
    resources, for measuring project performance.
  • Compares what was planned with what was actually
    spent with what was actually earned

6
Earned Value Management
  • Developed in the 1960s
  • Popular method for reporting and controlling
    project in the Department of Defense
  • A common language to report progress and cost
    against a project
  • Helps answer the questions
  • Are we on schedule?
  • How much did the work we do cost?
  • Are there variances?
  • Based on these trends, how much will it cost by
    the end of the project?

7
Early Warning System
  • based on the Project Performance Plan
  • and Projects Actual Performance against
  • the Plan,
  • the project will likely take this much time to
    finish, and
  • spend this much money.

8
Traditional System(Two Dimensional)
  • Cost compares what was planned to be expended
    versus what was actually expended
  • Time Compares the date you are on a project
    versus when the project is to be completed
  • Production Compares how much work was planned
    to be completed versus how much was actually
    completed.

9
Earned Value(Three Dimensional)
  • 1. Actual work that was earned
  • versus
  • 2. Work that was accomplished
  • versus
  • 3. Work that was scheduled to be accomplished

10
Critical Variables to EV Performance Indices
  • Quality of the project baseline plan
  • Actual performance against baseline plan
  • Managements determination to control (change)
    the final results

11
Project Baseline
  • Basis of performance measurement
  • Represents technical, cost and schedule
    objectives of the project
  • Cashflows
  • Outside Material
  • Outside Services

12
Scope of Work
  • The scope of work of entire project must be
    defined
  • The Work Breakdown Structure (WBS) identifies and
    groups major deliverables
  • Integrate scope with budget and schedule.

13
Performance Measurement Methods
  • Fixed formula by task
  • 0/100 , 25/75, 50/50
  • Weighted Milestones Percent complete based on
    specific work
  • (milestone) accomplished.
  • Percent Complete
  • Increment completed / total activity or task
  • Equivalent Completed Units

14
Cost Account Plan
15
Project Description
  • Installed approximately 14.5 miles of
    transmission line of which about 4,000 feet was
    installed underground.
  • Installed 93 steel poles 52 poles were direct
    buried and 41 were mounted on pier foundations.

16
Kuilima
Waialua
17
Visual Progress Report
  • Foundation Dug Concrete Poured
  • Pole Erection
  • Lines Strung
  • Trench
  • Conduit Installed
  • Cable Installed
  • Trench Covered

18
Kuilima
Waialua
19
Controlling Change
  • Essential Change Management Control System in
    the Project Plan prevents incorrect,
    inappropriate, or unauthorized changes to the
    project.
  • Inform appropriate stakeholders of authorized
    changes to the Baseline (scope/quality, schedule,
    cost)

20
EVM Input Data Required
  • PLANNING PHASE
  • Planned Value (PV)
  • Budget At Completion (BAC)
  • Complete - Planned
  • EXECUTING CONTROLLING PHASES
  • Actual Cost (AC)
  • Complete - Actual

21
Calculations from Input Data
  • Earned Value - EV
  • Cost Variance - CV
  • Schedule Variance - SV

22
Calculations for Analysis
  • Cost Performance Index - CPI
  • Schedule Performance Index - SPI
  • Budget at Completion - BAC
  • Estimate to Completion - ETC
  • Estimate at Completion - EAC
  • To Complete Performance Index - TCPI

23
Primary Data Elements
  • PV (Planned Value)
  • The value of the amount of work that was
  • planned to be accomplished on a task (or a
  • project) as of a certain date in the baseline
  • plan.
  • BAC (Budget at Completion)
  • Total cost of a task (or project) according to
  • the baseline plan.

24
Primary Data Elements (contd)
  • AC (Actual Cost)
  • The actual amount of money spent
  • on a task (or project) as of a certain date.

25
Performance Analysis
  • EV (Earned Value).
  • The value of the amount of work actually
  • completed on a task (or project) as of a
  • certain date, according to the baseline
  • plan.
  • EV Actual Complete x BAC

26
Performance Analysis (contd)
  • CV (Cost Variance)
  • The difference between the value of work
  • that was actually completed (EV) on a task
  • (or project) and the cost that was actually
  • spend (AC) on the task (or project) as of a
  • certain date.
  • CV EV - AC
  • ( spending less than planned)

27
Performance Analysis (contd)
  • SV (Schedule Variance)
  • The difference between the value of work
  • that was actually completed (EV) on a task
  • (or project) and the work that should have
  • been done (PV) as of a certain date.
  • SV EV - PV
  • ( Ahead of Schedule)

28
Performance Analysis (contd)
  • CPI (Cost Performance Index)
  • The ratio of the value of work actually
  • completed (EV) on a task (or project) and
  • amount actually spent (AC) on a task (or
  • project) as of a certain date.
  • CPI EV/AC
  • (gt1 Spending less than planned)

29
Performance Analysis (contd)
  • SPI (Schedule Performance Index)
  • The ratio between the value of work that was
  • actually completed (EV) on a task (or project)
  • and the work that should have been done
  • (PV) as of a certain date.
  • SPI EV/PV
  • (gt1 Ahead of Schedule)

30
Performance Analysis (contd)
  • ETC (Estimate To Completion)
  • The forecasted cost of the remaining task
  • (or project) is calculated by CPI or
  • CPI x SPI
  • ETC Remaining Work / CPI
  • (BAC - EV/ CPI
  • or
  • ETC Remaining Work/ (CPI x SPI)
  • (BAC - EV/(CPI x SPI)

31
Performance Analysis (contd)
  • EAC (Estimate at Completion)
  • The value expressed in either dollars or hours
  • to represent the projected final cost of work
  • when completed. The EAC equals the actual
  • costs (AC) incurred plus the estimated costs
  • to complete the remaining work (ETC).
  • EAC AC ETC

32
Performance Analysis (contd)Ranges of Estimate
at Completion
  • High-End Projection (Cumulative CPI x SPI)
  • EAC AC (BAC - EV) / (CPI x SPI)
  • In-Between Projection (80 CPI x 20 SPI)
  • EAC AC (BAC - EV) / (0.8 CPI x 0.2 SPI)
  • Low-End Projection (Cumulative CPI)
  • EAC AC (BAC - EV) / CPI

33
To Complete Performance Index
  • TCPI Project performance which must be
  • achieved on all remaining work in order to
  • meet the financial goal by management
  • TCPI Work Remaining / Funds Remaining
  • (Total Budget - Earned value)
  • (BAC - Actual Costs)
  • (BAC - EV)
  • (BAC - AC)

34
PMP Exam
  • Estimate At Completion (EAC)
  • EAC BAC
  • CPI
  • Estimate to Complete (ETC)
  • ETC EAC - AC
  • Rita Mulcahy, PMP Exam Prep 5th Edition (2005)

35
Example
  • Time 4th month of 10 month schedule
  • Budget at Completion BAC 10,000
  • Planned Value PV 4,000
  • Actual Cost AC 3,800
  • Actual Complete 36
  • Earned Value
  • EV 0.36 x 10,000 3,600

36
Earned Value Analysis
Status Date
BAC
10,000
5,000
PV 4,000
AC 3,800
EV 3,600
3
1
6
7
2
4
5
8
9
10
Time
37
Performance Analysis
  • Traditional Analysis
  • Cost Variance Planned Expenditure - Actual Cost
  • CV PV - AC
  • CV 4,000 - 3,800 200 (under spent by 200)
  • Earned Value Analysis
  • CV EV - AC
  • CV 3,600 - 3,800 -200 (spending more than
    planned for work performed)
  • SV EV - PV
  • SV 3,600 - 4,000 -400 (less work was done
    than planned)

38
Performance Analysis
  • Cost Performance Index (CPI)
  • CPI EV / AC
  • CPI 3,600/3,800 0.95 (lt1, for every 1
    spent, only 0.95 in physical work was done)
  • Schedule Performance Index (SPI)
  • SPI EV / PV
  • SPI 3,600 / 4,000 0.9 (lt1, for every 1 of
    physical work planned, only 0.9 was done)

39
Performance Analysis
  • Estimate To Complete (ETC)
  • ETC (BAC - EV) / CPI
  • ETC (BAC - EV) / (CPI x SPI)

40
Performance Analysis
  • Estimate At Completion (EAC)
  • EAC AC (BAC - EV)/(CPI x SPI)
  • 3,800 (10,000 3,600) / (0.95 x
    0.90)
  • 11,285 (high end)
  • EAC AC (BAC - EV) / CPI
  • 3,800 (10,000 3,600) / 0.95
  • 10,537 (low end)

41
Performance Analysis
  • To Complete Performance Index (TCPI)
  • TCPI (BAC - EV) / (BAC - AC)
  • TCPI (10,000 - 3,600) / (10,000 - 3,800)
  • TCPI 6,400 / 6,200
  • TCPI 1.03

42
Analyzing Data for Trends
10
5
0
(5)
Schedule Variance
(10)
(15)
Cost Variance
(20
43
Earned Value Analysis
EAC 9.5 M
CPI
EAC (7.5 M)
SPI
Baseline Budget CPI SPI 1
1.0
Time
44
Performance Report
45
Float and Management Reserves
  • The project manager should control contingency
    reserve and schedule float
  • The work at hand expands to fill the time
    available
  • Expenditures will rise to meet the budget.
  • The remaining management reserves should be
    added to EAC until such time when the reserve is
    no longer needed.

46
Earned Value Management SystemPerformance
Management
  • Accurate Baseline Estimate
  • Measure Performance against the Plan
  • Analyze variances to Plan
  • Assess impacts to Overall Plan
  • Identify corrective actions
  • Implement the corrective actions

47
  • Questions?
Write a Comment
User Comments (0)
About PowerShow.com