Title: Chapter 15 Material Requirements Planning
1Chapter 15 -Material Requirements Planning
2Demand Patterns
2000 1500 1000 500 0
(a)
(b)
3What went wrong when EOQ is used to manage a
dependent demand item?
- Incorrect assumption of uniform. continuous
demand - Incorrect assumption on item independence
- Lack of Forward visibility
4MRP Success
- American Sterilizer Company
- On-time deliveries up from 70 to 95
- Overtime down by at least 50
- Component shortage down by over 80
- Indirect labor down by 24
- Direct labor down by 7
- Survey of Other Firms
- Inventory turns up from 3.2 to 4.3
- On-time delivery up from 61 to 76
- Delivery lead time down from 71 to 59 days
5Material Requirements Plan Input/Output
Figure 15.2
6Bill of Materials (BOM)
7Bill of Materials
Back slats
Seat cushion
Seat-frame boards
Leg supports
Front legs
Back legs
A Ladder-back chair
Figure 15.3
8Master Production Schedule (MPS)
A detailed plan that states how many end items
will be produced within specified periods of
time. a. End items are either finished products
or the highest level assemblies from which
shippable products are built. b. Time periods
are usually measured in weeks, although they
may be measured in hours, days, or even months.
9Master Production Schedule
April
May
1
2
3
4
5
6
7
8
Ladder-back chair
150
150
Kitchen chair
120
120
Desk chair
200
200
200
200
Aggregate
670
production plan
670
for chair family
Figure 15.4
10Inventory Record
Figure 15.5
11Projected On-hand Inventory
- It I t-1 SRt PRt - GRt
- where
- It projected on-hand inventory at end of week t
- SRt scheduled receipt due in week t
- PRt planned order receipt in week t
- GRt gross requirements in week t
12Inventory Record
Figure 15.5
13Planned Orders
Figure 15.6
14Planned Orders
Figure 15.6
15Planned Orders
Figure 15.6
16Planned Orders
Figure 15.6
17Planned Orders
Figure 15.6
18Lot-Sizing Rules
- a. Static Lot-Sizing Rules
- Same order quantity each time
- Fixed order quantity (FOQ)
- Interger multiples
- b. Dynamic Lot-Sizing Rules
- Enough to cover a specified number of weeks
- Periodic order quantity (POQ)
- Lot for Lot (L4L)
19Lot-Sizing Rules - POQ
Figure 15.7
(120 0 150) - 117 153 units
117
117
153
20Lot-Sizing Rules - POQ
Figure 15.7
(120 0) - 0 120 units
117
117
150
150
0
0
0
153
120
153
120
21Lot-Sizing Rules - L4L
Figure 15.8
( )
L4L lot size
120 - 117 3
0
3
3
22Lot-Sizing Rule Comparison
- FOQ does not match requirements exactly, it
generates high average inventory because it
creates remnants. - POQ rule reduces average
- on-hand inventory due to a
- better match between order
- quantity and requirements.
- The L4L rule minimizes inventory investment but
increases the number - of orders placed.
23MRP Outputs
Figure 15.9
24Bill of Materials
Figure 15.10
25MRP Explosion
Figure 15.11
26MRP Explosion
Figure 15.11
27MRP Explosion
Figure 15.11
28MRP Explosion
Figure 15.11
29MRP Explosion
30MRP Explosion
31MRP Explosion--Example 2
32MRP Explosion-Example 2
33MRP Explosion-Example 2
34MRP Explosion-Example 2
35Action Notices
- A computer-generated memo indicating the need to
release a new order or adjust the due date of a
scheduled receipt. - Release New orders
- If planned order release is in the action bucket.
- Adjusting Due Dates
- 1. Arriving too early If subtracting scheduled
receipt from projected on-hand inventory does not
reduce inventory below desired safety stock. - 2. Arriving too late If projected on-hand
balance for week prior to its arrival is not
enough.
36Action Notices for Chair seat Assembly
37Capacity Requirements
Figure 15.12
38Input-Output Report
39Requirements Planning-the evolution
- MRP generates schedules that meet the materials
needs identified in the MPS - MRP II ties basic MRP with to the companys
financial system allows for what if analysis
(MPS, cash flow, etc.) - ERP enables firms to deal directly with
suppliers to assess their resources availability
(also includes quality, field services,distributio
n, marketing, accounting etc.)
40Bill of Resources
(b)
Figure 15.14
(a)
41MRP Implementation Issues
- Four Prerequisites
- 1. Computer Support
- 2. Accurate and Realistic Inputs
- a. MPS
- b. BOMs
- c. Inventory Record
- 3. Management Support
- 4. User Knowledge and Acceptance
42Distribution Requirements Planning