Title: A Look Ahead
1A Look Ahead
- We will now turn our attention to several tools
and techniques associated with Project Time
Management - First, we will consider
- PERT CPM Historical Perspective
- Overview of Sequencing Techniques
- ADM Arrow Diagramming Method
- Determining the Critical Path
- download ADM_Class_Example.doc
Strategic Project Management
1
SPM Basic PERT/CPM (Part 1)
2A Look Ahead(continued)
- After that, we will continue our exploration of
tools and techniques by considering - The Concept of Float
- download ADM_Float_Calcs.xls
- Probabilistic Activity Duration Estimates
- download ADM_Mean_Variance.xls
- Probabilistic Project Completion
- download ADM_Standard_Normal_Table.xls
Strategic Project Management
2
SPM Basic PERT/CPM (Part 1)
3PERT/CPMSome History
- PERT was first used in the late 1950s by the
Navy for the Polaris Missile Program - PERT gt Project Evaluation Review Technique
- Development was in conjunction with the
consulting firm of Booz, Allen, and Hamilton - Development was designed to meet the needs of the
age of massive engineering - The Navy was concerned with performance trends on
large military projects.
Strategic Project Management
3
SPM Basic PERT/CPM (Part 1)
4PERT/CPMSome History (continued)
- Virtually simultaneously CPM was developed by the
duPont Company and Remington-Rand-Univac. - CPM gt Critical Path Method
- For use on large construction projects
- Specifically targeted for process industries
- The two groups were unaware of each other's
existence until about 1960. - By then, each stood on its own merits
Strategic Project Management
4
SPM Basic PERT/CPM (Part 1)
5PERT/CPMSome History (continued)
- PERTs strengths are in its use of probabilistic
estimates of activity durations - CPMs strengths are in its ability to do
time-cost trade-offs - Today, PERT/CPM are widely recognized as
comprising one set of techniques - the differences are primarily viewed as only of
historical importance
Strategic Project Management
5
SPM Basic PERT/CPM (Part 1)
6Activity SequencingDisplay Techniques
- There are many suitable techniques for displaying
the sequence of activities involved in a project - Gantt Charts
- Precedence Diagramming
- Arrow Diagramming
- Conditional Diagrams
Strategic Project Management
6
SPM Basic PERT/CPM (Part 1)
7Gantt Charts
- Gantt charts use horizontal bars (or lines) to
represent activities - Gantt charts are more commonly used for schedule
display than activity sequencing - see BOK Figure 6-6 (1996 2000) for an example
- length of the bars show expected duration
- activity inter-relationships are not explicitly
shown - we will see Gantt Charts again when we consider
Resource Loading Leveling
Strategic Project Management
7
SPM Basic PERT/CPM (Part 1)
8The Precedence Diagramming Method
- The Precedence Diagramming Method (PDM) uses
boxes to represent activities and arrows to
represent dependencies - see BOK Figure 6-2 (1996 2000 for an example
- This technique is also known as the
Activity-on-Node (AON) Diagramming
Strategic Project Management
8
SPM Basic PERT/CPM (Part 1)
9More on PDM
- Dependencies can include
- Finish-to-Start
- Finish-to-Finish
- Start-to-Start
- Start-to-Finish
- Dependencies are usually indicated by the
placement of the arrow heads and tails relative
to the nodes but no consistent approach has been
universally adopted. - Looping and Conditional Branching is not allowed
Strategic Project Management
9
SPM Basic PERT/CPM (Part 1)
10The Arrow Diagramming Method (ADM)
- The Arrow Diagramming Method (ADM) uses the
following conventions - Arrows represent activities
- "Regular" activities require time and resources
- "Dummy" activities show precedence relationships
- Nodes represent events
- A point in time
- Some nodes may represent milestone events
- see BOK Figure 6-3 (1996 2000) for an example
Strategic Project Management
10
SPM Basic PERT/CPM (Part 1)
11More on ADM
- Also known as Activity-on-Arrow (AOA)
- Each activity is represented by one and only one
arrow in the network. - Nodes (events) are numbered uniquely.
- Duplicate node numbers are not allowed
- No two activities can be identified by the same
beginning and ending nodes. - Dummy activities may be required
Strategic Project Management
11
SPM Basic PERT/CPM (Part 1)
12More on ADM (continued)
- Before an activity can begin, all activities
terminating at the activities beginning node must
be completed. - Neither the length of an activity arrow nor its
compass direction have any significance. - Networks should (must) have only one initial
event and one terminal event.
Strategic Project Management
12
SPM Basic PERT/CPM (Part 1)
13An Example to TryDraw an Arrow Diagram
- A project consists of Activities A, B, C, D, E,
F, G, H, I, J, K, and L - A, B, and C, the 1st activities of the project,
can start simultaneously - A and B precede D
- B precedes E, F, and H
- F and C precede G
- E and H precede I and J
- C, D, F, and J precede K
- K precedes L
- I, G, and L are terminal activities for the
project
Strategic Project Management
13
SPM Basic PERT/CPM (Part 1)
14Lets Examine the Example Solution
- Solution to be shown in class.
Strategic Project Management
14
SPM Basic PERT/CPM (Part 1)
15Conclusion of Sequencing Techniques
- Well return to ADM in just a few minutes but
first lets complete the set of sequencing
techniques by considering Conditional Diagramming
Strategic Project Management
15
SPM Basic PERT/CPM (Part 1)
16Conditional Diagramming
- Conditional Diagramming methods allow for
probabilistic activities and looping - neither of these are allowed in traditional PDM
or ADM - Conditional diagramming techniques include
Graphical Evaluation and Review Technique (GERT)
and System Dynamics - these are beyond the scope of this course
Strategic Project Management
16
SPM Basic PERT/CPM (Part 1)
17Activity Durations
- The next logical step in Project Time Management
is to determine activity durations. - We are going to defer a detailed discussion of
estimating activity durations until later in the
course. - At this point we need to introduce the concept of
the Critical Path of a project.
Strategic Project Management
17
SPM Basic PERT/CPM (Part 1)
18The Concept of the Critical Path
- The determination of the start and completion
time of each activity on the network diagram
requires a special calculation procedure. - This approach classifies each activity as either
critical or non-critical. - The approach is commonly known as the Critical
Path Method
Strategic Project Management
18
SPM Basic PERT/CPM (Part 1)
19The Concept of the Critical Path (continued)
- A delay in the start or completion of a critical
path activity will cause a delay in the
completion of the entire project. - Non-critical path activities can absorb some
delay in start or completion without impacting
project completion. - The amount of delay which can be absorbed is
known as slack or float.
Strategic Project Management
19
SPM Basic PERT/CPM (Part 1)
20The Concept of the Critical Path (continued)
- There will always be at least one sequence of
activities from the initial node to the terminal
node that is made up entirely of critical
activities. - This is known as the Critical Path of the
Project. - Any delay of a critical path activity will delay
the completion of the project.
Strategic Project Management
20
SPM Basic PERT/CPM (Part 1)
21The Concept of the Critical Path (continued)
- The critical path defines the minimal completion
time for the project. - Multiple critical paths are possible.
- Complete multiple critical paths
- two or more critical paths exist from the initial
node to the terminal node of the project. - rare in uncrashed networks, common in fully
crashed - Partial multiple critical paths
- two or more sets of parallel activities are
critical over some segment of the project. - relatively common
Strategic Project Management
21
SPM Basic PERT/CPM (Part 1)
22Determining the Critical Path
- The critical path is found by a two phase
methodology after activity durations have been
determined. - A forward pass is made through the network
diagram to determine the earliest start time for
each node. - A backward pass is made through the network to
determine the latest completion time for each
node.
Strategic Project Management
22
SPM Basic PERT/CPM (Part 1)
23Determining the Critical Path (continued)
- This is best illustrated through an example.
- Mathematical details in SPM_PERTCPM_Math
- An ADM diagram for a project is shown on the
following page - the activities themselves are not labeled, we
will use the (start node, end node) pair to
uniquely identify activities (e.g., (0,1)) - duration estimates are indicated
Strategic Project Management
23
SPM Basic PERT/CPM (Part 1)
24Class ExampleCritical Path Calculations
Strategic Project Management
24
SPM Basic PERT/CPM (Part 1)
25Forward Pass and Backward Pass
- Solution to be shown in class.
Strategic Project Management
25
SPM Basic PERT/CPM (Part 1)
26The Critical Path
- An activity lies on the critical path if it meets
the three following conditions - The earliest start and latest completion for the
activitys terminal node are equal - The earliest start and latest completion for the
activitys initial node are equal - The difference between the earliest start of the
terminal node and the earliest start of the
initial node is the activity duration.
Strategic Project Management
26
SPM Basic PERT/CPM (Part 1)
27The Critical Path(continued)
- Lets re-examine the example for the critical
path. - Solution to be shown in class.
Strategic Project Management
27
SPM Basic PERT/CPM (Part 1)