Title: Specification EB2678
1Specification EB2678
- Quality Control Requirements for Procured
Materials
Approved for Public Release
2EB2678
- Required in virtually every purchase order
through - Standard Clause 60-29 or
- EB Specifications in the applicable document
section - Guaranteed quality audit topics
Approved for Public Release
3Why Imposed on Suppliers?
- Dept of Navy imposes requirements on Electric
Boat in the form of material control documents - NAVSEA 0900-070-6010
- NAVSEA 0948-LP-045-7010
- Electric Boat required by Navy to pass these
quality requirements on to suppliers through
procurement documents - Compilation of requirements EB2678 defines
level of quality expected from suppliers
Approved for Public Release
4Document Structure - Overview
- Base document Quality Control requirements for
all products - Appendix A Additional Level 1 Material QA
Requirements - Appendix B Contract Compliance Awareness of
Malpractice Prevention - Appendix C Glossary
- Appendix D Notice for Reporting Malpractice or
Fraud Falsification - Electric Boat expects these topics be addressed
in supplier procedures, internally audited, and
flowed down to subtier suppliers if appropriate
Approved for Public Release
5Base Document Addresses
- Submittal of VIRs VPARs SCAR
- VIRs electronic SPARS system submittal
disposition - Interpretation, contract change, conflict,
requirement waiver - Must be registered with EB for SPARS system usage
- VPAR customer approval of special processes
- Obtain approval prior to performance
- SCAR response
- Provide constructive root cause, corrective
action, and preventive action for a nonconforming
condition - Topics will be discussed further in related
modules
Approved for Public Release
6Base Document Addresses (contd.)
- Documentation Objective Quality Evidence (OQE)
- Substantiate conformance to purchase order
- Contains numerous important details
- Designate and document authorized signers for the
supplier - Correction to documents
- Record retention and destruction
- VIR approval for electronic signatures
Approved for Public Release
7Base Document Addresses (contd.)
- Drawing Specification Control
- Must comply with purchase order revision level
even if obsolete, discontinued, or otherwise
unavailable - Submit VIR if necessary
- Change to Design or Service
- Definition of design changes
- VIR submittal requirement
Approved for Public Release
8Base Document Addresses (contd.)
- Material Control
- Addresses Level N and Level 1 material
- Subtier flowdown and controls for material
- Identification must be maintained
- Change of mechanical properties
- Retest and unique reidentification
- DFAR requirements
- Further Level 1 requirements in Appendix A
Approved for Public Release
9Base Document Addresses (contd.)
- Non-conforming Material Control
- Waiver EB only VIR submittal
- Proprietary design Paragraph 4 test
- Include root cause and preventive action
- Include VIR copy with certification
- Manufacturing Special Processes
- Standard clause, drawing, or specification
- VPAR approval PRIOR to performance
Approved for Public Release
10Base Document Addresses (contd.)
- EBSI GSI at supplier facility
- Right of entry supplier and subtier
- Provide assistance and MTE
- Corrective Action System
- Internal and external program (RC, CA, PA)
- Audits
- Internal and external program
Approved for Public Release
11Appendix A for Level 1 Materials Discusses
- General requirements for quality inspection
systems - Compliance with documented inspection/quality
system identified in SC60-5, 60-19, or 60-58 - Flowdown of EB purchase order requirements to
subtiers discussed further during another
module - Material identification control
- Include requirements in Flowdown to subtiers
- Quality representative review of PO for Level
1product - Receipt inspection to ensure compliance with
detailed purchase order and specification
requirements - Suggest checklist for review of test report
contents
Approved for Public Release
12Appendix A for Level 1 Materials Discusses
(continued)
- Raw material storage and physical segregation
- By alloy type, grade, condition
- Ensure every piece of material is identified
- Segregate nonconforming material
- Ensure proper discipline and control within
procedures and by personnel
Approved for Public Release
13Appendix A for Level 1 Materials Discusses
(continued)
- Material traceability throughout all processing,
including all outsourcing. - Initiate and maintain written procedure.
- Note requirements when
- mechanical properties change note that this
requirement is discussed numerous times - marking is removed
- marking is lost need for procedure and
reporting to EB - Maintenance of ALL records
- Documentation trail from melt of raw materials
through shipment of final product
Approved for Public Release
14Appendix A for Level 1 Materials Discusses
(continued)
- Heat treat documentation records
- Supplier is responsible for performance by all
subtiers including heat treaters and the required
documentation - Annotated charts, re-identification, re-testing
- See Par 8.2.b.) for certification traceability
requirements in both directions - Finished product requirements
- Supplier verify all purchase order notes,
standard clauses, specifications, drawings have
been satisfied - Ensure physical identification marking is correct
- Ensure documentation is available and correct
- Electric Boat Source Inspection must verify all
purchase order requirements for Level 1 product
and services
Approved for Public Release
15Appendices B D Purpose
- Need for purchase order compliance and awareness
of malpractice prevention - Not intended to be punitive but rather
informative and to help keep honest people honest - Suggest new hire orientation and periodic
reminders to employees of the need to be aware
and alert to malpractice prevention - EB strongly recommends this information be an
internal program and a Flowdown to subtiers
Approved for Public Release
16Appendix C
- Glossary of terms related to processing of
purchase orders for Electric Boat