Title: PROJECT PHASES


1
PROJECT PHASES
CEM 520 CONSTRUCTION CONTRACTING
ADMINISTRATION Module 1.0 Unit 1.1 By MOHAMMED
JALALUDDIN LECTURER CONSTRUCTION ENGINEERING
MANAGEMENT DEPT
2
Presentation Outline
  • Major Project Phases
  • Planning
  • Design
  • Construction Procurement
  • Construction
  • Project Close out.

3
Objectives of Class
  • To acquire a working knowledge of the principal
    project phases.
  • To identify activities associated with each
    phase of a construction project.
  • To relate the roles and responsibilities of
    different participants during each phase of
    construction
  • To provide an understanding of the design and
    construction process and the roles of the
    different participants, and the types of
    documents produced during each phase

4
Major Project Phases
  • The major phases in the project cycle that are
    common to most design and construction projects
    are
  • Project Planning
  • Design
  • Schematic Design
  • Design Development
  • Contract Documents
  • Construction Procurement (Bidding Phase)
  • Construction
  • Occupancy

5
Project Life Cycle
6
Phase 1 Project Planning
  • The planning stage of the project
  • During this phase of the project the owner
    makes decisions that set the tone for the
    project. All projects begin with an idea or a
    need
  • During this stage the owner
  • selects the project site, and
  • establishes a conceptual estimate, schedule.
  • The most critical decision that is made during
    this project phase is to make a decision as to
    whether or not to proceed with the project
    (called a go/no go decision).

7
Phase 2 DESIGN PHASE
  • Design process involves
  • Schematic Design
  • Talk to owner, rough sketches
  • Design Development
  • Contract Documents
  • Preliminary Cost estimate
  • Develop Preliminary working drawings
  • Develop working drawings with Specifications
  • Bidding and Contract requirements

8
Schematic Design
  • The A/E reviews and evaluates the owners program
    and budget requirements and discusses with the
    owner alternative approaches to the design and
    construction
  • During this phase of the project the design team
    investigates alternate design solutions and
    alternate materials and systems.
  • During schematic design, the A/E prepares
    conceptual design documents. These may include
    Preliminary sketches ,Small scale schematic
    plans, elevations, sections, diagrams,
    renderings, and other graphic and written
    documents, General written description of
    project.
  • The completion of the schematic design phase
    represents approximately 30 percent design
    completion for the project

9
Design Development
  • The design development phase takes the project
    from about 30 percent to approximately 60 percent
    design.
  • It is the time when the design team will be
    evaluating and selecting all the major systems
    and components of the project.
  • During this phase of the project the design
    team is involved in the evaluation and
    finalization of all the architectural components
    and project systems.
  • The project's budget and schedule continue to be
    monitored and adjusted.

10
The Architectural Design Process - General
11
The Architectural Design Process - General
12
Construction Bid Documents
Architect
Structural Engineer
Mechanical Engineer
CAD Drafting Software
Construction Bid Documents
Specifications
Architectural Drawings
Structural Drawings
Mechanical Electrical Drawings
13
Phase 3 Construction Procurement
  • Contractor qualification/bidder list
  • Solicitation
  • Pre-bid meeting/site visit
  • Issue Addenda
  • Proposal preparation
  • Bid/proposal opening
  • Bid/proposal evaluation
  • Award of contract
  • Final negotiation

14
Phase 4 Construction
  • Mobilization
  • Subcontracting
  • Purchasing
  • Permits
  • Site preparation
  • Foundations
  • Interior finishes and equipment

15
Phase 5 Occupancy/Post construction
  • Start-up and testing
  • Leasing
  • Tenant improvements
  • Move-in
  • Operation
  • Correction
  • Repairs/maintenance

16
(No Transcript)
17
(No Transcript)
18
Phase 1 Project planning
  • Owner's consultants
  • prepare budgets
  • prepare/obtain site data
  • develop design criteria
  • Design professional
  • programming
  • budgeting
  • site selection
  • project planning
  • scheduling
  • Owner
  • programming/scope
  • budgeting
  • scheduling
  • project delivery system
  • select/engage/coordinate/pay consultants
  • financing
  • secure regulatory/zoning approvals

19
Phase 2 Design
  • Owner
  • coordinate consultant activities
  • review/approve designs
  • decide construction delivery, contract pricing
    method
  • bidding procedures, requirements
  • secure project financing
  • secure development approvals
  • Owners Consultants
  • develop design criteria for architect
  • develop/document designs
  • coordinate with architect
  • Contractor (if on board)
  • review designs
  • provide estimates
  • Design professional (Architect)
  • coordinate with Owner's consultants
  • manage/coordinate sub consultants
  • project budget/estimate construction costs
  • project schedule
  • recommend project delivery approach
  • design the project
  • prepare drawings and specifications
  • prepare bidding requirements, contract forms
  • Design professionals consultants
  • study and report
  • preliminary design
  • final design drawings and specifications
  • Others
  • zoning and development approval
  • building department plan review and approval

20
Phase 3 Construction procurement
  • Owner
  • identify/qualify contractors
  • issue invitation
  • take bids/proposals
  • secure lender/internal approvals
  • award contract
  • Design professional
  • review substitution requests
  • issue addenda
  • advise on/assist with award
  • prepare contract
  • Contractor
  • review of documents
  • planning
  • estimating
  • subcontractor bidding
  • bid/proposal preparation
  • preliminary submittals
  • Others
  • issue building permits
  • issue surety bonds
  • issue insurance policies
  • implement project financing

21
Phase 4 Construction
  • Owner
  • provide information
  • make decisions
  • make payments
  • coordinate schedules
  • coordinate separate contracts
  • Design Professional
  • on-site project representation
  • submittal review and approval
  • changes processing
  • payment certification
  • Contractor
  • initial submittals
  • secure permits
  • install temporary facilities
  • provide labor, materials, equipment
  • award subcontracts/allocate work
  • manage, supervise, direct
  • determine sequences and procedures
  • maintain schedules
  • implement safety programs
  • correct rejected work
  • Others
  • provide utilities
  • inspections, tests, approvals
  • certificates
  • claims handling

22
Phase 5 Occupancy/post construction
  • Owner
  • take possession
  • building operations
  • move in
  • Design professional
  • inspections/call back
  • building design performance evaluation
  • Contractor
  • testing/startup
  • correct call-back work
  • Others
  • certificate of occupancy
  • permanent financing
  • permanent insurance
  • tenant improvements and occupancy

23
CONCLUSION
  • The major phases in the project cycle are
  • Project Planning
  • Design
  • Schematic Design
  • Design Development
  • Contract Documents
  • Construction Procurement (Bidding Phase)
  • Construction
  • Occupancy
Write a Comment