Research - PowerPoint PPT Presentation

1 / 25
About This Presentation
Title:

Research

Description:

Coordination of PPAP for all initial components through quality process ... Submit prototype prints for purchasing to retrieve component quotes on ... – PowerPoint PPT presentation

Number of Views:43
Avg rating:3.0/5.0
Slides: 26
Provided by: larryc
Category:
Tags: research

less

Transcript and Presenter's Notes

Title: Research


1
Research Development Review
  • ETM5131-Capstone Project
  • NPI Concept Application RD
  • Larry Cochran Summer 2004

2
ETM-5131 Capstone Report
  • This is the final report on research, testing
    and development of a new travel-limiter device
    for the 2004 X-Brand light duty truck concept-unit

3
Introduction - Initial Details
  • 2004 X-Brand truck front McPherson Strut
  • OEM expects to produce 800,000 vehicles in
    FY2004
  • Replacement curve depicts growth to 40,000 units
    annually within 6-years
  • Due to vehicle model, long life-cycle is expected
  • First year this design has been used on any
    Domestic light-duty truck

4
A Look at Potential Sales
10-year sales 15.4-M Total Revenue 5.6-M Net
Profit 420-K units
A graphic look at potential sales, based on known
volumes and initial cost / price projections
5
Problem Statement
  • This project was initiated due to a top-customer
    requesting a specialty design for a high-volume
    vehicle replacement damper
  • Insufficient quantity in itself to warrant
    development
  • New development will provide working solution to
    broader coverage for all customers
  • Current travel-limiter is insufficiently strong
    enough for this application, regardless of
    customer
  • OEM manufacturer is projecting use of the new
    design across all truck platforms for the
    foreseeable future

6
Measures of the Problem
  • Our current welded travel-limiter design is
    constructed to withstand a 4400-9500-lb. axial
    load
  • We have not designed McPherson struts for light
    truck applications before
  • Initial Calculations showed that the X-Brand
    truck would potentially exert up to 10,000-lbs
    axial force onto the limiter. Later reviews
    found the value to require 15,000-lbs axial load
    capacity
  • As the travel-limiters (rod-stop) survival is
    considered a critical characteristic, the
    rod-stop must be designed in such a way as to
    survive 15,000-lbs minimum force

7
Project Objectives
  • To deliver a viable alternative, the following
    conditions must be met within the new design
  • It must prove to be of durable design in the
    field
  • It must be simple in overall design
  • It must work integral to all other designs and
    systems, so that incorporation to all other
    related components causes minimal manufacturing
    difficulties
  • Ideally, it should be non-directionally oriented,
    to reduce the risk of improper manufacturing
    assembly
  • It must be a cost-effective solution
  • Easily sourced at competitive costs
  • It must not significantly increase the overall
    cost of the unit
  • Easily moved to alternative suppliers if needed
    (non-proprietary to supplier)
  • It must meet customer quality and safety
    expectations for this heavy-duty application

8
Specific Deliverables
  • The new rod-stop must not fail to axial loads
    below 15,000-lbs.
  • It will be composed of as few components and
    processes as possible
  • It must not significantly increase the overall
    unit complexity
  • It must not compromise the structural integrity
    of the overall piston-rod assembly
  • In selection, it must take into account
    supply-logistics for necessary components
  • Stocking and re-order points for components must
    be established during startup
  • It must source from existing, approved suppliers
  • Teamwork with suppliers must be established, so
    that the final component can be made within
    specification, taking into account their
    process-capabilities
  • Design-for-Manufacture must be observed to the
    limits possible
  • Must maintain all related DFMEAs, PFMEAs,
    ECRs/ECOs, Benchmarking data, and Project
    Engineering Reports
  • Coordination of PPAP for all initial components
    through quality process

9
Considered Alternatives
  • Several designs to be considered
  • Must pass critical requirements 100
  • Only designs which can do so will be considered
    further
  • Those which pass all empirical tests will be
    compared based on their durability, cost,
    simplicity, and ease-of-manufacture
  • The final selected design will be prototyped into
    assembly for full unit testing, and upon
    approval, manufacture

10
Alternative 1
  • Press-Fit crenellate-filled design
  • Single-piece design
  • Requires special tooling
  • Currently used by OEM tier-1 suppliers
  • Requires rod modification (groove)
  • Eliminates differed-differentiation
  • Increases costs
  • Is this patented? (patent research)
  • Is feasible for application
  • FINAL RESULT REJECTED

11
Alternative 2
  • Free-Floating Rod-Stop with Snap-Ring Retainer
  • 2-piece design
  • Requires grooved rod
  • Eliminates differed-differentiation
  • Increases Costs
  • Generic machine design
  • No patent issues
  • Is feasible design
  • FINAL RESULT
  • FAILED IN PROTOTYPE

12
Alternative 3
  • Split-Diameter (ground-shoulder) piston-rod
  • No-pieces required
  • Rod uses compound diameters
  • Significant rod cost increase
  • No known existing applications
  • Highest Strength, Fail-safe
  • Feasibility depends on rod-grinding process
    availability
  • FINAL RESULT REJECTED

13
Accepted Alternative
  • Counter-Lock Design with Eaton Ring
  • Simple Mechanical Design
  • Two Pieces Ease-of-Manufacture
  • Four Processes
  • Groove Rod
  • Press on Eaton Ring
  • Drop on Rod-Stop
  • Stake Rod-Stop skirt behind ring
  • Strength in excess of 15,000-lbs axial
  • Cost 0.38 each over initial target

14
Alternative Evaluation Criteria
  • Accepted Alternative required to pass all
    empirical testing
  • Withstand axial load minimum of 15,000-lbs.
  • Must not compromise rod bend resistance of .315
    deflection at 10,000-12,500-lb load, applied to
    rod resting on 8.00 center-rests with 2 radii
  • Must be cost-competitive
  • Must be able to source from existing approved
    suppliers
  • Must be able to manufacture with minimal tooling
    costs
  • Must be durable in application
  • Must pass standard approval process
  • Peer-Engineer review
  • Director of Engineering approval
  • Plant Manager approval
  • Quality approval
  • Customer approval
  • Must be able to integrate with existing
    components to the maximum extent possible

15
Project Start Process
  • Collect Initial Data
  • Benchmark known processes and components
  • Make inquiries into available processes and
    knowledge-bases internally
  • Contact suppliers regarding their process
    capabilities
  • Create all relevant prints
  • Hold first meeting to detail pending design
  • Review meeting feedback
  • Provide tentative timeline for departmental
    actions

16
Start Process (continued)
  • Evaluate Alternatives
  • Develop initial prototypes for testing
  • Begin component testing for strength, durability
    and manufacturability
  • Document all testing
  • Maintain testing samples
  • Submit prototype prints for purchasing to
    retrieve component quotes on
  • Calculate per-unit costs as assembled
  • Compile CIP for tooling and NPI, if required
  • ROI
  • IRR
  • DTR
  • Tooling Amortization, if required
  • Start-Up expense (suppliers, production, etc.)
  • Complete and publish lead-time analysis

17
Start Process (continued-2)
  • Develop and Present Recommendation
  • Call 2nd management meeting to formally present
    design
  • Take feedback
  • Present alternatives (if applicable and required)
  • Initiate action plan

18
Project Planning
  • The overall scope of this project is to develop
    and implement a new travel limiter with
    heavy-duty capacity significantly in excess of
    our current component
  • The initial project team is composed of
  • Primary Design Engineer (and Project Champion)
  • Tooling-Process Engineer
  • Sales Representative (customer advocate)
  • Director of Engineering
  • Plant Manager
  • Planning for all forthcoming actions will be
    presented through this core group

19
Project Execution
  • Confirmation of all feasibility considerations
    must first be conducted
  • Prototypes of all alternatives to be created and
    empirically tested
  • Tests and all documentation to be reviewed, with
    consideration to
  • Manufacturability
  • Costs
  • Strength, durability, safety, customer
    satisfaction
  • Component Logistic considerations
  • Time-to-Market timeline considerations
  • Selection of alternative to take to market
  • Delegation of new assembly to standard
    manufacturing protocol

20
Project Closure
  • With attention to the project timeline that
    follows
  • The first prototype offered to the customer
    failed due to insufficient empirical testing
  • The second (Alternative 4, shown previously)
    prototype did pass all field tests and survive as
    per the design
  • Other problem-issues associated with the overall
    project led to the customer leaving Arvinmeritor
    for this product line, and seeking the
    application from a competitor.
  • Competitors are still fighting the durability
    issues associated with the rod-stop
  • We could not solve (in-time) the lower mount
    strength issues which the competitors did.

21
Projected Timeline (part 1 of 3)
22
Project Timeline (part 2 of 3)
23
Project Timeline (part 3 of 3)
24
Course Credits
  • I would like to give credit to a few classes I am
    currently taking at OSU, which have helped in the
    successful execution of this project. They have
    proven to be a valuable information source to
    help improve the quality of not only this project
    presentation, but the actual project itself
  • Benchmarking
  • This course brought to light several things which
    I had not paid sufficient attention to before,
    especially the precept of clearly defining your
    specific benchmark goal before attempting to
    acquire data on the objective.
  • Supply Chain Analysis
  • An excellent course with a strong technical text,
    Designing and Managing the Supply Chain,
    especially chapter 4, which covers the trade offs
    between lot size, inventory lead times versus
    costs. A significant consideration when many of
    our suppliers are foreign, with long logistical
    lines. A bad design which requires revisions may
    catch thousands of components in-transit,
    purchased but never useable.
  • Intro to Strategy, Technology Integration
  • The knowledge gained through the course texts and
    presentations has provided a better understanding
    of what drives new technology and invention in
    corporate business, as well as what corporations
    are looking for in new concepts.

25
References
  • Burgelman, Robert A. Sayles, Leonard R. Inside
    Corporate Innovation. New York, NY. The Free
    Press. 1988.
  • Bossidy, Larry Charan, Ram. Execution The
    Discipline of Getting Things Done. New York, NY.
    Crown Business. 2002.
  • Camp, Robert C. Business Process Benchmarking
    Finding and Implementing Best Practices.
    Milwaukee, WI. ASQ Quality Press. 1995.
  • Simchi-Levi, David Kaminsky, Philip
    Smichi-Levi, Edith. Designing Managing the
    Supply Chain Concepts, Strategies Case
    Studies. New York, NY. McGraw-Hill. 2003.
Write a Comment
User Comments (0)
About PowerShow.com