Title: Research
1Research Development Review
- ETM5131-Capstone Project
- NPI Concept Application RD
- Larry Cochran Summer 2004
2ETM-5131 Capstone Report
- This is the final report on research, testing
and development of a new travel-limiter device
for the 2004 X-Brand light duty truck concept-unit
3Introduction - Initial Details
- 2004 X-Brand truck front McPherson Strut
- OEM expects to produce 800,000 vehicles in
FY2004 - Replacement curve depicts growth to 40,000 units
annually within 6-years - Due to vehicle model, long life-cycle is expected
- First year this design has been used on any
Domestic light-duty truck
4A Look at Potential Sales
10-year sales 15.4-M Total Revenue 5.6-M Net
Profit 420-K units
A graphic look at potential sales, based on known
volumes and initial cost / price projections
5Problem Statement
- This project was initiated due to a top-customer
requesting a specialty design for a high-volume
vehicle replacement damper - Insufficient quantity in itself to warrant
development - New development will provide working solution to
broader coverage for all customers - Current travel-limiter is insufficiently strong
enough for this application, regardless of
customer - OEM manufacturer is projecting use of the new
design across all truck platforms for the
foreseeable future
6Measures of the Problem
- Our current welded travel-limiter design is
constructed to withstand a 4400-9500-lb. axial
load - We have not designed McPherson struts for light
truck applications before - Initial Calculations showed that the X-Brand
truck would potentially exert up to 10,000-lbs
axial force onto the limiter. Later reviews
found the value to require 15,000-lbs axial load
capacity - As the travel-limiters (rod-stop) survival is
considered a critical characteristic, the
rod-stop must be designed in such a way as to
survive 15,000-lbs minimum force
7Project Objectives
- To deliver a viable alternative, the following
conditions must be met within the new design - It must prove to be of durable design in the
field - It must be simple in overall design
- It must work integral to all other designs and
systems, so that incorporation to all other
related components causes minimal manufacturing
difficulties - Ideally, it should be non-directionally oriented,
to reduce the risk of improper manufacturing
assembly - It must be a cost-effective solution
- Easily sourced at competitive costs
- It must not significantly increase the overall
cost of the unit - Easily moved to alternative suppliers if needed
(non-proprietary to supplier) - It must meet customer quality and safety
expectations for this heavy-duty application
8Specific Deliverables
- The new rod-stop must not fail to axial loads
below 15,000-lbs. - It will be composed of as few components and
processes as possible - It must not significantly increase the overall
unit complexity - It must not compromise the structural integrity
of the overall piston-rod assembly - In selection, it must take into account
supply-logistics for necessary components - Stocking and re-order points for components must
be established during startup - It must source from existing, approved suppliers
- Teamwork with suppliers must be established, so
that the final component can be made within
specification, taking into account their
process-capabilities - Design-for-Manufacture must be observed to the
limits possible - Must maintain all related DFMEAs, PFMEAs,
ECRs/ECOs, Benchmarking data, and Project
Engineering Reports - Coordination of PPAP for all initial components
through quality process
9Considered Alternatives
- Several designs to be considered
- Must pass critical requirements 100
- Only designs which can do so will be considered
further - Those which pass all empirical tests will be
compared based on their durability, cost,
simplicity, and ease-of-manufacture - The final selected design will be prototyped into
assembly for full unit testing, and upon
approval, manufacture
10Alternative 1
- Press-Fit crenellate-filled design
- Single-piece design
- Requires special tooling
- Currently used by OEM tier-1 suppliers
- Requires rod modification (groove)
- Eliminates differed-differentiation
- Increases costs
- Is this patented? (patent research)
- Is feasible for application
- FINAL RESULT REJECTED
11Alternative 2
- Free-Floating Rod-Stop with Snap-Ring Retainer
- 2-piece design
- Requires grooved rod
- Eliminates differed-differentiation
- Increases Costs
- Generic machine design
- No patent issues
- Is feasible design
- FINAL RESULT
- FAILED IN PROTOTYPE
12Alternative 3
- Split-Diameter (ground-shoulder) piston-rod
- No-pieces required
- Rod uses compound diameters
- Significant rod cost increase
- No known existing applications
- Highest Strength, Fail-safe
- Feasibility depends on rod-grinding process
availability - FINAL RESULT REJECTED
13Accepted Alternative
- Counter-Lock Design with Eaton Ring
- Simple Mechanical Design
- Two Pieces Ease-of-Manufacture
- Four Processes
- Groove Rod
- Press on Eaton Ring
- Drop on Rod-Stop
- Stake Rod-Stop skirt behind ring
- Strength in excess of 15,000-lbs axial
- Cost 0.38 each over initial target
14Alternative Evaluation Criteria
- Accepted Alternative required to pass all
empirical testing - Withstand axial load minimum of 15,000-lbs.
- Must not compromise rod bend resistance of .315
deflection at 10,000-12,500-lb load, applied to
rod resting on 8.00 center-rests with 2 radii - Must be cost-competitive
- Must be able to source from existing approved
suppliers - Must be able to manufacture with minimal tooling
costs - Must be durable in application
- Must pass standard approval process
- Peer-Engineer review
- Director of Engineering approval
- Plant Manager approval
- Quality approval
- Customer approval
- Must be able to integrate with existing
components to the maximum extent possible
15Project Start Process
- Collect Initial Data
- Benchmark known processes and components
- Make inquiries into available processes and
knowledge-bases internally - Contact suppliers regarding their process
capabilities - Create all relevant prints
- Hold first meeting to detail pending design
- Review meeting feedback
- Provide tentative timeline for departmental
actions
16Start Process (continued)
- Evaluate Alternatives
- Develop initial prototypes for testing
- Begin component testing for strength, durability
and manufacturability - Document all testing
- Maintain testing samples
- Submit prototype prints for purchasing to
retrieve component quotes on - Calculate per-unit costs as assembled
- Compile CIP for tooling and NPI, if required
- ROI
- IRR
- DTR
- Tooling Amortization, if required
- Start-Up expense (suppliers, production, etc.)
- Complete and publish lead-time analysis
17Start Process (continued-2)
- Develop and Present Recommendation
- Call 2nd management meeting to formally present
design - Take feedback
- Present alternatives (if applicable and required)
- Initiate action plan
18Project Planning
- The overall scope of this project is to develop
and implement a new travel limiter with
heavy-duty capacity significantly in excess of
our current component - The initial project team is composed of
- Primary Design Engineer (and Project Champion)
- Tooling-Process Engineer
- Sales Representative (customer advocate)
- Director of Engineering
- Plant Manager
- Planning for all forthcoming actions will be
presented through this core group
19Project Execution
- Confirmation of all feasibility considerations
must first be conducted - Prototypes of all alternatives to be created and
empirically tested - Tests and all documentation to be reviewed, with
consideration to - Manufacturability
- Costs
- Strength, durability, safety, customer
satisfaction - Component Logistic considerations
- Time-to-Market timeline considerations
- Selection of alternative to take to market
- Delegation of new assembly to standard
manufacturing protocol
20Project Closure
- With attention to the project timeline that
follows - The first prototype offered to the customer
failed due to insufficient empirical testing - The second (Alternative 4, shown previously)
prototype did pass all field tests and survive as
per the design - Other problem-issues associated with the overall
project led to the customer leaving Arvinmeritor
for this product line, and seeking the
application from a competitor. - Competitors are still fighting the durability
issues associated with the rod-stop - We could not solve (in-time) the lower mount
strength issues which the competitors did.
21Projected Timeline (part 1 of 3)
22Project Timeline (part 2 of 3)
23Project Timeline (part 3 of 3)
24Course Credits
- I would like to give credit to a few classes I am
currently taking at OSU, which have helped in the
successful execution of this project. They have
proven to be a valuable information source to
help improve the quality of not only this project
presentation, but the actual project itself - Benchmarking
- This course brought to light several things which
I had not paid sufficient attention to before,
especially the precept of clearly defining your
specific benchmark goal before attempting to
acquire data on the objective. - Supply Chain Analysis
- An excellent course with a strong technical text,
Designing and Managing the Supply Chain,
especially chapter 4, which covers the trade offs
between lot size, inventory lead times versus
costs. A significant consideration when many of
our suppliers are foreign, with long logistical
lines. A bad design which requires revisions may
catch thousands of components in-transit,
purchased but never useable. - Intro to Strategy, Technology Integration
- The knowledge gained through the course texts and
presentations has provided a better understanding
of what drives new technology and invention in
corporate business, as well as what corporations
are looking for in new concepts.
25References
- Burgelman, Robert A. Sayles, Leonard R. Inside
Corporate Innovation. New York, NY. The Free
Press. 1988. - Bossidy, Larry Charan, Ram. Execution The
Discipline of Getting Things Done. New York, NY.
Crown Business. 2002. - Camp, Robert C. Business Process Benchmarking
Finding and Implementing Best Practices.
Milwaukee, WI. ASQ Quality Press. 1995. - Simchi-Levi, David Kaminsky, Philip
Smichi-Levi, Edith. Designing Managing the
Supply Chain Concepts, Strategies Case
Studies. New York, NY. McGraw-Hill. 2003.