Commissioning and Validation of Pharmacy Cleanroom Facilities - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

Commissioning and Validation of Pharmacy Cleanroom Facilities

Description:

The URS forms basis of the of the Design Qualification (DQ) ... Installation Qualification ... Operational Qualification (OQ) ... – PowerPoint PPT presentation

Number of Views:534
Avg rating:3.0/5.0
Slides: 16
Provided by: Ste56
Category:

less

Transcript and Presenter's Notes

Title: Commissioning and Validation of Pharmacy Cleanroom Facilities


1
Commissioning and Validation of Pharmacy
Cleanroom Facilities
  • Steve Willis
  • Pharmaceutical Business Development Manager
  • Daw Technologies

2
Introduction
  • Overview of approach
  • User Requirement Specification
  • Design Qualification
  • Installation Qualification
  • Operational Qualification Physical and
    Microbiological
  • Process Validation
  • Specific Problems relating to PFI

3
Overview
  • Project must be managed formally from outset to
    maximise the chance of success
  • By end user inclusive all disciplines
  • Relevant Regulatory Body
  • Early contact with potential providers

4
User Requirement Specification (URS)
  • This drawn up by the end user detailing exactly
    what the requirements for the facility will.
  • Must be as detailed as possible
  • Room Data sheets detailing
  • Room dimensions
  • Construction materials
  • Physical Parameters
  • Equipment
  • Occupancy levels

5
User Requirement Specification cont.
  • The URS forms basis of the of the Design
    Qualification (DQ)
  • This will in turn dictate how the facility will
    perform
  • Even at this stage the commissioning of the
    facility is dictated and difficult to rectify
    later

6
Design Qualification (DQ)
  • This can be considered the first stage of the
    validation of a new facility
  • Provides documentary evidence complies with all
    parameters set out in URS and complies with cGMP
  • Provides technical specification for all fabric
    and equipment to facilitate audit trail
  • Details how physical parameters of facility will
    be attained and maintained e.g. temp, RAC etc

7
Design Qualification cont
  • All information must be formally agreed by all
    parties
  • Large pieces of equipment to be installed e.g.
    Autoclaves need to undergo Factory Acceptance
    Tests and Site Acceptance Tests must be performed
    by the supplier and all relevant data provided
  • This activity usually occurs between DQ and IQ

8
Installation Qualification
  • Documented demonstration that all systems and
    operations are installed correctly and interface
    with existing systems
  • IQ is referenced back to DQ requirements
  • Tends to be mainly M E
  • Technical, Operational and Maintenance data must
    be supplied for all equipment and formally
    approved by all parties
  • Review of (OQ) data may be required to verify
    results

9
Operational Qualification (OQ)
  • Documented evidence that the facility meets all
    parameters detailed in the URS and DQ
  • Complex activity usually performed by specialist
    provider.
  • All testing should be witnessed by appropriate
    designated staff from the end user to ensure all
    tests are performed correctly

10
Operational Qualification Cont
  • Tests routinely performed may include
  • Room temperature and humidity tests. In use loads
    should be artificially achieved
  • Room Pressure Differentials and calibration of
    gauges
  • Room Air Change Rates
  • Filter integrity tests
  • Air flow Patterns
  • Airborne particle counts
  • Particle decay rates

11
Operational Qualification Cont
  • Issues to be wary of
  • Particle counts are performed in the unmanned
  • All equipment has current calibration
    certificates
  • Documentation routinely provided is acceptable to
    the MHRA
  • All equipment is in use e.g. isolators

12
Operational Qualification Cont
  • Microbiological validation follows
  • Usually performed by end user in the unmanned
    state in first instance
  • Fully documented plan must be in place detailing
    information such as
  • Tests to be performed
  • Duration and frequency of tests
  • Acceptance criteria
  • Exception report and action plan
  • Responsibilities of staff

13
Operational Qualification Cont
  • After completion all OQ documentation should be
    collated including that for equipment e.g.
    isolators.
  • Formal approval must documented by approved
    personnel

14
Summary
  • Control must be exerted from the beginning to
    assure greatest chance of success
  • The MHRA will go through all documentation from
    URS to OQ, PQ and Process Validation in great
    detail during 1st inspection
  • This is of particular importance when involved
    with PFI
  • Pharmacy staff may find it difficult to have
    input in the early stages

15
Summary Cont
  • Dealing with main contractors who may have little
    or no experience of pharmaceutical projects
  • They are working on very tight profit margins
  • They may subcontract the project to the several
    different general contractors on site
Write a Comment
User Comments (0)
About PowerShow.com