MS4801 Project Management Week 8, Chapter 9 Cost Planning - PowerPoint PPT Presentation

1 / 29
About This Presentation
Title:

MS4801 Project Management Week 8, Chapter 9 Cost Planning

Description:

MS4801 Project Management Week 8, Chapter 9 Cost Planning – PowerPoint PPT presentation

Number of Views:46
Avg rating:3.0/5.0
Slides: 30
Provided by: VGlennFu
Category:

less

Transcript and Presenter's Notes

Title: MS4801 Project Management Week 8, Chapter 9 Cost Planning


1
MS4801 Project ManagementWeek 8, Chapter 9Cost
Planning Performance
2
Project Cost Estimates
  • Cost starts when planning begins (proposal).
  • The cost section may include
  • Labor
  • Materials
  • Subcontractors and consultants (if used)
  • Equipment and facilities rental
  • Travel

4
3
Project Budgeting Two Steps
  • First, the project cost estimate is allocated to
    the various work packages in the project work
    breakdown structure. (see next slide)
  • Second, the budget for each work package is
    distributed over the duration of the work package.

5
4
(No Transcript)
5
Project Budgeting Two Steps
  • First, the project cost estimate is allocated to
    the various work packages in the project work
    breakdown structure.
  • Second, the budget for each work package is
    distributed over the duration of the work
    package. (see next slide)

5
6
(No Transcript)
7
Allocating Total Budgeted Cost
  • Allocating total project costs for the various
    elements establishes a total budgeted cost (TBC)
    for each work package.
  • Two approaches to establishing the TBC for each
    work package top-down and bottom-up.
  • When all budgets are summed, they cannot exceed
    the TBC.

6
8
Cumulative Budgeted Cost
  • A cost is determined for each period.
  • The cumulative budgeted cost (CBC) is the amount
    that was budgeted to accomplish the work that was
    scheduled to be performed up to that point in
    time. (see next slide)
  • One uses the CBC as the standard against which
    actual cost is compared.

7
9
(No Transcript)
10
Determining Actual Cost
  • Track actual cost by establishing a system to
    collect data on funds actually expended.
  • Periodically assign a portion of the total
    committed cost to actual cost.
  • Total actual and committed cost by work package
    for comparison to the CBC.
  • Cumulative actual cost (CAC) should be
    calculated.

8
11
(No Transcript)
12
Value of Work Performed
  • Earned value is the value of the work actually
    performed.
  • Determine earned value by collecting data on the
    percent complete for each work package.
  • Convert this percentage to a dollar amount by
    multiplying the TBC of the work package by the
    percent complete.

9
13
Project Variance
14
Earned Value Comparison
  • Budgeted Costs
  • Scheduled Costs
  • Actual Costs
  • Work Performed Costs

15
Earned Value Technique
  • Cost data or Schedule data alone lead to
    distorted perception of what is happening
  • Solution Earned Value Calculation
  • BCWS (CBC) Budgeted cost of work scheduled
  • ACWP (CAC) Actual cost of work performed
  • BCWP Budgeted cost of work performed (earned
    value)

16
Example
  • Invitations BCWS 500.00, 5 days duration
  • Printer Completes Order Day 4
  • ACWP Pay Printer 350.00
  • BCWP (day 4 of 5 80) 400
  • What do these totals tell you? Good / bad news?

Numbers identify slippage of 50
17
50/50 Example
  • Invitations BCWS 500.00, 5 days duration
  • Printer Completes Order Day 4
  • ACWP Pay Printer 350.00
  • BCWP (50) 250
  • What do these totals tell you? Good / bad news?

Numbers identify gain of 150
Value in this approach is realized when you have
many activities. Approximating 50/50 will
provide more realistic portrayal of budget status
18
Cost Performance Analysis Four Measures
  • TBC (total budgeted cost) BCWS
  • CBC (cumulative budgeted cost) ACWP
  • CAC (cumulative actual cost) BCWP
  • CEV (cumulative earned value) EV

10
19
(No Transcript)
20
Cost Control
  • The key is to analyze cost performance on a
    regular and timely basis.
  • Identify cost variances and inefficiencies early.

14
21
Cost Control (Cont.)
  • Involves the following
  • Analyzing cost performance to determine which
    work packages may require corrective action.
  • Deciding what corrective action should be taken
  • Revising the project plan.

15
22
Ways to Reduce Costs of Activities
  • Substitute less expensive materials.
  • Assign a person with greater expertise to perform
    or help with the activity.
  • Reduce the scope or requirements.
  • Increase productivity through improved methods or
    technology.

16
23
Project Costs
  • Total Cost direct indirect costs
  • Indirect costs continue for life of project
  • Direct costs grow at an increasing rate as
    project duration is reduced from planned duration.

24
Crashing
  • Shortening an activity is called crashing
  • Crash time shortest possible time to complete
  • Crash cost direct cost for completing activity
  • Both normal and crash data collected from those
    familiar with activity

25
Accelerating Completion - TIME
  • Add resources
  • Outsource project work
  • Schedule overtime
  • Establish a core team
  • Do it twice
  • Fast-tracking (move from sequential to parallel
    activities)
  • Critical-chain
  • Brainstorm
  • Reduce scope
  • Phase project delivery
  • Compromise quality

26
Cost Reduction - COST
  • Reduce scope
  • Have owner take more responsibility
  • Outsource
  • Brainstorm

27
Managing (avoiding) Change
  • Establish boundaries for change
  • Establish consistent project management practices
    (have a system)
  • Approvals
  • Common risks (subcontractors, dispersed teams,
    etc.)
  • Define, Plan, Execute, Close Out (project life
    cycle)
  • Create standard deliverables

28
Comparing Changes
  • Trade-Off Analysis
  • Determine rationale for change (logical or
    political)
  • Affirm project goals/objectives
  • Determine change effect on project success
  • Analyze (hold time and budget constant) to find
    other options
  • Zero-Base Budget Approach
  • List all the desired project outcomes
  • Rewrite the list in priority order
  • Write costs for each outcome until you have
    exhausted budget
  • Draw line at outcome that exhausts budget
  • Activities below line are low priority

29
Zero-Base Budget - 20,000
  • Beautiful ceremony
  • Fabulous food
  • Stunning dress
  • Close friends involved
  • Married by April 22
  • Happy bride and groom
  • 1 Happy bride and groom (priceless)
  • 2 Married by April 22 (2000)
  • 3 Stunning dress (8,000)
  • 4 Beautiful ceremony (3000)
  • 5 Fabulous food (7,000)
  • 6 Close friends involved (2500)
Write a Comment
User Comments (0)
About PowerShow.com