Title: MS4801 Project Management Week 8, Chapter 9 Cost Planning
1MS4801 Project ManagementWeek 8, Chapter 9Cost
Planning Performance
2Project Cost Estimates
- Cost starts when planning begins (proposal).
- The cost section may include
- Labor
- Materials
- Subcontractors and consultants (if used)
- Equipment and facilities rental
- Travel
4
3Project Budgeting Two Steps
- First, the project cost estimate is allocated to
the various work packages in the project work
breakdown structure. (see next slide) - Second, the budget for each work package is
distributed over the duration of the work package.
5
4(No Transcript)
5Project Budgeting Two Steps
- First, the project cost estimate is allocated to
the various work packages in the project work
breakdown structure. - Second, the budget for each work package is
distributed over the duration of the work
package. (see next slide)
5
6(No Transcript)
7Allocating Total Budgeted Cost
- Allocating total project costs for the various
elements establishes a total budgeted cost (TBC)
for each work package. - Two approaches to establishing the TBC for each
work package top-down and bottom-up. - When all budgets are summed, they cannot exceed
the TBC.
6
8Cumulative Budgeted Cost
- A cost is determined for each period.
- The cumulative budgeted cost (CBC) is the amount
that was budgeted to accomplish the work that was
scheduled to be performed up to that point in
time. (see next slide) - One uses the CBC as the standard against which
actual cost is compared.
7
9(No Transcript)
10Determining Actual Cost
- Track actual cost by establishing a system to
collect data on funds actually expended. - Periodically assign a portion of the total
committed cost to actual cost. - Total actual and committed cost by work package
for comparison to the CBC. - Cumulative actual cost (CAC) should be
calculated.
8
11(No Transcript)
12Value of Work Performed
- Earned value is the value of the work actually
performed. - Determine earned value by collecting data on the
percent complete for each work package. - Convert this percentage to a dollar amount by
multiplying the TBC of the work package by the
percent complete.
9
13Project Variance
14Earned Value Comparison
- Budgeted Costs
- Scheduled Costs
- Actual Costs
- Work Performed Costs
15Earned Value Technique
- Cost data or Schedule data alone lead to
distorted perception of what is happening - Solution Earned Value Calculation
- BCWS (CBC) Budgeted cost of work scheduled
- ACWP (CAC) Actual cost of work performed
- BCWP Budgeted cost of work performed (earned
value)
16Example
- Invitations BCWS 500.00, 5 days duration
- Printer Completes Order Day 4
- ACWP Pay Printer 350.00
- BCWP (day 4 of 5 80) 400
- What do these totals tell you? Good / bad news?
Numbers identify slippage of 50
1750/50 Example
- Invitations BCWS 500.00, 5 days duration
- Printer Completes Order Day 4
- ACWP Pay Printer 350.00
- BCWP (50) 250
- What do these totals tell you? Good / bad news?
Numbers identify gain of 150
Value in this approach is realized when you have
many activities. Approximating 50/50 will
provide more realistic portrayal of budget status
18Cost Performance Analysis Four Measures
- TBC (total budgeted cost) BCWS
- CBC (cumulative budgeted cost) ACWP
- CAC (cumulative actual cost) BCWP
- CEV (cumulative earned value) EV
10
19(No Transcript)
20Cost Control
- The key is to analyze cost performance on a
regular and timely basis. - Identify cost variances and inefficiencies early.
14
21Cost Control (Cont.)
- Involves the following
- Analyzing cost performance to determine which
work packages may require corrective action. - Deciding what corrective action should be taken
- Revising the project plan.
15
22Ways to Reduce Costs of Activities
- Substitute less expensive materials.
- Assign a person with greater expertise to perform
or help with the activity. - Reduce the scope or requirements.
- Increase productivity through improved methods or
technology.
16
23Project Costs
- Total Cost direct indirect costs
- Indirect costs continue for life of project
- Direct costs grow at an increasing rate as
project duration is reduced from planned duration.
24Crashing
- Shortening an activity is called crashing
- Crash time shortest possible time to complete
- Crash cost direct cost for completing activity
- Both normal and crash data collected from those
familiar with activity
25Accelerating Completion - TIME
- Add resources
- Outsource project work
- Schedule overtime
- Establish a core team
- Do it twice
- Fast-tracking (move from sequential to parallel
activities) - Critical-chain
- Brainstorm
- Reduce scope
- Phase project delivery
- Compromise quality
26Cost Reduction - COST
- Reduce scope
- Have owner take more responsibility
- Outsource
- Brainstorm
27Managing (avoiding) Change
- Establish boundaries for change
- Establish consistent project management practices
(have a system) - Approvals
- Common risks (subcontractors, dispersed teams,
etc.) - Define, Plan, Execute, Close Out (project life
cycle) - Create standard deliverables
28Comparing Changes
- Trade-Off Analysis
- Determine rationale for change (logical or
political) - Affirm project goals/objectives
- Determine change effect on project success
- Analyze (hold time and budget constant) to find
other options - Zero-Base Budget Approach
- List all the desired project outcomes
- Rewrite the list in priority order
- Write costs for each outcome until you have
exhausted budget - Draw line at outcome that exhausts budget
- Activities below line are low priority
29Zero-Base Budget - 20,000
- Beautiful ceremony
- Fabulous food
- Stunning dress
- Close friends involved
- Married by April 22
- Happy bride and groom
- 1 Happy bride and groom (priceless)
- 2 Married by April 22 (2000)
- 3 Stunning dress (8,000)
- 4 Beautiful ceremony (3000)
- 5 Fabulous food (7,000)
- 6 Close friends involved (2500)