PROJECT MANAGEMENT - PowerPoint PPT Presentation

1 / 31
About This Presentation
Title:

PROJECT MANAGEMENT

Description:

PROJECT MANAGEMENT Outline What is project mean? Examples of projects Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM – PowerPoint PPT presentation

Number of Views:352
Avg rating:3.0/5.0
Slides: 32
Provided by: Sof62
Category:

less

Transcript and Presenter's Notes

Title: PROJECT MANAGEMENT


1
PROJECT MANAGEMENT
  • Outline
  • What is project mean?
  • Examples of projects
  • Project Planning and Control
  • Project Life Cycle
  • Gantt Chart
  • PERT/CPM

2
What is Project?
  • What is the different between normal business
    activities and Project?
  • Project
  • Unique, one time operations design to
    accomplish a specific set of objectives in a
    limited time frame.

3
Examples of project
  1. Building a house
  2. Building a factory
  3. Add assembly line in the factory
  4. Merging to companies
  5. Managing political campaign
  6. Designing a new product
  7. Soft ware development

4
In project a lot of problem arise? Why?
  • a lot of activities should be handles
  • Limited time
  • Restricted resources

5
Project Planning and Control
  • Definition of Project Management
  • Work Breakdown Structure
  • Project Control
  • Organizational Structures
  • Critical Path Scheduling
  • CPM with a Single Time
  • CPM with Three Activity Time Estimates

6
Project Management
  • Project
  • Lengthy network of activities needed to complete
    a major output.
  • Project Management
  • Planning, execution, and controlling resources to
    needed to complete the project.

7
Project Life Cycle
  • Definition
  • Why we need to start new project
  • Feasibility Analysis (Cost, Benefit , risk of
    under taking a project)
  • Planning
  • Details of the work, estimates time, Human
    resource and cost
  • Execution
  • During which a project itself is done
  • Termination
  • During which closer is achieved

8
Work Breakdown Structure
9
Project Control Gantt Chart
  • The Gantt chart is a popular tool for planning
    and scheduling simple project.
  • It enables a manager to initially schedule
    project activities and then to monitor progress
    over time by comparing planned progress to actual
    progress

10
Project Control Gantt Chart
a
b
a
c
b
d
c
d
d
11
PERT and CPM
  • PERT (program evaluation and review technique)
  • U.S. Navy Special Projects Office (1958)
  • Polaris missile project
  • CPM (critical path method)
  • J. E. Kelly of Remington-Rand and M. R. Walker of
    Du Pont (1957)
  • Scheduling maintenance shutdowns of chemical
    processing plants

12
Questions answered by PERT/CPM
  • When will the entire project be completed?
  • What are the critical activities or tasks in the
    project, that is, the ones that will delay the
    entire project if they are late?
  • Which are the non-critical activities, that is,
    the ones that can run late without delaying the
    entire projects completion?
  • What is the probability that the project will be
    completed by a specific date?

13
Questions answered by PERT/CPM
  • At any particular date, is the project on
    schedule, behind schedule, or ahead of schedule?
  • On any given date, is the money spent equal to,
    less than, or greater than the budgeted amount?
  • Are there enough resources available to finish
    the project on time?
  • If the project is to be finished in a shorter
    amount of time, what is the best way to
    accomplish this at the least cost?

14
To Find Critical Path ???
  • To find the critical path, need to determine the
    following quantities for each activity in the
    network
  • 1. Earliest start time (ES) the earliest time an
    activity can begin without violation of immediate
    predecessor requirements.
  • 2. Earliest finish time (EF) the earliest time
    at which an activity can end.
  • 3. Latest start time (LS) the latest time an
    activity can begin without delaying the entire
    project.
  • 4. Latest finish time (LF) the latest time an
    activity can end without delaying the entire
    project.

15
CPM with Single Time Estimate
Consider the following consulting project
Develop a critical path diagram and determine
the duration of the critical path and slack times
for all activities
16
First draw the network
C, 1
17
Determine early start and early finish times
ES4 EF6
ES0 EF2
ES2 EF3
ES3 EF4
?
C, 1
ES4 EF9
18
When I can start depends on when predecessors
finish.
ES4 EF6
ES0 EF2
ES2 EF3
ES3 EF4
C, 1
ES4 EF9
19
Determine late starts and late finish times
ES4 EF6
ES0 EF2
ES2 EF3
ES3 EF4
LS7 LF9
C, 1
ES4 EF9
LS14 LF15
LS9 LF14
?
LS4 LF9
20
Dont delay the project
ES4 EF6
ES0 EF2
ES2 EF3
ES3 EF4
LS7 LF9
C, 1
ES4 EF9
LS14 LF15
LS9 LF14
LS4 LF9
21
Critical Path Slack
ES4 EF6
D, 2
ES0 EF2
ES2 EF3
ES3 EF4
LS7 LF9
C, 1
ES4 EF9
LS14 LF15
LS9 LF14
E, 5
LS4 LF9
Duration 15 weeks
22
Probabilistic Time Estimates
  • Optimistic time
  • Time required under optimal conditions
  • Pessimistic time
  • Time required under worst conditions
  • Most likely time
  • Most probable length of time that will be required

23
Probabilistic Estimates
Figure 17.8
24
Expected Time
te expected time to optimistic time tm most
likely time tp pessimistic time
25
Variance
?2 variance to optimistic time tp
pessimistic time
26
CPM with Three Activity Time Estimates
Find the estimated time and variance of each
activity?
27
Expected Times
28
PERT/ CPM
  • CPM uses two sets of time and cost estimates for
    activities
  • A normal time and cost and
  • A crash time and cost
  • The normal cost is an estimate of cost to
    complete an activity in normal time.
  • The crash time is the shortest possible activity
    time.
  • Crash cost is the cost of completing the activity
    on a crash or deadline basis.

29
Project Crashing with PERT/CPM Four Steps
  • Find the normal critical path and identify the
    critical activities.
  • Compute the crash cost per week (or other time
    period) for all activities in the network.
  • This process uses the following formula

30
Project Crashing with PERT/CPM Four Steps
  • 3. Select the activity on the critical path with
    the smallest crash cost per week.
  • Crash this activity to the maximum extent
    possible or to the point at which your desired
    deadline has been reached
  • 4. Check to be sure that the critical path you
    were crashing is still critical.
  • Often, a reduction in activity time along the
    critical path causes a non-critical path or paths
    to become critical.
  • If the critical path is still the longest path
    through the network, return to step 3.
  • If not, find the new critical path and return to
    step 2.

31
Subproject
  • For extremely large projects, an activity may be
    made of several smaller sub-activities.
  • Each activity might be viewed as a smaller
    project or a subproject of the original project.
  • The person in charge of the activity might wish
    to create a PERT/CPM chart for managing this
    subproject.
  • Many software packages have the ability to
    include several levels of subprojects
Write a Comment
User Comments (0)
About PowerShow.com