Title: PROJECT MANAGEMENT
1PROJECT MANAGEMENT
- Outline
- What is project mean?
- Examples of projects
- Project Planning and Control
- Project Life Cycle
- Gantt Chart
- PERT/CPM
2What is Project?
- What is the different between normal business
activities and Project? - Project
- Unique, one time operations design to
accomplish a specific set of objectives in a
limited time frame.
3Examples of project
- Building a house
- Building a factory
- Add assembly line in the factory
- Merging to companies
- Managing political campaign
- Designing a new product
- Soft ware development
4In project a lot of problem arise? Why?
- a lot of activities should be handles
- Limited time
- Restricted resources
5Project Planning and Control
- Definition of Project Management
- Work Breakdown Structure
- Project Control
- Organizational Structures
- Critical Path Scheduling
- CPM with a Single Time
- CPM with Three Activity Time Estimates
6Project Management
- Project
- Lengthy network of activities needed to complete
a major output. - Project Management
- Planning, execution, and controlling resources to
needed to complete the project. -
7Project Life Cycle
- Definition
- Why we need to start new project
- Feasibility Analysis (Cost, Benefit , risk of
under taking a project) - Planning
- Details of the work, estimates time, Human
resource and cost - Execution
- During which a project itself is done
- Termination
- During which closer is achieved
8Work Breakdown Structure
9Project Control Gantt Chart
- The Gantt chart is a popular tool for planning
and scheduling simple project. - It enables a manager to initially schedule
project activities and then to monitor progress
over time by comparing planned progress to actual
progress
10Project Control Gantt Chart
a
b
a
c
b
d
c
d
d
11PERT and CPM
- PERT (program evaluation and review technique)
- U.S. Navy Special Projects Office (1958)
- Polaris missile project
- CPM (critical path method)
- J. E. Kelly of Remington-Rand and M. R. Walker of
Du Pont (1957) - Scheduling maintenance shutdowns of chemical
processing plants
12Questions answered by PERT/CPM
- When will the entire project be completed?
- What are the critical activities or tasks in the
project, that is, the ones that will delay the
entire project if they are late? - Which are the non-critical activities, that is,
the ones that can run late without delaying the
entire projects completion? - What is the probability that the project will be
completed by a specific date?
13Questions answered by PERT/CPM
- At any particular date, is the project on
schedule, behind schedule, or ahead of schedule? - On any given date, is the money spent equal to,
less than, or greater than the budgeted amount? - Are there enough resources available to finish
the project on time? - If the project is to be finished in a shorter
amount of time, what is the best way to
accomplish this at the least cost?
14To Find Critical Path ???
- To find the critical path, need to determine the
following quantities for each activity in the
network - 1. Earliest start time (ES) the earliest time an
activity can begin without violation of immediate
predecessor requirements. - 2. Earliest finish time (EF) the earliest time
at which an activity can end. - 3. Latest start time (LS) the latest time an
activity can begin without delaying the entire
project. - 4. Latest finish time (LF) the latest time an
activity can end without delaying the entire
project.
15CPM with Single Time Estimate
Consider the following consulting project
Develop a critical path diagram and determine
the duration of the critical path and slack times
for all activities
16First draw the network
C, 1
17Determine early start and early finish times
ES4 EF6
ES0 EF2
ES2 EF3
ES3 EF4
?
C, 1
ES4 EF9
18When I can start depends on when predecessors
finish.
ES4 EF6
ES0 EF2
ES2 EF3
ES3 EF4
C, 1
ES4 EF9
19Determine late starts and late finish times
ES4 EF6
ES0 EF2
ES2 EF3
ES3 EF4
LS7 LF9
C, 1
ES4 EF9
LS14 LF15
LS9 LF14
?
LS4 LF9
20Dont delay the project
ES4 EF6
ES0 EF2
ES2 EF3
ES3 EF4
LS7 LF9
C, 1
ES4 EF9
LS14 LF15
LS9 LF14
LS4 LF9
21Critical Path Slack
ES4 EF6
D, 2
ES0 EF2
ES2 EF3
ES3 EF4
LS7 LF9
C, 1
ES4 EF9
LS14 LF15
LS9 LF14
E, 5
LS4 LF9
Duration 15 weeks
22Probabilistic Time Estimates
- Optimistic time
- Time required under optimal conditions
- Pessimistic time
- Time required under worst conditions
- Most likely time
- Most probable length of time that will be required
23Probabilistic Estimates
Figure 17.8
24Expected Time
te expected time to optimistic time tm most
likely time tp pessimistic time
25Variance
?2 variance to optimistic time tp
pessimistic time
26CPM with Three Activity Time Estimates
Find the estimated time and variance of each
activity?
27Expected Times
28PERT/ CPM
- CPM uses two sets of time and cost estimates for
activities - A normal time and cost and
- A crash time and cost
- The normal cost is an estimate of cost to
complete an activity in normal time. - The crash time is the shortest possible activity
time. - Crash cost is the cost of completing the activity
on a crash or deadline basis.
29Project Crashing with PERT/CPM Four Steps
- Find the normal critical path and identify the
critical activities. - Compute the crash cost per week (or other time
period) for all activities in the network. - This process uses the following formula
30Project Crashing with PERT/CPM Four Steps
- 3. Select the activity on the critical path with
the smallest crash cost per week. - Crash this activity to the maximum extent
possible or to the point at which your desired
deadline has been reached - 4. Check to be sure that the critical path you
were crashing is still critical. - Often, a reduction in activity time along the
critical path causes a non-critical path or paths
to become critical. - If the critical path is still the longest path
through the network, return to step 3. - If not, find the new critical path and return to
step 2.
31Subproject
- For extremely large projects, an activity may be
made of several smaller sub-activities. - Each activity might be viewed as a smaller
project or a subproject of the original project. - The person in charge of the activity might wish
to create a PERT/CPM chart for managing this
subproject. - Many software packages have the ability to
include several levels of subprojects