Superintendents Proposed Capital Improvement Plan 20092019 - PowerPoint PPT Presentation

1 / 25
About This Presentation
Title:

Superintendents Proposed Capital Improvement Plan 20092019

Description:

... reviews enrollment/housing/population trends annually to determine new school ... CAR. BRP. Replace. HVAC. Replace. Roofs. Major Maintenance $14,313,400 ... – PowerPoint PPT presentation

Number of Views:29
Avg rating:3.0/5.0
Slides: 26
Provided by: Naka4
Category:

less

Transcript and Presenter's Notes

Title: Superintendents Proposed Capital Improvement Plan 20092019


1
Superintendents Proposed Capital Improvement
Plan 2009-2019
  • November 6, 2008

2
Does the school division have any capital needs
for the 2009-2019 planning period?
YES!
3
How Are the School Divisions Capital Needs
Outlined in the CIP?
  • Projects listed by middle school planning area
  • Project Summary Tables
  • Table 39 in current year dollars
  • Table 39A in inflation dollars (5.6)
  • Major maintenance projects listed by priority
    based on need (by project and by year)

4
CIP Priority ProjectsYears 1-5 (2009-14)
5
Why Are Major Mechanical/Maintenance Repairs
Needed?
  • Systems and parts have a finite life
  • Scarcity or unavailability of older parts
  • Increased operational costs
  • Increased operational failures (example no heat
    more frequently and for longer periods)
  • No temporary fix for failed roofs or HVAC systems

6
Why Are Modernization Projects Needed?
  • Aging facilities that require updating
  • Replacement of interior finishes (flooring,
    lighting, doors hardware, lockers, paint, etc.)
  • Installation of new technology
  • Replacement of exterior finishes (parking lot
    surfaces, exterior lighting, canopies, etc.)
  • Improve safety

7
Why are New School Projects Needed?
  • Reduce reliance on portable classrooms
  • Provide additional permanent
  • classroom space
  • Ease overcrowding of core
  • facilities at existing schools

It is important to note staff reviews
enrollment/housing/population trends annually to
determine new school needs and proposed timelines
8
Year 1 CIP Projects (2009-10)19,102,300
Major Maintenance 18,180,400
Mixing boxes only
9
Year 1 CIP Projects (2009-10)19,102,300
10
Year 1 CIP Projects (2009-10)Highlights
  • 95 of costs are for major maintenance (HVAC
    roof replacements)
  • 5 of costs are for CAS repairs and repaving at 3
    schools
  • No modernization, addition and/or renovation
    projects
  • No new school projects

19,102,300
11
Year 2 CIP Projects (2010-11)27,862,500
Major Maintenance 14,313,400
12
Year 2 CIP Projects (2010-11)27,862,500
13
Year 2 CIP Projects (2010-11)Highlights
  • 51 of costs are for major maintenance (HVAC
    roof replacements)
  • No construction costs for facilities but does
    include A/E costs for
  • modernization at 2 schools
  • the 8th high school (Elbow Rd./Centerville
    Trpke.)

27,862,500
14
Year 3 CIP Projects (2011-12)53,439,400
Major Maintenance 9,291,100
15
Year 3 CIP Projects (2011-12)53,439,400
16
Year 4 CIP Projects (2012-13)230,627,900
Major Maintenance 6,243,100
17
Year 4 CIP Projects (2012-13)230,627,900
18
Year 5 CIP Projects (2013-14)48,396,400
Major Maintenance 17,233,800
19
Year 5 CIP Projects (2013-14)48,396,400
20
2009-2014 CIP Summary
  • Most pressing funding needs are
  • Major maintenance projects
  • If not funded in a timely manner, this portion of
    the CIP will increases as more needs arise
  • Modernization of aging facilities
  • 8th high school (Elbow Rd./ Centerville Trpke.)
    to provide relief to IRHS, OSHS, HHS GBHS

21
2009-2014 Five-Year Grand Total(Inflated Dollars)
466,751,400
22
Extended Public Hearing Work Session
Coverage700PM at SAB

Monday, Nov. 24, 2008 Final Action
Monday, Nov. 10, 2008
23
  • Additional copies of the CIP are available
  • Planning Development Dept.
  • www.cpschools.com
  • All branches of the public library

CIP 2009-19
24
What Sources are Used to Assist with Student
Enrollment Projections?
  • Review enrollment/housing/population trends on a
    local, regional and national scale including
  • CPS historical data
  • City Planning Dept. data (comprehensive plan)
  • Hampton Roads Planning District Commission
  • UVAs Weldon Cooper Center
  • VA Dept. of Ed.
  • ODU State of Hampton Roads Annual Report
  • US Census
  • Surrounding school divisions

25
Factors Affecting Enrollment
  • Basics economy, growth rate, birth rate,
    migration
  • US Dept. of Ed. VA school enrollment expected
    increase 13 (2005-17)
  • UVA Weldon Cooper Center VA enrollment will
    increase thru 2012
  • Grades K-7 increase
  • Grades 8-9 small increase
  • Grades 10-12 decline