1Design and Development of a Water Channel
For Flow Visualization
- Jennifer Panik
- Senior Project 2003-2004
- Advisor Ann Anderson
- Mechanical Engineering
2Approach
- Research Existing Systems
- Tunnels
- Techniques
- Develop Design Specifications
- Design
- Determine flow and pumping needs
- Configuration
3Water Tunnel Background
- Large
- Small
- Horizontal
- Vertical
Source http//www.sm.go.dlr.de/sm-sm_info/TRTinfo
/wuk.html
Source http//www.dfrc.nasa.gov/Gallery/Photo/Pla
ces/Small/ED96-43468-4.jpg
Source http//rollinghillsresearch.com/Water_Tunn
els/Model_0710.html
4Flow Visualization Background
- Techniques
- Hydrogen Bubble Technique
- Dye Technique
1/48-scale model of an F-18 aircraft
Model of the future supersonic transport aircraft
(ATSF) in the water-tunnel.
Source http//www.dfrc.nasa.gov/Gallery/Photo/FVF
/index.html
Source http//www.onera.fr/photos-en/tunnel/avion
-ecoulement.html
5Dye Technique
- Tracers
- -Milk - Food Coloring
- - Ink - Alcohol
- - Rhodamine - Fluoresceine
- B 6G
- -Methylene Blue Dye
- Buoyancy
- - Density
- Filtration
- - X gallons will be contaminated in x time
- Safety
- Tracers
Source http//rollinghillsresearch.com/Water_Tunn
els/Prepared_experiments.htm
6Design Specificationsfrom Professors
Wind Tunnel Motor Speed (Hz) Approximate Air Speed in Test Section (m/s) Reynolds Number for 6in object Reynolds Number for 12in object
6 5 5.0 E04 1.0 E05
40 30 3.0 E05 6.0 E05
- Reynolds Numbers outside the wind tunnel range
- Low Reynolds Numbers ? 1
- View Creeping Flow
- Undisturbed Flow
- View Vortices
7Design Specifications
- Geometric
- Must fit on a table top
- Test section 121220 inches
- Test section made of Plexiglas
- Performance
- Flow rate of water must allow for Reynolds number
of 1 - Flow rate must be easily adjustable
- Test section must be easily viewed
- Must be able to run tests in a reasonable time
- Cost
- Must be under 800
8- Time
- Tunnel design must be completed by the end of
this term - Manufacturing
- The pump will be store bought
- All other portions will be assembled and
fabricated by me - Transport
- System will be able to be transported on table
- Ergonomic
- Models need to be easily loaded and unloaded
- Safety
- Tracers must be safe
- No electrical- water interactions
9Performance Specifications
10Results
Approximately 6 min 3.5 min 1 min
11Design Concepts
Test section
Reservoir
Test section
pump
12System and Operating Curve
13Whats Next
- StarWorks must be used to find inlet design
- Flow Conditioning
- Finalized design
- Fabrication
- Testing in the completed tunnel
14Questions
Acknowledgements Professor Ann
Anderson Professor Brad Bruno IEF for funding