Shoulder-to-Shoulder Contracting Presented By: James Gill David Block - PowerPoint PPT Presentation

1 / 19
About This Presentation
Title:

Shoulder-to-Shoulder Contracting Presented By: James Gill David Block

Description:

Shoulder-to-Shoulder Contracting Presented By: James Gill David Block Who we are Mr. James Gill Currently Contracts Committee, SMC 30+ Years of Acquisition ... – PowerPoint PPT presentation

Number of Views:143
Avg rating:3.0/5.0
Slides: 20
Provided by: Bride
Category:

less

Transcript and Presenter's Notes

Title: Shoulder-to-Shoulder Contracting Presented By: James Gill David Block


1
(No Transcript)
2
Shoulder-to-Shoulder ContractingPresented
ByJames GillDavid Block
3
Who we are
  • Mr. James Gill
  • Currently Contracts Committee, SMC
  • 30 Years of Acquisition Experience
  • Peacekeeper, Small ICBM, SBIRS, SBR, Launch
    Programs
  • Professor Cal State San Bernardino, National
    Security Studies
  • Mr. David Block
  • Currently Deputy Chief SBIRS Contracting, SMC
  • 25 Years of Acquisition Experience
  • Sustainment of F-117, A-10, F-111, Classified
    programs
  • Major weapons systems acquisition, SBIRS, SBR

4
Overview
  • Definitions
  • Traditional approach
  • Benefits of Shoulder-to-shoulder
  • Issues with shoulder-to-shoulder
  • Lessons learned
  • Positive
  • Improvement
  • Conclusions

5
Definitions
  • Fact finding
  • Process by which the government assesses the
    information provided by the contractor in
    response to the request for proposal
  • Shoulder-to-shoulder
  • Describes a specific form of fact finding,
    applicable in sole source arrangements, where the
    government and the contractor work as a team to
    build a proposal
  • For the purposes of this briefing, the term is
    synonymous with alpha-contracting, IPT pricing,
    one pass pricing

6
Traditional Approach
  • Traditionally, the acquisition would follow a
    serial path
  • The Government would issue an RFP
  • Contractor would prepare proposal
  • Customer, DCAA, and DCMA would analyze the
    proposal
  • Fact finding would be scheduled
  • Usually, proposal would be updated to address
    misunderstandings (red-line or new proposal)
  • Negotiations would conclude
  • Process is formal and long taking as much as 6-8
    months on major acquisitions

7
Problems with the traditional approach
  • This highly serial process where the government
    and the contractor pass products back and forth
    over a formal fence, is not conducive for a
    meeting of the minds
  • The contractor must interpret the government
    requirement, leading to misunderstandings over
    scope and available resources
  • Information may flow, no agreements made
  • The process can lead to competing teams
  • This may be a model for adversarial negotiations
  • Not a good start for performance after
    negotiations are complete
  • Disruptive to the government/contractor
    relationship
  • A significant investment in resources is expended
    by the government and contractor as the pursue
    this long process
  • Inefficient and expensive

8
Shoulder-to-shoulder
  • This process has been around for quite awhile
  • Process has many names, Alpha contracting, IPT
    contracting, one pass contracting
  • All are attempts to shorten the time it takes to
    negotiate changes to a program
  • Government works in a team with the contractor to
    prepare the proposal
  • DCAA, DCMA, and other government stakeholders are
    often part of the team
  • Allows for detailed communication between the
    government and the contractor during proposal
    preparation
  • Enhances communication, resulting in better
    understanding of the requirements and available
    resources
  • Builds a team to enable contract performance
    after negotiations
  • More of a parallel process, which should reduce
    lead-time

9
Shoulder-to-shoulder Process
  • Step One
  • Government and contractor establish a schedule
    for the process and the basic ground rules of the
    team
  • Develop organizational structure of the the team
  • Leadership team, individual IPTs
  • Step Two
  • Team discusses the requirement so that the
    contractor completely understands the government
    requirement
  • Step Three
  • The team jointly prepares the basis of estimate
  • All areas of direct costs are agreed to at the
    lowest level
  • Disagreements are raised up the chain of command
  • Process to agree to disagree if appropriate
  • Step Four
  • Contractor prepares the proposal based on direct
    cost inputs
  • Government documents shoulder-to-shoulder process
    in preparation of negotiations
  • Step Five
  • Negotiations of any areas of disagreement,
    indirect costs and fee

10
Issues
  • How much authority should be delegated to S2S
    Team?
  • Clearance Approval Authority has limited
    visibility into agreements that are made during
    S2S process
  • Without a documented trail, there is no way to
    validate amount of time effort involved in S2S
    process
  • Formal, structured and disciplined process must
    be in place including training for S2S team,
  • Given relative inexperience of workforce, S2S
    should be judiciously applied there are limited
    ways to validate effectiveness of S2S
  • Team Members must appreciate that there will be
    legitimate areas of disagreement catalogue
    those areas and identify them to Clearance
    Approval Authority

11
Issues
  • How much authority should be delegated to S2S
    Team?
  • Avoid temptation toward groupthink legitimate
    differences should be highlighted, not covered up
  • S2S is labor intensive and should be restricted
    to those actions where resources are available to
    support this approach most Program Offices do
    not have enough resources to support S2S for all
    proposals
  • Too many clearances have come in with no
    differences between the Government and
    Contractors positions, S2S should not force
    parties to agree
  • When no differences exist at Clearance, have team
    show where Contractors initial input was
    rejected or where a revised BOE was utilized due
    to Government team input

12
Lessons Learned
  • Shoulder-to-shoulder process is used extensively
    in the Space Based Infra-Red System (SBIRS)
    System Program Office at the Space and Missile
    Center in Los Angeles, CA
  • A recent application of the process was the
    addition of the Mission Capability Station
    Backup
  • This was approximately an 90M effort
  • Definitization of an Undefinitized Contractual
    Action
  • Generally viewed as a success by the government
    and the contractor
  • The following is a discussion of the pros and
    cons of the process as an illustration

13
Positive 1 of 2
  • Up front training of all stakeholders is
    beneficial
  • Process for all participants
  • Government training on how contractor team
    develops proposals
  • Proposal themes are encouraged and highly
    effective in building team synergy
  • FISH Flexibility instill team values stay on
    schedule HEO capability to the user
  • Team adopted a stuffed fish mascot, tee shirts
  • Face-to-face kick-off and ice breaker
  • Breaks down the natural barriers that exist when
    people dont know each other
  • Establish team awards to encourage performance
  • Ethical considerations, so needs to emphasis
    recognition not monetary reward and criteria must
    be based on successful completion of the process

14
Positive 2 of 2
  • Set expectations that BOE reviews and training
    would be done face to face
  • Appropriate server access for all participants,
    including applicable subs, so that information is
    freely shared
  • Preparation of stop light charts beneficial in
    tracking progress
  • Keeping BOE delta hours checklist after each BOE
    review
  • Ensured IPTs keep their tracking current
  • Essential for final technical review report
  • Daily stand ups with proposal leadership team
    critical to keeping schedule

15
Improvement (Organizational)
  • Insure adequate buy-in from team members and
    their management
  • Individuals must have adequate time to
    participate in the process
  • Ensure prime and all significant subcontractors
    have bought into the process at the management
    level
  • Ensure all company work sharing agreements are
    vetted prior to beginning the proposal process
  • Disagreements in the contractor team over scope
    of participation of subs and TWTA
  • Ensure DCAA and DCMA are totally committed to the
    process
  • Insure government and contracting pricers are
    participating in the POE review

16
Improvement (Proposal Ops)
  • Proposal schedule must take into account lags for
    company specific management reviews
  • Allow for adequate time in the schedule to allow
    prime proposal manager to develop RFP/SOW for
    subcontractors and IWTAs
  • Government must fully staff and coordinate
    requirements through all appropriate stake
    holders prior to start of process
  • Functional managers must have final approval of
    all lower level IPT BOE inputs
  • Dont try to standardize company unique BOEs

17
Improvement (Techniques/processes)
  • Insure mechanism for cross talk among all IPTs
  • This allows baseline change impacts to be
    addressed across the entire proposal team
  • Provide checklist to insure BOEs contain
    appropriate justification
  • Create a catalog of all required BOEs to insure
    completeness
  • Date and time stamp all BOEs
  • Ensure that bill of materials (BOM) gets same
    level of scrutiny as the BOEs
  • Vendor quotes on BOM better than engineering
    judgment

18
Improvement (Roles and Responsibilities)
  • Ensure team members involved in the
    reviews/decisions wear the team hat as much as
    possible
  • Limit individual company and government
    perspective
  • Win/win solutions should be the goal
  • Ensure roles and responsibilities are fully
    understood by all participants
  • If multiple companies, remember who is the prime
  • Within the team, understand limits of
    responsibilities of the individual
  • Understand what items are beyond the scope of the
    review, such as Fee and indirect rates

19
Conclusions
  • Shoulder-to-shoulder is a valuable tool in the
    movement to reduce cycle time for major weapon
    system contracting
  • Senior managers must implement a disciplined,
    formal process to insure a reasonable application
    of the process
  • Must protect the integrity of the process to
    prevent future scandals tainting the acceptance
    of this valuable tool
  • Remember that faster does not always mean better
Write a Comment
User Comments (0)
About PowerShow.com