Title: PROJECT CONTROL
1PROJECT CONTROL
- Project Control Defined
- Types of Control Systems
- Need for Balance in Control Systems
- Control of Creative Efforts
- Changes and Change Control
2Project Control Defined
- CONTROL The act of reducing the difference
between plan and reality - The last element in the plan-implement-monitor-con
trol cycle - Uses the information from the monitoring process
to get and keep a project on track
3Control Can Be Complicated
- Performance, cost, and schedule issues all have a
human element - Symptoms are obvious, but root causes never are
- Messes vs. problems
- Hard to separate random events from systemic
difficulties
4Two Fundamental Purposes of Project Control
- Regulate project results through alteration of
activities - Efficiently use and protect organizational assets
5Asset Conservation Has Three Aspects
- Physical Assets
- Maintenance, inventories, security protection
- Human Resources
- Managing acquisition, development and performance
of people - Financial Resources
- Budgets, audits, financial ratio analyses
- The concept of due diligence
6Purpose of Control
- To make the actual meet the plan
- The Process
- 1. Identify key performance areas
- 2. Set standards
- 3. Measure performance
- 4. Compare
- 5. Take corrective action
7Three Types of Controls
- Cybernetic controls
- Steering
- Key feature automatic operation
- Go-no go controls
- Most common project control
- Test that predetermined specifications have been
met - Post controls
- After the fact
8A Cybernetic Control System, Figure 11-1
9Typical Paths for Correction of Deviation, Figure
11-2
10A 2nd-Order Feedback System, Figure 11-3
11A 3rd-Order Feedback System, Figure 11-4
12More on Go-No Go Controls
- Based on project plans, budgets, schedules
- Can be periodic or milestone-driven
- Both are essential
- Phase-gated criteria are hurdles that must be
passed to go to next project stage - Common terms exit criteria, milestone
decisions, system maturity models
13Sample Project Status Report, Figure 11-5
14Components of Post Control Process
- Benefits future projects more than the present
one - See Project Auditing in Chapter 12
- Four parts
- Project objectives
- Milestones, checkpoints, budgets
- Final report on project results
- Recommendations
15Some Desirable Control System Features
- Flexible, able to adapt to unforeseen events
- Cost effective (control value gt control cost)
- Useful and ethical
- Accurate, precise, timely
- Simple and maintainable
- Fully documented
16Critical Ratio
- Critical ratio actual progress X
budgeted cost scheduled progress
actual cost - I.e., CSI SPI X CPI, as in Chapter 10
- Indices and ratios greater than 1.0 are favorable
17Critical Ratio Control Limits, Figure 11-8
18Cost Control Chart, Figure 11-9
19Effective Control Systems Must be Balanced
- Balance means
- Measuring both tangibles and intangibles
- Looking at both long-term and short
- Keeping flexibility in the system
- Addressing human factors
- Focusing on correction, not punishment
- Optimizing control, not maximizing it
20A Question of Balance
- Too little control?
- Too much control?
C
Control
C
Mistakes
Amount of Control
21Control of Creative Activities
- Controlling knowledge work is difficult
- Three tools
- Progress reviews
- Reassigning people
- Control of resource inputs
22Controlling Changes and Scope Creep
- Changes can drive higher costs and stretched out
schedules - So controlling them is an essential project
management task - A formal change system is a must for project
control
23Five Principles of a Formal Change Program
- All contracts specify formal change process
- All changes require formal change order
- All change orders approved in writing by client
and project organization - Project manager is always consulted
- The approved change order becomes part of the
master plan
24Changes and Change Control
- Remember the last step of the control process
Take corrective action, so that the actual
matches the plan - Two Types Business and Technical Changes
25Business Changes
- Business-related
- Driven by such things as
- Spec relief
- Deliverables changes
- Funding shifts
- Schedule changes
- Acts of God
- Subcontractor changes
26Technical Changes
- Technological issues, such as
- New technologies
- Laws of physics
- Competitor response
- Changes in client requirements (real or political)