Calculating Project Schedule Risk Using Monte Carlo Simulation - PowerPoint PPT Presentation

About This Presentation
Title:

Calculating Project Schedule Risk Using Monte Carlo Simulation

Description:

Calculating Project Schedule Risk Using Monte Carlo Simulation Curt Blair, PMP Project Schedule Risk The Problem Projected completion dates are estimates, not hard ... – PowerPoint PPT presentation

Number of Views:65
Avg rating:3.0/5.0
Slides: 6
Provided by: CurtB7
Category:

less

Transcript and Presenter's Notes

Title: Calculating Project Schedule Risk Using Monte Carlo Simulation


1
Calculating Project Schedule Risk Using Monte
Carlo Simulation
  • Curt Blair, PMP

2
Project Schedule RiskThe Problem
  • Projected completion dates are estimates, not
    hard facts
  • These estimates often only represent a median
    scenario 50 probability
  • Parallel paths (concurrent development) decrease
    estimate quality
  • A single completion date estimate does not
    reflect component risk factors

3
Project Schedule RiskOne Solution
  • Monte Carlo simulation provides a more complete
    picture of the risk
  • Uses Optimistic, Pessimistic and Most likely WBS
    task durations
  • Provides a range of completion dates each with an
    associated probability

4
Project Schedule RiskAdvantages
  • Gives stakeholders a better feel for the
    schedule risk
  • Reflects contribution of individual high risk
    tasks on near-critical paths
  • Allows the Project Manager to demonstrate
    relative schedule risk of alternate scenarios

5
Project Schedule RiskTools
  • Excel spreadsheet
  • Add-ins for Microsoft Project
  • _at_Risk
  • Risk Example