Title: Financing a CDM Project
1- Financing a CDM Project
- DBBLs experience
Farhad Ahmed Khan Assistant Vice
President Syndication Structured Finance Credit
Division, Dutch-Bangla Bank Ltd
2DBBLs Participation in Euro 12 Million Project
- DBBL to provide to the extent of Taka eqvt. Euro
2.00 million in part funding of implementation of
WWR Bio Fertilizer Ltd, a municipal organic
waste-to-bio-fertilizer plant - FMO to act as Arranger and DBBL to act as Agent
and Security Trustee
3Project Partners
Waste Concern Consultants (WCC) from Bangladesh.
It is working in the area of waste management in
Bangladesh since 1995. It is specialized in small
and medium scale waste management projects
especially composting. Waste Concern is involved
in design and implementation of 47
compost/recycling plants distributed in 26 cities
and towns of Bangladesh. Apart from Bangladesh,
WC is also involved in waste composting projects
in Sri Lanka and Vietnam. World Wide Recycling
BV from Netherlands. It is also working in the
areas of waste management. This company is
associated with VAR a large scale waste recycling
company. It is specialized in large scale waste
projects including composting
WWR Bangladesh Holding BV.
4The Shareholders Structure
WBH holds 100 less legally required local
shareholding of one share of WWR Bio.
The shareholders of WBH are WWR (EUR 1.7m,
54.2), WCC (EUR 0.4m, 13.6), FMO (EUR 0.5m,
16.1) and Triodos (EUR 0.5m, 16.1).
5About VAR/WWR
-
- WWR is closely related to the VAR via Jan Boone,
who is the founder of VAR, was director of VAR
till July 2002, and still is main shareholder of
VAR with 80 and he is chairman of the
supervisory board of VAR. VAR was established in
1981 by Jan Boone. VAR is one of the largest and
most innovative companies in the area of
sustainable waste treatment in the Netherlands.
VAR and WWR have signed a Cooperation Agreement
via which VAR is obliged to provide technological
support to WWR. -
- At the end of 2006, VAR had a Balance Sheet
total of EUR 83m, turnover of EUR 48m, net profit
EUR 4.1m, solvency 32 and 140 staff. The
following key figures of VAR in 2006 - Balance sheet total EUR 79,992,817
- Equity EUR 27,096,302
- Turnover EUR 47,643,755
- EBIDTA EUR 7,300,429
- Net profit EUR 4,122,329
6Financing Plan of WWR Bioin million Euro
Amounts x1m EUR Equity to WBH Loan to WBH Loan to WWR Bio Total
FMO 0.43 1.54 3.90 5.87
Triodos 0.43 0.43 1.50 2.36
WWR/WCC 1.80 - - 1.80
DBBL - - 2.00 2.00
Total 12.03
the amounts paid out to WBH are transferred to
WWR Bio as equity
7Investment and Financing
 Investment Plan (in Euro) 2007 2008/2009 2009/2010
1 Investments in intangibles 690,000 0 0
2 Land 187,198 327,273 297,521
3 Buildings machines 1,304,035 3,899,706 3,806,134
4 Contingencies (activated) 167,903 502,112 490,064
5 Enrichment  550,000 413,223
6 One-off costs 225,000 Â Â
Total 2,574,136 5,279,091 5,006,942
Financing Plan (in Euro) Â Â Â
7 Capital injection WWR/WC 840,000 804,900 155,100
8 Capital injection FMO 200,000 191,643 36,929
9 Capital injection Triodos 200,000 191,643 36,929
10 WBH subloan FMO 164,805 689,914 688,138
11 WBH subloan Triodos 79,305 191,643 157,623
12 WWR Bio subloan FMO 721,680 1,743,950 1,434,370
13 WWR Bio subloan Triodos 269,639 651,586 535,919
14 WWR Bio loan DBBL 372,736 900,721 740,829
Total 2,848,164 5,366,000 3,785,836
8Projected Operating Results
Amounts in x1000 EUR 2008 2009 2010 2011 2012 2013 2014 2015
Turnover 1,537 6,323 6,178 11,293 10,986 9,367 8,852 8,365
EBITDA 412 2,541 2,447 4,550 4,584 3,313 3,122 2,942
Net profit -129 1114 1169 2692 1767 1117 1100 1137
Operational cash flow 220 1,416 2,477 3,484 4,648 3,650 3,230 3,043
Cash at end of year 240 999 1,177 2,804 4,704 6,257 6,151 5,993
Â
Balance sheet total 7,989 9,502 13,941 16,018 16,902 17,158 16,163 15,200
Solvency () 26 34 33 42 48 53 61 71
Risk Bearing Capital as of TA 82 81 85 88 92 95 95 95
Debt/EBITDA 14.05 2.28 3.61 1.83 1.71 2.21 1.76 1.25
Current ratio 4.37 5.40 5.79 6.48 8.64 11.52 11.84 12.10
DSCR excl. investments 2.03 3.87 4.07 5.39 4.63 4.00 2.26 2.47
9Tenor/Repayment Period
Tenor Tranche I IV for the loans, 10 years from the financial close, with a grace period of 6 years. Tranche V (6 years) from Financial Close with a grace period of 12 months. Repayment Period Tranche I-IV In 8 semi-annual equal installments with the first such installment due 78 months after the closing date. Tranche V In 20 quarterly installments with the first such installment due 15 months after the closing date.
10Perceived Risk as assessed by DBBL
Construction risk
Feedstock risk
Off-take risk
Loan Structure Risk
11- Feedstock risk
- Input of organic waste is guaranteed by a
Concession Agreement with the municipality that
allows WWR Bio to collect up to 700 ton/day waste
from designated areas, like local markets.
12- Construction risk
- A compost facility is a relatively easy concept.
Also, the construction is done under supervision
of the VAR with extensive experience and
knowledge
13- Operational risk
- Employees will be trained, partly at the VAR in
the Netherlands. If major problems occur the VAR
will give technical assistance. Management of the
companies will come from WCC and WWR and thus
have experience with waste management
14- Off-take risk (demand, competition and
distribution) - Compost can be used as a substitute for or
additional to more expensive fertilizers. The
compost market is only marginally developed,
while the domestic fertilizer market can not
foresee in total demand. So (potential) demand is
high, while competition is low. Because the
compost will be tailor made for different crops
it can be sold during the whole year. WWR Bio
negotiates on agreements with end-users directly
and off-take agreements with wholesalers/distribut
ors. Own distribution will then be considered
later
15- Land
- For the first 100-130 ton/day capacity land is
acquired under a lease contract, which might not
be sustainable. DBBLs investment is however
limited to EUR 0.372 m in the first phase and for
subsequent phases it is required that land is
obtained in ownership.
16- Revenue from CERs
- The used methodologies are approved as CDM
projects and thus CERs will be generated as soon
as the compost facility is operational. The price
of CERs stays, nevertheless, very insecure, but
profits of the project are mainly generated by
selling (enriched) compost -
- DBBL assumed a fixed selling price of Euro 8 per
unit CER
17- Environmental and social risks
- The project has significant environmental and
social positive impacts, the most important being
the reduction of greenhouse gas emissions, the
production of soil improving compost and the
offering of livelihood opportunities and
improvements for poor and marginalized people.
Potential adverse impacts do exist, but are
limited and manageable and they can be mitigated.
18- Key Man Risk
- The Directors of WWR Bio are A.H. Md. Maqsood
Sinha of WCC and a representative of WWR,
currently Jan Boone. A.H. Md. Maqsood Sinha has
experience with waste management in Bangladesh.
A.H. Md. Maqsood Sinha and Jan Boone seem very
capable of running WWR Bio. Nevertheless, if Jan
Boone or any other key person should fall away,
an important financial and business partner is
lost (key man risk), especially during
construction phase.
19- Loan Structure Risk
- The tenor for the DBBLs loans is 6 year, with a
grace period of 1 year. DBBL (senior loans)
receives security over all fixed and floating
assets of WWR Bio. - Another mitigant is that disbursements of the
loans to expand capacity from 100 to 700 ton/day,
will be considered only if the project at phase 1
has proven to be a success.
20Milestones Achieved
- Concession Agreement with DCC has been signed
to collect and transport waste - National CDM Board Approval has been obtained
- Land lease agreement for 22 years has been
signed - Trade licensee obtained
- Land use clearance obtained
- BOI registration obtained
- Third party verification of Environmental and
Social Compliance has been done - Environmental clearance obtained from DOE
- Work permit for the WWR engineer has been
obtained - Import permit has been obtained
- Land development completed
- Detailed Engineering design completed
- Major construction works for phase 1 completed
by March 2008 - The project has gone into trial operation end of
March 2008 - Pending Registration of compost/enriched
compost
21DBBL to finance First CDM project in Bangladesh
- Commercial lenders are cautious in providing new
loans particularly to projects involving
unfamiliar technologies. - Technologies, equipment processes relevant for
CDM are available commercially, many of which
offer viable economic returns yet, not many of
such projects are being implemented in Asia
compared to what can be potentially achieved. - Bangladesh is yet to see any lender, other than
DBBL, to finance CDM project. - DBBL wishes to extend thanks to FMO for involving
it with the countrys first ever CDM project.
22Summing up DBBLs Feeling
- An adequate risk-sharing structure is often
difficult to put in place and almost always
creates unanticipated delays in achieving
financial closing. - Risk should be allocated, by contract, to the
party that is best able to mitigate or control. - Completion risk could be avoided by implementing
such project in phases. - There should be transfer of technical know-how
from Annex I country. - Carbon Credit market development needs
accelerators. Action by participating players
needed advisors, buyers, FIs, government to put
in place the necessary accelerators. - Regulatory support needed.
- Lenders should have greater oversight of the
project. They should have control the application
of cash flows.
23Summing up - DBBLs Feeling (Contd.)
- First time lenders for projects like CDM should
be in the senior loan category. Equity and quasi
equity should be invested first. - Banks need assets to back-up however, CDM
project is often not asset based but idea based. - Documentation is lengthy and complex, and costs a
great deal to put into place. - Success of WWR Bio is crucial for other lenders
to finance CDM project. - Bangladesh is an attractive market for CDM.
- DBBL will embark on the lessons learned to take
on more such viable CDM projects. Journey has
just begun.
24The End