Title: Fukushima Response
1Fukushima Response
- George Attarian
- 1/21/2013
2Fukushima Response
- Timeline
- March 11 Event occurred
- March 18 INPO IER 11-1 issued (April 15)
- March 23 NRC TI 2515/183 issued (May 13)
- April 25 INPO IER 11-2 issued (September 20)
- April 19 NRC TI 2515/184 issued (June 30)
- May 11 NRC Bulletin 2011-01 issued (July 11)
- June 8 NEI The Way Forward issued
- July 12 NRC NTTF issued
- August 1 INPO IER 11-4 issued (January 28)
- August 1 INPO Equipment Survey issued (November
4)
3Fukushima Response
- Timeline
- September 1 INPO IER 11-1 Supplement issued
(March) - September 9 NRC SECY-11-0124 issued, SRM
issued October 18 - October 3 NRC SECY-11-0137 issued, SRM
issued November 8 - December 14 NRC holds first public, issue
specific meetings on
SECY-11-0137 - January 18-19NRC holds second public issue
specific meetings and
presents draft 50.54(f) letter with enclosures - March 9 50.54(f) letter and enclosures
and Orders issued to
the Licensee for Tier I NTTFs
4Fukushima Response
- NRC Near Term Task Force (NTTF) Recommendations
(12) - Clarifying The Regulatory Framework (1)
- Ensuring Protection (2)
- Enhancing Mitigation (5)
- Strengthening Emergency Preparedness (3)
- Improving the Efficiency of NRC Programs (1)
5Fukushima Response
- NTTF Impact
- NTTF 2.1 Flood and Seismic
- 50.54(f) letter to licensee
- New flood analysis beyond design basis
- Seismic currently following GI 199
- NTTF 2.3 Walkdowns
- 50.54(f) letter to licensee
- Walk down the site for all external design basis
events flood seismic, other external events - NTTF 4.1 SBO
- Rule making
6Fukushima Response
- NTTF Impact
- NTTF 4.2
- By order
- Additional pumps and related equipment
- FLEX approach
- NTTF 5.1 Harden Vents
- By order
- BWR Mark I II only
- Filtration system not in order
- NTTF 7.1 Spent Fuel Pool Instrumentation
- By order
- Level only
- Primary and backup
- Control Room or Alternate Shutdown monitoring
- Qualifications
7Fukushima Response
- NTTF Impact
- NTTF 8 EDMG EOP SAMG integration
- Rule making
- NTTF 9.3 Emergency Preparedness Staffing
- 50.54(f) letter to licensee
- Extension of the EP Rule
- Staffing impact to multiple Unit plant sites
- Communication guidance
8Station Blackout Definition
- 10CFR50.2 Definition
- The complete loss of alternating current (ac)
electric power to the essential and nonessential
switchgear buses in a nuclear power plant. - Station blackout does not include the loss of
available buses fed by station batteries through
inverters or by alternate ac sources as defined,
nor does it assume a concurrent single failure or
design basis accident.
9Alternate AC Sources
- An alternating current (ac) power source that is
available to and located at or nearby a nuclear
power plant and meets the following requirements - Is connectable to but not normally connected to
the offsite or onsite emergency ac power systems - Has minimum potential for common mode failure
with offsite power or the onsite emergency ac
power sources - Is available in a timely manner after the onset
of station blackout and - Has sufficient capacity and reliability for
operation of all systems required for coping with
station blackout and for the time required to
bring and maintain the plant in safe shutdown
(non-design basis accident)
10Current NRC Rule
- 10CFR 50.63 Loss of all alternating current power
- (a) Requirements. (1) Each light-water-cooled
nuclear power plant licensed to operate must be
able to withstand for a specified duration and
recover from a station blackout as defined in
50.2. The specified station blackout duration
shall be based on the following factors - (i) The redundancy of the onsite emergency ac
power sources - (ii) The reliability of the onsite emergency ac
power sources - (iii) The expected frequency of loss of offsite
power and - (iv) The probable time needed to restore offsite
power.
11Current NRC Rule (contd)
- (2) The reactor core and associated coolant,
control, and protection systems, including
station batteries and any other necessary support
systems, must provide sufficient capacity and
capability to ensure that the core is cooled and
appropriate containment integrity is maintained
in the event of a station blackout for the
specified duration. - The capability for coping with a station blackout
of specified duration shall be determined by an
appropriate coping analysis. Licensees are
expected to have the baseline assumptions,
analyses, and related information used in their
coping evaluations available for NRC review.
12Regulatory Guide 1.155
- Reg. Guide 1.155, Station Blackout
- Specifies a method acceptable to the NRC staff
for complying with 10CFR50.63 - Twenty four pages of detailed guidance
- EDG Target Reliability Levels
- Restoration of Offsite Power
- Ability to Cope with a Station Blackout
- Quality Assurance Guidance for Non-Safety Systems
and Equipment
13NUMARC 87-00
- Guidelines and Methodologies for Implementing the
Nuclear Management an Resources Council (NUMARC)
Station Blackout Initiatives - Three Hundred Pages of Detailed Guidance,
Examples, Topical Reports, and Questions
Answers - Endorsed by Reg. Guide 1.155 as Acceptable
Guidance for Compliance to 10CFR50.63 - Contains Detail Beyond Reg. Guide 1.155
14Typical Results
- Plant Specific SBO Coping Analyses Produced
- Specifies How Long You Have to Cope Without AC
Power - Typically 4 or 8 hours
- Specifies How Coping is Achieved
- Batteries, alternate ac power, RCS leak rates,
water sources, pumps, instrumentation control,
etc. - Requires Containment Isolation
- Typically Addresses Pre- Hurricane Preparations
for Coastal Plants - Excludes Concurrent Design Basis Events
- Assumes Restoration of at Least One Source of
Offsite or Onsite AC Power is Successful Before
the Coping Period Ends
15Typical Limitations Beyond SBO Coping
- Battery Depletion
- Water Sources Run Out CST Inventory
- RCS Inventory Losses - PWR RCP Seal Leakage
- BWR Suppression Pool Heat-up Saturation
- Emergency Lighting Battery Packs Deplete
- Increasing Manual Actions for Available Personnel
as SBO Time Increases
16Beyond SBO Coping Strategies
- Medium Size Generators to Re-Energize Battery
Chargers - Emergency Engine Driven Pumps to Replenish Water
Sources CST Make-up - Medium Size Generators and Pumps to Restore RCP
Seal Injection - RCP Shutdown Seal Package Designs to Limit
Leakage - BWR Hardened Wetwell Venting Systems and
Suppression Pool Make-up with Cool Water - Helmet Mounted LED Lights for Personnel or Longer
Lasting LED Emergency Lights - Pre-Plan and Pre-Stage More Emergency Equipment
to Make Manual Actions Easier and Train More
Personnel to Use it
17What is FLEX?
- Response to NRC Mitigating Strategies Order (EA
12-049) - Provides a diverse and flexible means to prevent
fuel damage while maintaining containment
function in beyond design basis external event
conditions resulting in an - Extended Loss of AC Power, and
- Loss of Normal Access to the Ultimate Heat Sink
- Objective
- Establish an essentially indefinite coping
capability by relying upon installed equipment,
onsite portable equipment, and pre-staged offsite
resources
18Diverse Flexible Coping Capability (FLEX)
Emergency Plans
SAMGs
Emergency Plans
Emergency Response
Diverse Flexible CopingStrategy (FLEX)
SAMGs
Increased Defense-in-Depth
SBO Coping Capability
SBO Coping Capability
Prevention of Fuel Damage
Design Basis External Events
Design Basis External Events
Protection of Plant Equipment
Current
Current plus FLEX
19Tier 1 FLEX Approach
20FLEX Mitigation Strategies
- FLEX employs a three phase approach
- Phase 1 - Initially cope by relying on installed
plant equipment, - Phase 2 - Transition from installed plant
equipment to onsite FLEX equipment, - Phase 3 - Obtain additional capability and
redundancy from offsite equipment until power,
water, and coolant injection systems are restored
or commissioned. - Diverse and flexible to enable deployment of the
strategies for a range of initiating events and
plant conditions
21Representative High-level Example (BWR)
- Phase 1 Initial Coping Capability
- Use RCIC for RPV makeup from suppression pool
- Rely on DC Power for key instrumentation and
controls - Phase 2/3 Extended Coping Capability
- Charge battery to maintain DC power
- Use Reliable Hardened Vent for containment heat
removal - Provide extended RPV makeup with portable pump
22Representative High-level Example (PWR)
- Phase 1 Initial Coping Capability
- Turbine-driven AFW for SG makeup from Condensate
Storage Tank - Rely on DC Power for key instrumentation and
controls - Phase 2/3 Extended Coping Capability
- Charge battery to maintain DC power
- Provide extended SG makeup with portable pump
- Provide RCS makeup with portable pump, as needed
23NRC Advance Notice of Rule Making
- Rule Making Objectives
- What specific objectives should the SBO rule be
designed to achieve? - How should actions taken in the NTTF 4.2 be used?
- What regulatory approach to SBO mitigation that
follows the conceptual approach outlined in NTTF
4.1? - How can regulatory action in NTTF 8.0 be best
integrated with SBO? - How can regulatory action in NTTF 5.1 be best
integrated with SBO? - How can regulatory action in NTTF 7.1 be best
integrated with SBO?
24NRC Advance Notice of Rule Making
- Relationship between 10CFR 50.63 and the new SBO
rule - Keep existing rule and supplement with scenarios
that go beyond the existing rule. - Integrate existing rule with new requirements
into a new rule for SBO. - Supersede the existing SBO rule with an
enveloping rule. - Comments have been submitted, ACRS meeting to be
held. - Ball in NRC court.