Title: Construction Proposal
1 Construction Proposal
2Features
- The proposal form is an offer and a promise to
enter into a contract if selected - A prepared proposal form is included in the bid
documents - Not using the prepared form results in
disqualification
3Features (cont.)
- The proposal form must include
- the promise
- list of addenda
- base cost and alternatives
- accompanied by surety deposit or bid bond
- signatures and seal
4Features (cont.)
- Examine the proposal form for unit price
contracts in Appendix E, p. 483 - Notice the acceptance period of 60 days is cited
- Financial responsibility
- Competency
- Experience
- Bonds and insurance
5Proposal Details
- Detailed Costs
- Item by item
- Total Bid
- Bidders Statement of Understanding
- Sufficient time to examine work
- Understanding of General Conditions,
supplements, and addendums - Bid Proposal Guaranty Bond
6Proposal Details
- Prequalification certificate
- List of Subcontractors
- Qualifications
- Bonded and insured
- Certifications
- DBE, MBE, PA or US suppliers
- Specialty requirements..
7Sample Schedule of Prices
Item Approximate Quantity Item Unit Item Total
1018-0001 1 Removal of Existing Bridge, LS
1999-9999 6000 hrs Trainees/Interns 90,000
8000-0288 1 Prestressed Concrete Bridge Structure, LS
8100-0288 1 or Steel Bridge Structure, LS
9005-1000 3771 LF Concrete Filled Pipe Bearing Piles, 14 Dia. LF
9005-1301 1921 LF Predrilling for Pipe Piles, LF
8Penn States Bid Form
9Penn States Bid Form
10Bid Development
11Bid Components
Bid Price
Markup
Home Office Job Site
Indirect Job Cost
Direct Job Cost
12Bid Components (cont.)
Direct Job Cost
Labor
Materials
Equipment
Subcontracts
13Bid Components (cont.)
Indirect Job Cost
Overhead
Support Structures
Purchase Orders
Salaries Insurance Office equip. Training Safety U
tilities
Access roads Parking lots Project Office Storage
trailers
Portable toilets Trash Security Testing
14Bid Components (cont.)
Markup
Home Office Overhead
Contingency
Profit
Clerks Secretaries Officers Utilities Travel Adver
tising Bidding
Quality of plans Unforeseen cond. Owner and
designer Schedule Location Work on hand
15Risks
- Quantity takeoff
- something will be left out or computed
incorrectly - plans are incomplete and the quantities change
- owner will delete certain items
16Risks (cont.)
- Detail sheets
- numbers will be erroneously transferred
- subcontractor quotes will be misunderstood
- productivity will be overly optimistic or
pessimistic - unforeseen conditions will affect productivity
- there may be noncompensable fabrication errors
- overestimate ability of superintendent to
organize and plan the work
17Risks (cont.)
- Markup
- incorrectly assess contingencies
- desired profit is too great or too little
18Form of Agreement
19Terms
- Retainage - That portion of each progress payment
that is withheld to cover correction of
deficiencies and omissions - Liquidated Damages - A damage assessment that is
withheld in the event of late completion
20Features
- The form of agreement is the contract
- PSUs Construction Contract
- On public contracts, statutory requirements must
be followed - One doing business with a public entity must be
aware of the laws governing its administration
and the limitations on the powers of the public
officials involved
21Contractor Acceptance
22Background
- Construction services are procured by negotiation
or competitive bid - For competitive bid projects, the d.p. usually
prepares the proposal form
23Background (cont.)
- The proposal
- is a legally binding promise to enter into a
contract - references the project, requires addenda to be
listed, and is accompanied by security deposits
or bid bonds - assures everyone is bidding on the same thing
24Private Sector
- Owner can do as he or she pleases
- negotiate with one or more contractors
- receive competitive bids from selected
contractors or in an open bidding process - select any bidder he or she wants
25Public Sector
- Statutes require competitive bidding
- Agency is seeking a fair and reasonable
(competitive) price - Process begins with advertisements
- Timeliness and other parameters of advertising
are governed by regulations - Statutes also govern how bids are received and a
contract is awarded
26Contractor Qualification
- Is a way to screen who is on the prospective
bidders list - The purpose is to assure a reputable contractor
- Inquiries ask questions about
- financial capability
- past experience
- managerial expertise
- integrity-
27Construction Contracts
28Pricing Arrangements
- cost proposal can be lump sum (fixed price), unit
price, or cost reimbursable - The choice is a function of the type and size of
project and the project risks
29Lump Sum (Fixed Price) Contracts
- I propose to be paid ________ to build this
project - Used most often on residential, commercial
buildings, engineered projects, and most
industrial projects - Design must be complete or nearly so
- Price will be fair and reasonable only if the
contractor can assess and assume the risks
30Advantages of Lump Sum
- If properly applied, the owner receives a
competitive price - Minimum owner risks for unforeseen conditions
- Well-established administrative, legal, and
contractual precedents
31Advantages of Lump Sum (cont.)
- Owner knows the cost in advance of the work
- Minimum owner involvement in construction process
- Significant contractor incentive to control costs
and meet the schedule
32Disadvantages of Lump Sum
- Design-construct time frame takes more time
- Adversarial relationships sometimes develop
- Changes and unforeseen conditions are more
difficult to handle - Contractor has limited input into
constructability issues
33Unit Price Contracts
- I propose to be paid this way to build this
project
34Unit Price Contracts (cont.)
- Used where quantities are uncertain
- Removes some of the contractors risk
- Unit prices are requested for major or all items
in the project - Sum of all unit prices times the quantity yields
the bid price - There can be several hundred or more items
35Unit Price Contracts (cont.)
- D. p. must provide estimated quantities for each
item - Bid equals actual cost only if all quantities are
exactly right - In reality, owner knows only the approximate cost
prior to the start of the work - Used often on earthwork type projects where
quantities are not known
36Unit Price Example
- Prices include layout, excavation, bedding,
materials, placement, sealing, testing,
compaction, backfill, overhead, profit, etc.
37Advantages of Unit Price
- Risk to the contractor of variations in
quantities is minimized - Changes are easier to make
- Owner knows the approximate cost in advance
- Well established administrative, legal, and
contractual precedents
38Disadvantages of Unit Price
- Owner has to provide greater contract
administrative services - Cost can escalate with significant changes in
quantities - Some of the same disadvantages of lump sum
39Cost Reimbursable Contracts
- Owner pays contractor expenses plus a fee
- Used sometimes on large, industrial type projects
where scope cannot be determined - More appropriate where design is incomplete or
changes will be common - Can sometimes be used on emergency projects
- Reserved for only extreme or highly unusual
circumstances
40Advantages of Cost Reimbursable
- Can accelerate the schedule because the design
need not be complete - Can make changes easily
41Disadvantages of Cost Reimbursable
- Owner has no idea of the final cost until the end
- There is greatly increased contract
administration - There is little incentive for contractors to
control cost or meet the schedule
42Variations in Fee Arrangements
- Cost plus of cost-- is fixed or may be a
sliding scale - Cost plus fixed fee--provides some incentive to
minimize cost and time of performance - Cost plus incentive target--could be fee
bonus/penalty - Guaranteed maximum price (GMP)--cost fee lt max
43Delivery System
Owner
Cost Reimb.
Cost Reimb.
CM
D.P.
Lump Sum/ Unit Price/ Cost Reimb.
Unit Price/ Cost Reimb.
Mech.
Fixed
Unit Price
Elec.
Piping
HVAC
44Subcontracts
45Contractual Obligations
- A subcontract is an agreement between a
contractor and a subcontractor where the sub
agrees to complete a part of the work - The sub has no contract with the owner
- The sub is usually bound by the same obligations
as the prime has to the owner (see AIA AS201,
Art. 5.3.1)
46Contractual Obligations (cont.)
- The owner often has the right to approve
subcontractors (AIA A201, Art. 5.2.1 - 5.2.4) - Disapproval of subcontractors is not that common
47Potential Problems
- Disagreements often occur when a non standard
contract is used - Sub may not be bound to the same obligations as
the prime - Sub may not receive all the prime contract
provisions to know the full extent of its
obligations - Sub may not get paid
48Relationship with Subcontractors
- Ethical considerations
- bid shopping or using a subs bid as the low bid
and shopping for a better bid after the prime
contract is awarded is troublesome - trying to get a lower bid from a sub after being
awarded the contract is to be frowned on - sub should be offered the same payment provisions
as the prime - pay the sub when the subs work is complete
49Relationship with Subcontractors (cont.)
- Contractual and legal considerations
- sub should be given all the contract provisions
to use in preparing the subs bid
50Contract Bonds
51Background
- A surety is a party that assumes a liability for
the debt, default, or failure of another - A bond is not insurance, but rather an extension
of credit in the form of an endorsement - A bond is a three party instrument where the
surety promises the owner (obligee) that the
contractor will perform in accordance with the
contract documents
52Background (cont.)
- If there is a default, the surety will step in
and see that the project is finished - The extent of the suretys obligation is defined
by the contract documents - The face value of the bond is the value of the
bond and is expressed as a percentage of the
contract amount, i.e., 100 bond
53Contractor Risks
- A surety will investigate contractors to evaluate
their financial capacity and available capital - Bonding capacity is the maximum value of
uncompleted work the surety will allow the
contractor to have on hand at any one time
54Types of Bonds
- Bid bond
- protect the owner against a contractor that
submits the lowest bid but refuses to sign a
contract - Performance bond
- protects the owner against default and assures
that the owner will get the facility without
undue delay
55Types of Bonds (cont.)
- Payment bond
- protects third parties like suppliers, vendors,
craft labor against not being paid - protects the owner from liens being attached to
the project
56Bond Premiums
- Premium amounts are a function of risk to the
surety - Premiums are based on two risk factors
- project risks
- contractor risks
57Project Risks
- Project risks are related to the type of project
and time of performance - Assume we have a commercial project (use the
Walker Building on campus as an example) that is
estimated to cost 4.0 million and as a project
schedule of 30 months. Calculate the bond
premium using the information in the following
Tables
58Construction Classification for Bonds
59Bond Premium Determination
60Bond Premium Calculation
- Classification B
- Base rate
61Bond Premium Calculation (cont.)
- Adjustment for time of performance
- Bond premiums usually range around 0.75 - 1.50
of the bid
62Contractor Default Options
- When the contractor defaults, the surety has two
options - assume charge of and complete the contract.
Surety may be able to get a lower price or be
able to limit its exposure if the surety is in
control. The surety is responsible for the total
cost of completing the work, less the contract
amount, even if the difference is higher than the
face amount of the bond
63Contractor Default Options (cont.)
- make available to the owner sufficient funds to
complete the work. Owner secures a new
contractor. The liability of the surety is
limited to the face value of the bond - The purpose of the bond is not to allow the owner
to make a profit
64Default Liability Example
- Suppose a 100 bond was issued on a 4,000,000
project. Shortly after the work began, the
contractor went bankrupt and the owner called on
the surety to complete the work. The following
conditions existed - initial contract value 4,000,000
- face value of the bond 4,000,000
- value of work performed 450,000
- retainage 45,000
- amount paid to contractor 405,000
65Default Liability Example (cont.)
- The surety elects to let the owner secure another
contractor, thus limiting its liability to the
face value of the bond - If the owner pays the new contractor 4,250,000,
what is the extent of obligation of the surety?
66Default Liability Example (cont.)
67Cash Flow and Bonding Capacity
68Topics
- Cash flow
- normal project
- impacted project
- Bond capacity calculations
- Effect of cash flow on bond capacity
69Cash Flow - Normal Project
- Cash flow is the difference between project
receipts and expenditures - It is usually expressed graphically
- Since expenditures exceed receipts part of the
time, the contractor is a short term investor in
the project - Contractor must have cash reserves to pay for
labor and materials - Consider the New Jersey contractor PHA
70Cash Flow Diagram - Normal Project
Investment in Project
60 90 days
Positive Cash Flow Negative Cash Flow
71Cash Flow
- Where the expenditures greatly exceed receipts,
the contractors financial position is seriously
compromised--perhaps leading to bankruptcy - On impacted projects, owners often stop paying
which makes matters worse
72Cash Flow Diagram Impacted Project
Investment in Project
Positive Cash Flow never occurs! Negative Cash
Flow entire project
73Bond Capacity
- There are two types of capacities
- project capacity
- aggregate capacity
- Project capacity is the maximum size single
project that the surety will allow the contractor
to undertake - Aggregate capacity is the total amount of
uncompleted work that the surety will bond
74Bond Capacity Equations - Project Capacity
75Bond Capacity Equations - Aggregate Capacity
- Aggregate capacity (Worth of Firm)
76Risk Management
77Owner Strategy
- Recognize and identify risks
- Measure the degree of exposure
- Decide how to protect against those risks
- Develop a company-wide program of loss control
and prevention
78Categories of Risk
- Project risks
- Legal and contractual risks
- Business risks
79Insurance Policy
- A contract where an insurer assumes financial
responsibility for a specific loss
80Differences With Bonds
- Insurance covers specific known losses or risks,
bonds cover a failure to perform - In a bond, the owner is covered over and above
initial contract amounts, insurance may have
fixed limits - In bond defaults, the surety seeks to recover
losses from the contractor
81Insurance Checklist
- Property insurance on project
- Property insurance on contractors property
- Liability insurance
- Employee insurance
- Automobile insurance
82Types of Policies
- Property insurance
- covers the project from damages or loss
- also covers subcontractors
- Builders risk insurance
- normally the basic policy on buildings
- two types are all-risk and named risk the latter
is seldom used
83Types of Policies (cont.)
- Builders risk (cont.)
- policies are flexible and can include many
coverages - covers direct losses, temporary structures,
materials, etc. - may not cover labor losses
- Contractors equipment floater
- covers construction equipment, but not liability
84Types of Policies (cont.)
- Liability insurance
- imposed by law
- Public liability and property damage
- covers liability to third persons
- Workmans compensation
- is a legal requirement
- covers injuries to employees
85Types of Policies (cont.)
- Wrap-up insurance
- owner provides certain coverages
- Owners liability insurance
- Social security
- employers and employees share the cost