Title: Construction Contract Administration
1Construction Contract Administration
2Randy Over
- District Construction Engineer, ODOT District 12
Ohio Department of Transportation
3Construction Contract Administration
- Getting Contract Administration off on the Right
Foot.. Prior to PreCon - DBE Goals
- ODOT Qualified DBEs
- Total s Meet Goal or.
- Approved Waiver
- Qualified Staff
- Names and qualifications of engineers and
inspectors - Testing Lab is AMRL certified
4Construction Contract Administration
- Getting Contract Administration off on the Right
Foot.. Prior to PreCon - Make sure District Construction LPA Coordinator
are involved in PreCon planning, 2 weeks prior to
meeting, invitations sent - Draft invoice from District Construction, review
funding amounts and categories w/DCE or designee - Hold stand alone PreAward meeting if LPA and/or
consultant is new to process, project is unique,
etc., otherwise complete by phone or combine
w/PreCon
5Construction Contract Administration
- Getting Contract Administration off on the Right
Foot.. Prior to PreCon - Last, but not least DBE/EEO/Prevailing Wage
personnel understand Federal and State
requirements, District personnel available to
answer questions, shadow LPA/consultant
personnel
6Construction Contract Administration
- Example
- PreCon/PreAward
- Letter
7Construction Contract Administration
8Construction Contract Administration
- Having a successful PreCon. Best Practices
- Contractor comes prepared with.
- List of subcontractors
- List of suppliers (ODOT approved)
- List of proposed JMFs
- Proposed schedule showing important milestones
- Everyone prepared with.
- Contact info and sign-in sheet
- Contractors and LPA/Consultants Decision Trees
and hierarchy to resolve disputes - LPA/Consultant
- Tape recorded and/or minutes taken and circulated
- Rep of Design Consultant, Testing Lab, ODOT CM,
ODOT LPA Coordinator, District EEO/DBE/Prevailing
Wage, LPA EEO/DBE/Prevailing Wage personnel
9Construction Contract Administration
- The First Shovel of Dirt Has Moved.Best
Practices as the project moves forward - Weekly submissions of payrolls
- Completion of Daily Diaries
- Weekly, Biweekly or Monthly Progress Meetings
including Construction Monitor (CM) - Materials are checked against ODOT certified
materials lists - JMFs are ODOT approved
10Construction Contract Administration
- Example Job Mix Formula (JMF)
11Construction Contract Administration
- The First Shovel of Dirt Has Moved.Best
Practices as the project moves forward - Through District Testing, OMM involved for steel
fab, concrete beam shop approvals, if there is a
timely request and staff is available - Track disposition of failed materials
- Track materials use against PreCon suppliers
12Construction Contract Administration
- Getting Everyone Paid.Best Practices for
submitting invoices and getting approvals - Aim for a 30 day turnaround for all parties.
- Daily Diaries w/quantities
- LPA, Consultant and ODOT reviews in parallel
- 10 working days for ODOT to approve and submit
for reimbursement or direct pay - Central Office turnaround 10 working days
- Include only approved change orders
- Dont pay for it if it isnt acceptable (dont
rely on retainage) - Dont include retainage
- Clearly note 100 local items
13Construction Contract Administration
- Getting Everyone Paid.Best Practices for
submitting invoices and getting approvals - Consultant LPA Staff Invoices
- ODOT approved overhead rates
- Summary sheet
- Include timesheets and/or monthly reports
- Request for increases must be accompanied by
justification, project completion date extended,
extensive extra work, change in overhead rate
mid-project, etc. - Should be in the range or 10-15 of contractor
payments - Requests to District Construction Offices
- Plan for Encumbrance Increases in advance..
- Proof of matching funds paid
14Construction Contract Administration
- Example
- Invoice for
- Contractor
15Construction Contract Administration
- Example
- Invoice for
- Consultants
- LPAs
16Construction Contract Administration
- So there is a changed condition, what next.
- Extend existing bid items.
- Extra Work. No existing bid item
- Funding Caps and Contract limits?
- Contractor wont agree to a price?
- Hope and pray..
- Justification to ODOT for additional funds.
17Construction Contract Administration
- Justification to ODOT for additional funds.
- Establishment of a fair price.
- Extend bid items
- Establish a new bid item, similar work on other
contracts, cost analysis - Last choice, force account
- Required to complete project as scoped
- Doesnt impact environmental approvals/permits
- Communication to CM before work begins
- Approval can be verbal, but noted in writing, via
email or by letter - Summary of smaller changes so costs reconcile
18Construction Contract Administration
- And the Contractor Yells, Unless I am paid for
the claim right now, Im walking off the job!
What to do if you cant agree.. And how to not
get there in the first place - Make everyone follow an administrative process
established prior to bid, preferably as part of
the contract - Use comparatives, historical data such as days in
the bid for traffic control, prorate the days. - Resolve the changed condition if at all possible
without stopping work, otherwise home office
overhead claims could occur, keep the contractor
working
19Construction Contract Administration
- Claims solutions and avoidance
- Pay estimates and changes promptly
- Seek third party assistance, experts that both
parties trust - Use formal Partnering
- Dont write yet another letter when a phone call
or a personal visit has a chance to break the
deadlock - Completing by the completion date is to
everyones benefit, dont be afraid to pay for
some OT, MS concrete, etc., it builds goodwill
with the public and the contractor - Before the attorneys take control, consider
mediation, arbitration, etc., ODOT has names
20Construction Contract Administration
- And one last comment on Claims..
- A contract is overall, an equally shared
agreement although various specific
responsibilities are not equally shared. If
there is no clear solution yet there is agreement
there was a changed condition, split shared
responsibility items in half.
21Construction Contract Administration
- Example
- Justification
- Letter
22Construction Contract Administration
- Adequate DBE/EEO Prevailing Wage Contract
Administration - Weekly payroll submissions and wage checks
- Track the DBE s against goals, approved subs and
suppliers each pay request - DBEs actually doing the work, if not involve
District - Monthly or quarterly DBE reports to District
EEO/DBE - Jobsite EEO Prevailing Wage Posters
- Regular employee interviews, proper records
- Complaint follow-through w/guidance and
communication to District EEO/DBE or Prevailing
Wage
23Construction Contract Administration
- Example
- Monthly
- Prevailing
- Wage
- Report
24Construction Contract Administration
- Example
- DBE
- Quarterly
- Report
25Construction Contract Administration
- Example
- EEO/DBE/Prevailing
- Wage Interview Form
26Construction Contract Administration
- The Project is almost complete..
27Construction Contract Administration
- So the project is open to traffic, but all that
paperwork remains to final the project.. - Final Inspection by contractor, LPA, consultant,
ODOT, official punchlist is developed - All claims resolved or dismissed, both with the
contractor and with 3rd parties - Documentation compiled for failed materials have
been removed or a deduct made - Contractor and DBE subs/suppliers sign affidavits
- Final certification is signed and sealed by the
CPE
28Construction Contract Administration
29Construction Contract Administration
- Remaining paperwork..
- Upon completion of punchlist, ODOT completes the
C-85 - Final estimate is processed when all required
paperwork is completed - District notifies Central Office to close all
encumbrances
30Construction Contract Administration
- Example
- Final Certification
31Construction Contract Administration
32All personnel and their respective employers
portrayed in this example are fictional. Any
resemblance to an existing or proposed project
and involved personnel is purely coincidental.