Construction Contract Administration - PowerPoint PPT Presentation

1 / 32
About This Presentation
Title:

Construction Contract Administration

Description:

Construction Contract Administration Randy Over District Construction Engineer, ODOT District 12 Construction Contract Administration Getting Contract Administration ... – PowerPoint PPT presentation

Number of Views:539
Avg rating:3.0/5.0
Slides: 33
Provided by: LindaB62
Category:

less

Transcript and Presenter's Notes

Title: Construction Contract Administration


1
Construction Contract Administration
2
Randy Over
  • District Construction Engineer, ODOT District 12

Ohio Department of Transportation
3
Construction Contract Administration
  • Getting Contract Administration off on the Right
    Foot.. Prior to PreCon
  • DBE Goals
  • ODOT Qualified DBEs
  • Total s Meet Goal or.
  • Approved Waiver
  • Qualified Staff
  • Names and qualifications of engineers and
    inspectors
  • Testing Lab is AMRL certified

4
Construction Contract Administration
  • Getting Contract Administration off on the Right
    Foot.. Prior to PreCon
  • Make sure District Construction LPA Coordinator
    are involved in PreCon planning, 2 weeks prior to
    meeting, invitations sent
  • Draft invoice from District Construction, review
    funding amounts and categories w/DCE or designee
  • Hold stand alone PreAward meeting if LPA and/or
    consultant is new to process, project is unique,
    etc., otherwise complete by phone or combine
    w/PreCon

5
Construction Contract Administration
  • Getting Contract Administration off on the Right
    Foot.. Prior to PreCon
  • Last, but not least DBE/EEO/Prevailing Wage
    personnel understand Federal and State
    requirements, District personnel available to
    answer questions, shadow LPA/consultant
    personnel

6
Construction Contract Administration
  • Example
  • PreCon/PreAward
  • Letter

7
Construction Contract Administration
  • Example
  • PreAward
  • Outline

8
Construction Contract Administration
  • Having a successful PreCon. Best Practices
  • Contractor comes prepared with.
  • List of subcontractors
  • List of suppliers (ODOT approved)
  • List of proposed JMFs
  • Proposed schedule showing important milestones
  • Everyone prepared with.
  • Contact info and sign-in sheet
  • Contractors and LPA/Consultants Decision Trees
    and hierarchy to resolve disputes
  • LPA/Consultant
  • Tape recorded and/or minutes taken and circulated
  • Rep of Design Consultant, Testing Lab, ODOT CM,
    ODOT LPA Coordinator, District EEO/DBE/Prevailing
    Wage, LPA EEO/DBE/Prevailing Wage personnel

9
Construction Contract Administration
  • The First Shovel of Dirt Has Moved.Best
    Practices as the project moves forward
  • Weekly submissions of payrolls
  • Completion of Daily Diaries
  • Weekly, Biweekly or Monthly Progress Meetings
    including Construction Monitor (CM)
  • Materials are checked against ODOT certified
    materials lists
  • JMFs are ODOT approved

10
Construction Contract Administration
  • Example Job Mix Formula (JMF)

11
Construction Contract Administration
  • The First Shovel of Dirt Has Moved.Best
    Practices as the project moves forward
  • Through District Testing, OMM involved for steel
    fab, concrete beam shop approvals, if there is a
    timely request and staff is available
  • Track disposition of failed materials
  • Track materials use against PreCon suppliers

12
Construction Contract Administration
  • Getting Everyone Paid.Best Practices for
    submitting invoices and getting approvals
  • Aim for a 30 day turnaround for all parties.
  • Daily Diaries w/quantities
  • LPA, Consultant and ODOT reviews in parallel
  • 10 working days for ODOT to approve and submit
    for reimbursement or direct pay
  • Central Office turnaround 10 working days
  • Include only approved change orders
  • Dont pay for it if it isnt acceptable (dont
    rely on retainage)
  • Dont include retainage
  • Clearly note 100 local items

13
Construction Contract Administration
  • Getting Everyone Paid.Best Practices for
    submitting invoices and getting approvals
  • Consultant LPA Staff Invoices
  • ODOT approved overhead rates
  • Summary sheet
  • Include timesheets and/or monthly reports
  • Request for increases must be accompanied by
    justification, project completion date extended,
    extensive extra work, change in overhead rate
    mid-project, etc.
  • Should be in the range or 10-15 of contractor
    payments
  • Requests to District Construction Offices
  • Plan for Encumbrance Increases in advance..
  • Proof of matching funds paid

14
Construction Contract Administration
  • Example
  • Invoice for
  • Contractor

15
Construction Contract Administration
  • Example
  • Invoice for
  • Consultants
  • LPAs

16
Construction Contract Administration
  • So there is a changed condition, what next.
  • Extend existing bid items.
  • Extra Work. No existing bid item
  • Funding Caps and Contract limits?
  • Contractor wont agree to a price?
  • Hope and pray..
  • Justification to ODOT for additional funds.

17
Construction Contract Administration
  • Justification to ODOT for additional funds.
  • Establishment of a fair price.
  • Extend bid items
  • Establish a new bid item, similar work on other
    contracts, cost analysis
  • Last choice, force account
  • Required to complete project as scoped
  • Doesnt impact environmental approvals/permits
  • Communication to CM before work begins
  • Approval can be verbal, but noted in writing, via
    email or by letter
  • Summary of smaller changes so costs reconcile

18
Construction Contract Administration
  • And the Contractor Yells, Unless I am paid for
    the claim right now, Im walking off the job!
    What to do if you cant agree.. And how to not
    get there in the first place
  • Make everyone follow an administrative process
    established prior to bid, preferably as part of
    the contract
  • Use comparatives, historical data such as days in
    the bid for traffic control, prorate the days.
  • Resolve the changed condition if at all possible
    without stopping work, otherwise home office
    overhead claims could occur, keep the contractor
    working

19
Construction Contract Administration
  • Claims solutions and avoidance
  • Pay estimates and changes promptly
  • Seek third party assistance, experts that both
    parties trust
  • Use formal Partnering
  • Dont write yet another letter when a phone call
    or a personal visit has a chance to break the
    deadlock
  • Completing by the completion date is to
    everyones benefit, dont be afraid to pay for
    some OT, MS concrete, etc., it builds goodwill
    with the public and the contractor
  • Before the attorneys take control, consider
    mediation, arbitration, etc., ODOT has names

20
Construction Contract Administration
  • And one last comment on Claims..
  • A contract is overall, an equally shared
    agreement although various specific
    responsibilities are not equally shared. If
    there is no clear solution yet there is agreement
    there was a changed condition, split shared
    responsibility items in half.

21
Construction Contract Administration
  • Example
  • Justification
  • Letter

22
Construction Contract Administration
  • Adequate DBE/EEO Prevailing Wage Contract
    Administration
  • Weekly payroll submissions and wage checks
  • Track the DBE s against goals, approved subs and
    suppliers each pay request
  • DBEs actually doing the work, if not involve
    District
  • Monthly or quarterly DBE reports to District
    EEO/DBE
  • Jobsite EEO Prevailing Wage Posters
  • Regular employee interviews, proper records
  • Complaint follow-through w/guidance and
    communication to District EEO/DBE or Prevailing
    Wage

23
Construction Contract Administration
  • Example
  • Monthly
  • Prevailing
  • Wage
  • Report

24
Construction Contract Administration
  • Example
  • DBE
  • Quarterly
  • Report

25
Construction Contract Administration
  • Example
  • EEO/DBE/Prevailing
  • Wage Interview Form

26
Construction Contract Administration
  • The Project is almost complete..

27
Construction Contract Administration
  • So the project is open to traffic, but all that
    paperwork remains to final the project..
  • Final Inspection by contractor, LPA, consultant,
    ODOT, official punchlist is developed
  • All claims resolved or dismissed, both with the
    contractor and with 3rd parties
  • Documentation compiled for failed materials have
    been removed or a deduct made
  • Contractor and DBE subs/suppliers sign affidavits
  • Final certification is signed and sealed by the
    CPE

28
Construction Contract Administration
  • Example
  • DBE Affidavit

29
Construction Contract Administration
  • Remaining paperwork..
  • Upon completion of punchlist, ODOT completes the
    C-85
  • Final estimate is processed when all required
    paperwork is completed
  • District notifies Central Office to close all
    encumbrances

30
Construction Contract Administration
  • Example
  • Final Certification

31
Construction Contract Administration
  • Example
  • C-85

32
All personnel and their respective employers
portrayed in this example are fictional. Any
resemblance to an existing or proposed project
and involved personnel is purely coincidental.
Write a Comment
User Comments (0)
About PowerShow.com