INFRASTRUCTURE DELIVERY IN THE UMGUNGUNDLOVU REGION Presentation to Chief Director: Umgungundlovu Region Date: 14 October 2005 - PowerPoint PPT Presentation

1 / 26
About This Presentation
Title:

INFRASTRUCTURE DELIVERY IN THE UMGUNGUNDLOVU REGION Presentation to Chief Director: Umgungundlovu Region Date: 14 October 2005

Description:

Title: PowerPoint Presentation Author: corrie Created Date: 5/25/2005 4:14:44 AM Document presentation format: On-screen Show Other titles: Arial Tahoma Wingdings ... – PowerPoint PPT presentation

Number of Views:49
Avg rating:3.0/5.0
Slides: 27
Provided by: cor7151
Category:

less

Transcript and Presenter's Notes

Title: INFRASTRUCTURE DELIVERY IN THE UMGUNGUNDLOVU REGION Presentation to Chief Director: Umgungundlovu Region Date: 14 October 2005


1
INFRASTRUCTURE DELIVERY IN THE
UMGUNGUNDLOVU REGIONPresentation to Chief
Director Umgungundlovu Region Date 14 October
2005
2
Overview
  • Key messages
  • Situation analysis
  • Complication
  • Resolution

3
Key Message
  • Current non transparent and inefficient processes
    can be radically overhauled to improve service
    delivery

4
Situation
  • Overly complicated and non transparent process of
    infrastructure planning, without link to budget,
    including poor consultation and communication
    with stakeholders such as community, principals,
    governing bodies etc resulting in inadequate and
    inappropriate products and dissatisfaction
    amongst stakeholders

5
Situation
  • 1415 schools in region (2005)
  • 565 375 learners (2003)
  • Shortfall of 2270 classrooms in the region (on 1
    40 norm, disregarding specialist rooms)
  • Excessive response time on maintenance requests
  • Principals office petrol bombed, reported on 13
    September but no action yet
  • Conservancy tank at school overflowing, reported
    in March 2001 but still not attended to
  • Burst water pipe reported in September and now
    water bill is R7000 per month

6
(No Transcript)
7
Situation
  • Complicated and non transparent processes for
    addressing need for new buildings, additions and
    repairs.
  • Reporting of needs happens either to Mr Bulcock
    or department of Works or Municipality. Seems as
    if Mr Bulcock is contact point for 1415 schools
  • Budget centralised at head office for new
    buildings, additions and upgrades, at region for
    maintenance.

8
Pace of response things are not happening at
the pace they should and the Department of
Education should be man enough to admit this
  • Information base for doing prioritisation flawed
    EMIS information is suspect at best of times

Classrooms needed badly more classrooms in
schools is promised every year and is not at all
fulfilled we have the problem that projects
should have been done in 2001 but up to now
nothing..
9
Situation
  • No input and accountability from other layers and
    managers especially circuits and wards
  • One Director in head office dealing with 5695
    schools

At present it is extremely difficult to provide
exact details on the number, type, conditions and
utilisation of all school building and related
infrastructure KZN DOE infrastructure plan
2005/06
10
Situation
  • Delivery rate vs need? (2 new schools built since
    1994. In 2005 budget monies allocated to 6
    schools but not one has taken off yet)
  • Turnaround time for maintenance request from
    region to Works for quote around 2 months.
    Average 30 requests per region per month (low
    relative to number of schools - 25 per year)
    Poor tracking of requests due to various channels
    to obtain quote
  • Average cost of classroom at R3300 per sq meter

11
Building costs for class rooms seem high
12
Complication
  • School budgets which should be used for
    educational purposes are channeled towards
    infrastructure maintenance
  • Feedback loop to inform principals on status of
    their requests does not exist
  • Track on expenditure of maintenance budget non
    existent
  • Unclear consultation process with principals
    feeling that not enough inputs are given
  • Roles of all stakeholders not clear

13
Complication
  • Demographic shifts makes infrastructure planning
    difficult e.g. Inter provincial migration of
    learners from Eastern Cape (120 out of 1035
    pupils in one school)
  • No link between project approval and budget
    available
  • Physical planning process driven by units in
    regions and head office, both understaffed.

Post Total Filled Vacant
CES 1 1 0
DCES 3 2 1
FES 4 1 3
14
Complication
  • No feedback to principals on progress with regard
    to priority position of project
  • Criteria that determine priority not clearly
    defined and communicated
  • Inappropriate skills for planning and project
    management
  • No clarity exists in the role the ward and
    circuit level should perform.
  • Process change not communicated for example the
    change to put requests through regional office to
    Works

15
Complication
  • No system documented. Institutional memory
    captured in specific individuals
  • Organisational misplacement of unit with
    supervisory skills not in line with those needed
    for oversight of unit
  • Implementation agent is Works department with
    their own capacity constraints
  • Principal requests more classrooms but head
    office insists that they will build storerooms
  • Kwa Mpungose school built with oversupply of
    classrooms even though the oversupply was
    indicated by the principal before construction
    was completed

16
Resolution
  • PROCESS SIMPLIFICATION
  • MAINTENANCE FOR AMOUNTS NOT EXCEEDING R5000
  • Decentralise budget to ward for section 20
    Schools and for section 21 schools to the school
    itself R25 000 per school
  • Establish database of SME service providers in
    local community with long term contracts. To be
    used with 3 quote system and on rotational basis
  • Publish one page idiots guide with process map
    for all schools,principals and inspectors
  • Pilot in one ward per district before rollout

17
A process map for maintenance under R5000
(Section 20)
School requests
Submits to Ward
Commission
Obtain 3 Quotes from service provider
Selection
Signs off
Ward Pays
School
Ward
18
A process map for maintenance under R5000
(Section 21)
School requests
Commission
Obtain 3 Quotes from service providers
Selection
Signs off
School Pays
School
19
Resolution
  • MAINTENACE EXCEEDING R5000
  • Remaining budget to be retained in Regional
    Office
  • Submit request to works and copy regional office
    see process map
  • Publish standard operating procedure and
    communicate to all stakeholders
  • Pilot as indicated for amounts not exceeding R5000

20
A parallel process for major repair submissions
would speed up the process
Approves budgets
School requests
Copy to Region
Region Logs On database
Submits to Works
Investigate Estimate
To Reg.Off For approval
Tenders/ Quotes
Commissions Repair
Signs off
School
Principal Signs off
Pay Works Contractor
Region
Works
21
Resolution
  • New Schools/Upgrades and Additions
  • Link 3 year planning cycle to MTEF thus one
    planning session every three years
  • Publish clear and simple criteria for
    prioritisation which must be transparent.
  • Publish idiots guide and process maps for all
    stakeholders

22
Resolution
  • COMMUNICATION AND CONSULTATION
  • Establish District Principals Forum (or existing
    structure)
  • To include principals,SEMs and relevant staff
    from the region where necessary
  • Forum to meet quarterly to minimise periods away
    from school
  • Deal with all issues relevant to functionality of
    schools
  • For new schools
  • Ward Committes/Councillors and principals with
    schools in close proximity
  • For Upgrades and Additions
  • SGBs and Prinicipal

23
Resolution
  • FEEDBACK
  • Once priority list is finalised it must indicate
    only funded projects which must be communicated
    to principals and SEMs in writing
  • Develop and set up M E tracking system in
    Regional Office Client updates every 2 months
  • Publish service standards including turnaround
    times

24
Resolution
  • TACKLE BACKLOGS THROUGH ACCELERATED DELIVERY
    PROCESS PROJECT ACCELERATE
  • Establish Project office War Room
  • Use extra capacity, freed from line duties to
    focus on backlog
  • Draw in IDIP for technical support
  • Mobilise EPWP process and resources
  • Utilise excess personnel that can be deployed
    from Education and other departments
  • Undertake needs assessment for ECD and Special
    Schools in consultation with Social Welfare

25
Resolution
  • LOBBY FOR DECENTRALISATION OF CAPITAL BUDGET FROM
    HEAD OFFICE TO REGION
  • Region to manage both capital and current budget

26
Areas for further attention
  • Expenditure tracking
  • Allocation of budget and link to other
    role-players such as Head Office and Works
  • More innovative responses such as Enviro loo,
    more mobile classes etc.
  • Required skills levels in relation to existing
    skills
  • Investigate current cost structures