Title: INFRASTRUCTURE DELIVERY IN THE UMGUNGUNDLOVU REGION Presentation to Chief Director: Umgungundlovu Region Date: 14 October 2005
1 INFRASTRUCTURE DELIVERY IN THE
UMGUNGUNDLOVU REGIONPresentation to Chief
Director Umgungundlovu Region Date 14 October
2005
2Overview
- Key messages
- Situation analysis
- Complication
- Resolution
3Key Message
- Current non transparent and inefficient processes
can be radically overhauled to improve service
delivery
4Situation
- Overly complicated and non transparent process of
infrastructure planning, without link to budget,
including poor consultation and communication
with stakeholders such as community, principals,
governing bodies etc resulting in inadequate and
inappropriate products and dissatisfaction
amongst stakeholders
5Situation
- 1415 schools in region (2005)
- 565 375 learners (2003)
- Shortfall of 2270 classrooms in the region (on 1
40 norm, disregarding specialist rooms) - Excessive response time on maintenance requests
- Principals office petrol bombed, reported on 13
September but no action yet - Conservancy tank at school overflowing, reported
in March 2001 but still not attended to - Burst water pipe reported in September and now
water bill is R7000 per month
6(No Transcript)
7Situation
- Complicated and non transparent processes for
addressing need for new buildings, additions and
repairs. - Reporting of needs happens either to Mr Bulcock
or department of Works or Municipality. Seems as
if Mr Bulcock is contact point for 1415 schools - Budget centralised at head office for new
buildings, additions and upgrades, at region for
maintenance.
8Pace of response things are not happening at
the pace they should and the Department of
Education should be man enough to admit this
- Information base for doing prioritisation flawed
EMIS information is suspect at best of times
Classrooms needed badly more classrooms in
schools is promised every year and is not at all
fulfilled we have the problem that projects
should have been done in 2001 but up to now
nothing..
9Situation
- No input and accountability from other layers and
managers especially circuits and wards - One Director in head office dealing with 5695
schools
At present it is extremely difficult to provide
exact details on the number, type, conditions and
utilisation of all school building and related
infrastructure KZN DOE infrastructure plan
2005/06
10Situation
- Delivery rate vs need? (2 new schools built since
1994. In 2005 budget monies allocated to 6
schools but not one has taken off yet) - Turnaround time for maintenance request from
region to Works for quote around 2 months.
Average 30 requests per region per month (low
relative to number of schools - 25 per year)
Poor tracking of requests due to various channels
to obtain quote - Average cost of classroom at R3300 per sq meter
11Building costs for class rooms seem high
12Complication
- School budgets which should be used for
educational purposes are channeled towards
infrastructure maintenance - Feedback loop to inform principals on status of
their requests does not exist - Track on expenditure of maintenance budget non
existent - Unclear consultation process with principals
feeling that not enough inputs are given - Roles of all stakeholders not clear
13Complication
- Demographic shifts makes infrastructure planning
difficult e.g. Inter provincial migration of
learners from Eastern Cape (120 out of 1035
pupils in one school) - No link between project approval and budget
available - Physical planning process driven by units in
regions and head office, both understaffed. -
Post Total Filled Vacant
CES 1 1 0
DCES 3 2 1
FES 4 1 3
14Complication
- No feedback to principals on progress with regard
to priority position of project - Criteria that determine priority not clearly
defined and communicated - Inappropriate skills for planning and project
management - No clarity exists in the role the ward and
circuit level should perform. - Process change not communicated for example the
change to put requests through regional office to
Works
15Complication
- No system documented. Institutional memory
captured in specific individuals - Organisational misplacement of unit with
supervisory skills not in line with those needed
for oversight of unit - Implementation agent is Works department with
their own capacity constraints
- Principal requests more classrooms but head
office insists that they will build storerooms - Kwa Mpungose school built with oversupply of
classrooms even though the oversupply was
indicated by the principal before construction
was completed
16Resolution
- PROCESS SIMPLIFICATION
- MAINTENANCE FOR AMOUNTS NOT EXCEEDING R5000
- Decentralise budget to ward for section 20
Schools and for section 21 schools to the school
itself R25 000 per school - Establish database of SME service providers in
local community with long term contracts. To be
used with 3 quote system and on rotational basis - Publish one page idiots guide with process map
for all schools,principals and inspectors - Pilot in one ward per district before rollout
17A process map for maintenance under R5000
(Section 20)
School requests
Submits to Ward
Commission
Obtain 3 Quotes from service provider
Selection
Signs off
Ward Pays
School
Ward
18A process map for maintenance under R5000
(Section 21)
School requests
Commission
Obtain 3 Quotes from service providers
Selection
Signs off
School Pays
School
19Resolution
- MAINTENACE EXCEEDING R5000
- Remaining budget to be retained in Regional
Office - Submit request to works and copy regional office
see process map - Publish standard operating procedure and
communicate to all stakeholders - Pilot as indicated for amounts not exceeding R5000
20A parallel process for major repair submissions
would speed up the process
Approves budgets
School requests
Copy to Region
Region Logs On database
Submits to Works
Investigate Estimate
To Reg.Off For approval
Tenders/ Quotes
Commissions Repair
Signs off
School
Principal Signs off
Pay Works Contractor
Region
Works
21Resolution
- New Schools/Upgrades and Additions
- Link 3 year planning cycle to MTEF thus one
planning session every three years - Publish clear and simple criteria for
prioritisation which must be transparent. - Publish idiots guide and process maps for all
stakeholders
22Resolution
- COMMUNICATION AND CONSULTATION
- Establish District Principals Forum (or existing
structure) - To include principals,SEMs and relevant staff
from the region where necessary - Forum to meet quarterly to minimise periods away
from school - Deal with all issues relevant to functionality of
schools - For new schools
- Ward Committes/Councillors and principals with
schools in close proximity - For Upgrades and Additions
- SGBs and Prinicipal
23Resolution
- FEEDBACK
- Once priority list is finalised it must indicate
only funded projects which must be communicated
to principals and SEMs in writing - Develop and set up M E tracking system in
Regional Office Client updates every 2 months - Publish service standards including turnaround
times
24Resolution
- TACKLE BACKLOGS THROUGH ACCELERATED DELIVERY
PROCESS PROJECT ACCELERATE - Establish Project office War Room
- Use extra capacity, freed from line duties to
focus on backlog - Draw in IDIP for technical support
- Mobilise EPWP process and resources
- Utilise excess personnel that can be deployed
from Education and other departments - Undertake needs assessment for ECD and Special
Schools in consultation with Social Welfare
25Resolution
- LOBBY FOR DECENTRALISATION OF CAPITAL BUDGET FROM
HEAD OFFICE TO REGION - Region to manage both capital and current budget
26Areas for further attention
- Expenditure tracking
- Allocation of budget and link to other
role-players such as Head Office and Works - More innovative responses such as Enviro loo,
more mobile classes etc. - Required skills levels in relation to existing
skills - Investigate current cost structures