Title: Chilled Engineering Systems
1Chilled Engineering SystemsHelping You Be Cool
- Ice Pond Refrigeration System
Derek Britten Roger Connolly Ben Francis Adam
Trudeau Steve Vines
Final Presentation to the Mechanical
Engineering Faculty, Students, Clients and
Guests April 7, 2005
2CO2 Emissions Reductions
- 2002 world FF emissions
- 24.5 billion metric tonnes
- 0.703 kg of CO2 emitted per KWh of energy
produced - Environmental stewardship
- One Tonne Challenge
www.ge-at.iastate.edu
3System Overview
- Evaluate the effectiveness of an ice pond system
- Under development in Norway, Japan
- Potential to save energy and lower emissions
- Kyoto Protocol
- System was created to compare results to vapor
compression system
4System Components
- Ice Reservoir
- Heat Exchanger Support
- Reservoir Cover
- Fan Coil Unit (FCU)
5Selected Pond
- 12 foot diameter
- 3 feet high
- 8 tonnes of ice
- Double liner
- Water tight vinyl
- Protective tarp
6Selected HX Support
- 1 x 4 wood planks
- 2 x 4 wood spacers
- ¼ steel flat bars
- Ice block support
7Selected Heat Exchanger
- 1 M copper piping
- 6 pipe spacing
- Length 51.7m
- 20 PG mix
8FCU SelectionSystem Balancing
- Load Selection
- Cooling Load 12000Btu/hr per 500ft2 (USDOE 2004)
- ½ HVAC Lab 300ft2 2110W
- Qin 2000W
- Trane FCU vs. CES HX
9FCU SelectionModel Chosen
- 4 pass, 2 row horizontal FCU
10Ice Pond Cover
- Design
- Self weight
- 1.8kPa snow load
- Result
- No significant snow accumulation
- Withstood all environmental conditions
11Insulation
- Heat transfer major concern
- Ice preservation during summer
- All reservoir components will be insulated
- Sub-floor
- Reservoir wall
- Protective cover
- Pipes and hoses
12Ice Making
- Began Feb. 17
- Delayed due to warm temps - highs of 7C
- Slow initial production rates
13Ice Making
- Ice farms employed Feb. 21
- Production rate increased 2 - 3x
- Ice making completed in two weeks
14Finished Product
- Core sample showing layers
15Remaining SystemCompression Fittings
16Remaining SystemInterior
17Remaining SystemAir Separator
18Remaining SystemPump Flow Meter
19Measurements
Q mcp?T
- ?T across pool inlet and outlet
- ?T across FCU inlet and outlet
- Control volume temperature
- Power consumed by system
20Measurements
- 10 thermocouples located throughout system
21Control Volume
22Closed Loop Testing
- One 24 hour test
- Test with maximum flow rate 2.3gpm 2100W heat
input
23 Closed Loop Temperatures
24Closed Loop Power
25Closed Loop Testing
- 24 hours
- Average FCU cooling rate 1660W
- Average pool cooling rate 1989W
- Average COP 7.22
- Average system efficiency 83.68
- Estimated 400 kg of ice melted
- Average control volume temp 20.94C
26Open Loop
- Converted system to open loop bypassed heat
exchanger due to mild temperatures
- Compare systems
- Flow rate increased
- 2.9gpm
- Less head loss
- Less viscous
27Open Loop Testing
- Same 2 hour tests as closed loop
- One 2 hour test at maximum flow rate
- One 24 hour test
- Test with maximum flow rate 2.9gpm 2500W heat
input
28 Open Loop Temperatures
29Open Loop Power
30Open Loop Testing
- 24 hours
- Average FCU cooling rate 2264W
- Average pool cooling rate 2892W
- Average COP 9.84
- Average system efficiency 78.45
- Estimated 815 kg of ice melted
- Average control volume temp 19.35C
31Project Assessment
Design Requirement Delivered To Client
Create Working Model to Evaluate Ice Pond System Yes
Volume of Approximately 10 12 m3 10 m3 Reservoir
Overall HX Heat Transfer U 100W/m2K U 130W/m2K
Cool at a Rate of 2kW Max Rate of 2.27kW
System Efficiency of 30 System Efficiency of 80
Budget 5000 Total Cost 5413.51
COP gt COP V/C COP 10 (3x Greater)
32Conclusions
- All tests had a COP gt 5
- Little to no transient operating zone reached
steady state quickly - More melt water less performance
- Open loop is better than closed loop
- ?T between working fluid and air
- Mass flow rate
- Cp of working fluid
Q mcp?T
33Conclusions
- Need a powerful system for low temperatures
- No energy consumed for ice making
- System efficiency high because of cool ambient
temperatures during testing
34Budget
- Estimated Budget 5000.00
- Actual Costs
Ice Reservoir 1235.73
Piping and HXs 2078.06
Ice/ HX Support 238.00
Pool Cover 764.70
Testing Equipment 826.59
Miscellaneous 270.42
Grand Total 5413.51
35CO2 Emissions Reductions
- Environmental stewardship
- One Tonne Challenge
-
- OUR SYSTEM
- Reduced by 3x!
www.ge-at.iastate.edu
36Recommendations
- Full scale model
- Melt water
- No heat exchanger
- Increase space between pool inlet outlet
- Colder outlet temperatures
- Higher flow rates
- Turbulent instead of laminar flow
- Increases rate of heat transfer
- More durable reservoir
- Not dependent on vinyl liner
- Automated ice making system
37Demonstration
38Special Thanks To
- Mr. Richard Rachals
- Dr. Murat Koksal
- Albert Murphy
- Greg Jollimore
- Dr. Peter Allen
- Import Tool Corporation
- Jeff MacNeil of Trane
- Mike Trudeau of HCDJ
39Questions?
40(No Transcript)