Resource Loading and Leveling - PowerPoint PPT Presentation

1 / 14
About This Presentation
Title:

Resource Loading and Leveling

Description:

Title: Introduction to Project Management Lecture Outline Author: Mark Keil Last modified by: Kathy Schwaig Created Date: 8/11/2000 8:05:42 PM Document presentation ... – PowerPoint PPT presentation

Number of Views:2203
Avg rating:3.0/5.0
Slides: 15
Provided by: MarkK153
Category:

less

Transcript and Presenter's Notes

Title: Resource Loading and Leveling


1
Resource Loading and Leveling
  • Kathy S. Schwaig

2
A Roadmap of the Project Planning Process
  • Develop project charter
  • Establish work breakdown structure
  • Analyze sequencing relationships
  • Estimate normal activity durations
  • Perform network calculations
  • Validate/revise initial schedule
  • Perform time-cost tradeoff analysis
  • Load resources to activities
  • Resolve any resource/workload imbalances
  • Develop budget and cash flow plan based on
    analysis of direct and indirect costs

Our Focus Today
3
What is a Resource?
  • Whats a resource?
  • A resource is any entity that contributes to the
    accomplishment of project activities
  • Personnel
  • Equipment
  • Contractors
  • Space
  • Materials

4
Resource Planning
  • Resource planning is the process of making sure
    resources are available as required to execute
    the project according to schedule
  • Questions to ask
  • What type of resource is required?
  • How much resource is required?
  • When and how long is the resource needed?
  • Where is the resource required?

5
Resource Loading
  • Resource loading involves specifying the types
    and quantities of resources required to complete
    each activity in a project
  • Note that resources are loaded not at the project
    level, but at the activity level
  • Resources can be identified
  • By name (if you have individual professionals
    with unique skills, this is a reasonable
    approach)
  • By generic type (e.g., system analysts)

6
How Do We Quantify Resources Used?
  • One way is to use some measure of resource usage
  • Programmer days
  • Staff hours
  • Equipment hours
  • Another way is to indicate the number of units of
    resource assigned
  • Programmers
  • Workstations

7
Scheduling Resources
  • A resource requirements list can be constructed
    by listing each activity and the resources that
    will be required
  • Example
  • Required resources are then mapped to the
    activity plan to assess the distribution of
    resources required over the duration of the
    project

Activity Resource Days Notes
Design database Systems Analyst 7 F/T
8
Developing a Resource Profile
9
Developing a Resource Profile
Day
1 2 3 4 5 6 7 8
9 10 11 12 13 14 15
B
F
G
H
I
J
K
10
Developing a Resource Profile
12
10
Ideal profile
8
Resource Requirement (programmers)
6
4
2
1 2 3 4 5 6 7 8 9
10 11 12 13 14 15
Time Period (days)
11
Resolving Workload/Resource Imbalances
  • Request additional resources
  • Plan to work overtime
  • Contract out work
  • Delay start or extend durations of non-critical
    activities
  • Change the approach used to perform the work
  • Reduce project scope or extend project deadline

12
Resource Leveling
  • Scheduling resources by earliest possible start
    date often leads to an uneven resource profile
    that is more likely to call for levels of
    resource beyond those available
  • By adjusting the start date of some activities
    and splitting others, we can achieve a more level
    resource profile, reducing the maximum level of
    demand for limited resources

13
Resource Leveling
  • Allocating a resource to one activity limits the
    flexibility for resource allocation and
    scheduling of other activities
  • Resources should be allocated to activities in
    some rational order
  • The priority must always be to allocate resources
    to critical path activities and then to those
    activities that are most likely to affect others
  • In this way, lower priority activities are made
    to fit around the more critical, already
    scheduled activities

14
Approaches for Prioritizing Activities
  • Total slack priority
  • Activities are ordered according to their to
    total slack, those with the smallest total slack
    having the highest priority
  • Ordered list priority
  • Shortest critical activity
  • Critical activities
  • Shortest non-critical activity
  • Non-critical activity with least slack
  • Non-critical activities
Write a Comment
User Comments (0)
About PowerShow.com