INNOVATIVE SMALL HYDRO TECHNOLOGIES - PowerPoint PPT Presentation

1 / 45
About This Presentation
Title:

INNOVATIVE SMALL HYDRO TECHNOLOGIES

Description:

Title: No Slide Title Author. Last modified by: Ghislain Simard Created Date: 9/16/2002 3:49:58 PM Document presentation format: On-screen Show Company – PowerPoint PPT presentation

Number of Views:162
Avg rating:3.0/5.0
Slides: 46
Provided by: 56861658
Category:

less

Transcript and Presenter's Notes

Title: INNOVATIVE SMALL HYDRO TECHNOLOGIES


1
  • INNOVATIVE SMALL HYDRO TECHNOLOGIES
  • Upgrading Refurbishments (Modernization)
  • Niels M. Nielsen, P.Eng.
  • Manager, Sustainable Energy Solutions
  • BC Hydro Engineering

Waterpower XIII July 2003
2
Introduction
  • INTRODUCTION
  • Of the 30 hydroelectric sites (up to 2,700 MW)
    operated by BChydro, 8 have a capacity lt 20MW.
  • The total capacity of these projects is 53MW -
    roughly 0.5 of the BChydro Generating Capacity
    (10,008MW). Alternatively, the largest 5 projects
    contribute roughly 84 (8,383MW)
  • Small hydro plants pose a special problem as part
    of a large utility
  • Small revenue stream
  • High unit cost based on large scale utility
    processes (Union effect vs. IPP approach)
  • Can have a high environmental/risk profile

3
Introduction
  • These sites require special considerations when
    modernizing
  • Must follow business practices to ensure
    profitability and maximum value
  • Modern equipment (including automation and remote
    control) is required.
  • Low Operation and Maintenance (OM) costs
  • Minimal environmental / risk profile.

4
Innovative Approaches to Modernizing Small Hydro
Plants
  • OUTLINE
  • Modernization Drivers
  • Process to select Modernization Plan
  • Innovative Approaches (examples)
  • Management Approaches (asset planning software,
    implementation, risk management training)
  • Summary

5
MODERNIZATION DRIVERS
6
Innovative Approaches to Modernizing Small Hydro
Plants
  • Small Hydro Asset Life Cycle

10 20 30 40 Stage of Diminishing Returns
7
Innovative Approaches to Modernizing Small Hydro
Plants
  • The Modernization Drivers
  • Modernization provides the best opportunity to
    make changes the drivers include
  • Licensing/regulatory requirements
  • Increased profitability (improved dependability)
  • Reduced labour and/or costs (reduced OM)
  • Competition in the Electricity Market
  • New products (ancillary services)
  • New technology/existing equipment obsolete
  • Changing customer/stakeholder requirements
  • Risk reduction

8
PROCESS TO SELECT MODERNIZATION PLAN
9
Innovative Approaches to Modernizing Small Hydro
Plants
  • Prioritizing Small Hydro Facilities
  • Core
  • Does the plant provide system stability?
  • Strategic
  • Does the facility increase supply in a supply
    constrained region?
  • Does the facility belong to a river system?
  • Non Strategic
  • Financial contributors

10
Innovative Approaches to Modernizing Small Hydro
Plants
  • Establish Need for Capital Investment
  • Criterion used to establish value of each small
    hydro facility

11
Asset Management Process to Modernize Hydro Plants
12
Innovative Approaches to Modernizing Small Hydro
Plants
  • Life Extension Modernization Plan

13
Innovative Approaches to Modernizing Small Hydro
Plants
  • Plant Survey Methodology for Assessing Needs
    Opportunities

14
INNOVATIVE APPROACHES (CASE HISTORIES)
15
Innovative Approaches
16
Innovative Approaches
17
Case Histories - Aberfeldie
Aberfeldie Penstock
18
Case Histories - Aberfeldie
Aberfeldie Turbine Runner
19
Case Histories - Aberfeldie
  • Status Quo
  • 5MW powerhouse built in 1922 (80 years old).
  • Requires 20M of investment to continue to
    operate.
  • Original dam suffered severe deterioration due to
    ice build-up and avalanches - rehabilitated
    in1953 and now meets all current dam safety
    standards.
  • Penstock at end of life.

20
Case Histories - Aberfeldie
  • Potential Solutions
  • Three Options
  • Redevelop to 30 MW with 120 GWh per annum
    (F2006).
  • Refurbish at 5MW
  • Run to failure
  • Refurbishment is not economic
  • Redevelopment is more economic, but not as
    economic as other BC generation development
    options.
  • Recommend different operation. For example,
    contract out routine work.

21
Case Histories - Falls River
22
Case Histories - Falls River
  • Status Quo
  • Two unit powerhouse totaling 7MW - built in 1930
  • Requiring 13 M of investment to continue to
    operate.
  • End of the line, isolated and difficult to access
    (50km south of Prince Rupert)
  • Significant rehabilitation work completed in
    1992
  • Dam stabilized with rock anchors
  • Plant automated (This is a remote plant and
    existing operators were retiring)

23
Case Histories - Falls River
  • Recommendation
  • Redevelop to 20 MW with 78 GWh per annum (F2008).
  • Transmission lines capacity constraints may be an
    issue - Brown lake (operated by IPP) is also on
    this line.
  • Recommend different operation. For example,
    contract out routine work.

24
Case Histories - Shuswap
Shuswap Penstock (summer)
25
Case Histories - Shuswap
Shuswap Penstock (winter)
26
Case Histories - Shuswap
  • Status Quo
  • 6MW powerhouse built in 1929.
  • Project comprises of Wilsey and Sugar Lake Dam
    located at 35km and 55km east of Vernon
  • Challenges
  • Downstream of the plant is a fish hatchery in
    addition to a high value natural salmon stream
  • Deteriorating wood stave penstock and surge tank
    on failing rock fill foundation (also rock-fall
    hazard at tunnel/penstock interface)
  • Rehabilitation of low level outlet in dam was
    required

27
Case Histories - Shuswap
  • Solutions
  • Bypass Valve installed for reliable water release
    at facility if unit trips (low level outlets are
    not automated)
  • In 1993, the facility was refurbished/rebuilt
  • one penstock was rebuilt in steel. The surge
    tower was eliminated - not required for steel
    penstock.
  • Generating unit refurbished during penstock
    rebuild.
  • Low level outlets refurbished

28
Case Histories - Woodfibre
Woodfibre penstock, screen house and surge tank
29
Case Histories - Woodfibre
  • Woodfibre mill built in 1955 is located near
    Squamish, BC. The electricity needs of the mill
    are provided by a 2.5MW Pelton wheel impulse
    turbine.
  • Age related efficiency losses
  • Reduced output 2.1 MW (1955) to 1.5 MW
  • Deteriorating penstock (16)
  • Reduced turbine efficiency (1)
  • Realigned penstock (additional 90 degree bends
    and valves - following slide) (1)
  • Increased mill use of high pressure water (10)

30
Case Histories - Woodfibre
Penstock realignment for Mill Expansion
31
Case Histories - Woodfibre
  • Generation/water supply challenges
  • Long penstock for mill water supply - too
    expensive to replace for turbine use only.
  • Penstock realignment is not cost effective.
  • New Pelton wheel marginally cost effective.
  • Solutions
  • Benefits from improved management of the source
    of high pressure mill water and adjustment to
    turbine operating point.
  • Run until end of life. At this point, penstock
    replacement is justifiable.

32
Case Histories - Butlers Gorge
Tasmania, Australia
33
Case Histories - Butlers Gorge
  • Status Quo
  • 12.7MW powerhouse commissioned in 1951
  • Static Head of 50m (Butlers lake)
  • The water from the lake also supplies Tarraleah
    power station via a tunnel then canal. Before
    entering the tunnel, energy is dissipated via an
    energy dissipater valve (next slide).
  • Recommendations
  • Develop a mini hydro project to take advantage of
    lost energy. Replace energy dissipater valve with
    a 2.5MW turbine.

34
Case Histories - Butlers Gorge
Energy dissipater valve in operation
35
MANAGEMENT APPROACHES
36
Facility Asset Planning
37
Asset Management
  • APTUS Asset Planning System
  • APTUS is a software tool that streamlines the
    Asset Planning process.
  • APTUS uses a discounted cash flow that recognizes
    economic and financial methods to provide
    decision support regarding capital and operating
    investment decisions. It also addresses
    non-financial issues using multiple account
    analysis.
  • APTUS has the ability to analyze the value of a
    portfolio of assets in a market context, and
    hence the value added from asset enhancements or
    risk reduction initiatives
  • Information from engineering assessments is
    stored and used as input.
  • Report provide a ranking of projects based on
    standard criteria NPV, PV of EVA, B-C and value
    weighted non financial criteria.
  • Model has flexibility to interact with enterprise
    software packages (PeopleSoft, SAP, JD Edwards
    etc.) It can also be used on a stand alone basis.

38
Aptus Financial Model Overview
39
Aptus Base Case Forecasting
Customer Classes Peak/Load Profile Growth
Forecasts Rate Forecasts Market Prices
Demand Forecast
Core
Base Case Business Model
Report Structure
Supply Forecast
Asset Classes Generation/Supply Profile
Expansion Forecasts Variable Cost
Forecasts Other Production Costs
40
Aptus Scenario Planning Model
Financial Return Goals liquidity, activity,
return, coverage Supply Mix Objectives
hydro, fossil, renewable, etc. Other Triple
Bottom Line Goals
Financial Performance Goals
Framework
Scenario Planning Model
What if? What is the effect?
Report Structure
Macro Variable Changes demand, supply,
growth, price, etc. Micro Variables Changes
spending, discount rates, etc. Sensitivity
Analysis
Risk Opportunity
41
Reports Menu
42
Innovative Approaches to Modernizing Small Hydro
Plants
  • Investment Risk Minimized

43
Risk Management
  • Strategic Objective (overall goal for each small
    hydro project)
  • Project Objectives, covering safety, financial,
    power quality, dependability, compliance, etc.
  • Risk Assessment of likelihood and consequences of
    plant not meeting objectives
  • Risk Management includes measures to ensure
    objectives met.

44
Innovative Approaches to Modernizing Small Hydro
Plants
  • Training
  • The application of knowledge is a crucial part of
    a change process. To learn and benefit from new
    approaches to modernization, two initiatives are
    available
  • Through a management consulting arrangement with
    roll-out of a modernization plan on a specific
    plant and hands on training for future work.
  • Classroom workshop simulation training to
    promote understanding of the methodology.

45
Innovative Approaches to Modernizing Small Hydro
Plants
  • Summary
  • Small Hydro plants age and eventually require
    modernization
  • Present technical and business drivers can be
    markedly different to original considerations.
  • Opportunities often available to increase value.
  • Systematic processes lead to greatest gains
    (asset management).
  • Innovative and new approaches can improve
    modernization outcomes.
Write a Comment
User Comments (0)
About PowerShow.com