Title: INNOVATIVE SMALL HYDRO TECHNOLOGIES
1- INNOVATIVE SMALL HYDRO TECHNOLOGIES
- Upgrading Refurbishments (Modernization)
- Niels M. Nielsen, P.Eng.
- Manager, Sustainable Energy Solutions
- BC Hydro Engineering
-
Waterpower XIII July 2003
2Introduction
- INTRODUCTION
- Of the 30 hydroelectric sites (up to 2,700 MW)
operated by BChydro, 8 have a capacity lt 20MW. - The total capacity of these projects is 53MW -
roughly 0.5 of the BChydro Generating Capacity
(10,008MW). Alternatively, the largest 5 projects
contribute roughly 84 (8,383MW) - Small hydro plants pose a special problem as part
of a large utility - Small revenue stream
- High unit cost based on large scale utility
processes (Union effect vs. IPP approach) - Can have a high environmental/risk profile
3Introduction
- These sites require special considerations when
modernizing - Must follow business practices to ensure
profitability and maximum value - Modern equipment (including automation and remote
control) is required. - Low Operation and Maintenance (OM) costs
- Minimal environmental / risk profile.
4Innovative Approaches to Modernizing Small Hydro
Plants
- OUTLINE
- Modernization Drivers
- Process to select Modernization Plan
- Innovative Approaches (examples)
- Management Approaches (asset planning software,
implementation, risk management training) - Summary
5MODERNIZATION DRIVERS
6Innovative Approaches to Modernizing Small Hydro
Plants
- Small Hydro Asset Life Cycle
10 20 30 40 Stage of Diminishing Returns
7Innovative Approaches to Modernizing Small Hydro
Plants
- The Modernization Drivers
- Modernization provides the best opportunity to
make changes the drivers include - Licensing/regulatory requirements
- Increased profitability (improved dependability)
- Reduced labour and/or costs (reduced OM)
- Competition in the Electricity Market
- New products (ancillary services)
- New technology/existing equipment obsolete
- Changing customer/stakeholder requirements
- Risk reduction
8PROCESS TO SELECT MODERNIZATION PLAN
9Innovative Approaches to Modernizing Small Hydro
Plants
- Prioritizing Small Hydro Facilities
- Core
- Does the plant provide system stability?
- Strategic
- Does the facility increase supply in a supply
constrained region? - Does the facility belong to a river system?
- Non Strategic
- Financial contributors
10Innovative Approaches to Modernizing Small Hydro
Plants
- Establish Need for Capital Investment
- Criterion used to establish value of each small
hydro facility
11Asset Management Process to Modernize Hydro Plants
12Innovative Approaches to Modernizing Small Hydro
Plants
- Life Extension Modernization Plan
13Innovative Approaches to Modernizing Small Hydro
Plants
- Plant Survey Methodology for Assessing Needs
Opportunities
14INNOVATIVE APPROACHES (CASE HISTORIES)
15Innovative Approaches
16Innovative Approaches
17Case Histories - Aberfeldie
Aberfeldie Penstock
18Case Histories - Aberfeldie
Aberfeldie Turbine Runner
19Case Histories - Aberfeldie
- Status Quo
- 5MW powerhouse built in 1922 (80 years old).
- Requires 20M of investment to continue to
operate. - Original dam suffered severe deterioration due to
ice build-up and avalanches - rehabilitated
in1953 and now meets all current dam safety
standards. - Penstock at end of life.
20Case Histories - Aberfeldie
- Potential Solutions
- Three Options
- Redevelop to 30 MW with 120 GWh per annum
(F2006). - Refurbish at 5MW
- Run to failure
- Refurbishment is not economic
- Redevelopment is more economic, but not as
economic as other BC generation development
options. - Recommend different operation. For example,
contract out routine work.
21Case Histories - Falls River
22Case Histories - Falls River
- Status Quo
- Two unit powerhouse totaling 7MW - built in 1930
- Requiring 13 M of investment to continue to
operate. - End of the line, isolated and difficult to access
(50km south of Prince Rupert) - Significant rehabilitation work completed in
1992 - Dam stabilized with rock anchors
- Plant automated (This is a remote plant and
existing operators were retiring)
23Case Histories - Falls River
- Recommendation
- Redevelop to 20 MW with 78 GWh per annum (F2008).
- Transmission lines capacity constraints may be an
issue - Brown lake (operated by IPP) is also on
this line. - Recommend different operation. For example,
contract out routine work.
24Case Histories - Shuswap
Shuswap Penstock (summer)
25Case Histories - Shuswap
Shuswap Penstock (winter)
26Case Histories - Shuswap
- Status Quo
- 6MW powerhouse built in 1929.
- Project comprises of Wilsey and Sugar Lake Dam
located at 35km and 55km east of Vernon - Challenges
- Downstream of the plant is a fish hatchery in
addition to a high value natural salmon stream - Deteriorating wood stave penstock and surge tank
on failing rock fill foundation (also rock-fall
hazard at tunnel/penstock interface) - Rehabilitation of low level outlet in dam was
required
27Case Histories - Shuswap
- Solutions
- Bypass Valve installed for reliable water release
at facility if unit trips (low level outlets are
not automated) - In 1993, the facility was refurbished/rebuilt
- one penstock was rebuilt in steel. The surge
tower was eliminated - not required for steel
penstock. - Generating unit refurbished during penstock
rebuild. - Low level outlets refurbished
28Case Histories - Woodfibre
Woodfibre penstock, screen house and surge tank
29Case Histories - Woodfibre
- Woodfibre mill built in 1955 is located near
Squamish, BC. The electricity needs of the mill
are provided by a 2.5MW Pelton wheel impulse
turbine. - Age related efficiency losses
- Reduced output 2.1 MW (1955) to 1.5 MW
- Deteriorating penstock (16)
- Reduced turbine efficiency (1)
- Realigned penstock (additional 90 degree bends
and valves - following slide) (1) - Increased mill use of high pressure water (10)
30Case Histories - Woodfibre
Penstock realignment for Mill Expansion
31Case Histories - Woodfibre
- Generation/water supply challenges
- Long penstock for mill water supply - too
expensive to replace for turbine use only. - Penstock realignment is not cost effective.
- New Pelton wheel marginally cost effective.
- Solutions
- Benefits from improved management of the source
of high pressure mill water and adjustment to
turbine operating point. - Run until end of life. At this point, penstock
replacement is justifiable.
32Case Histories - Butlers Gorge
Tasmania, Australia
33Case Histories - Butlers Gorge
- Status Quo
- 12.7MW powerhouse commissioned in 1951
- Static Head of 50m (Butlers lake)
- The water from the lake also supplies Tarraleah
power station via a tunnel then canal. Before
entering the tunnel, energy is dissipated via an
energy dissipater valve (next slide). - Recommendations
- Develop a mini hydro project to take advantage of
lost energy. Replace energy dissipater valve with
a 2.5MW turbine.
34Case Histories - Butlers Gorge
Energy dissipater valve in operation
35MANAGEMENT APPROACHES
36Facility Asset Planning
37Asset Management
- APTUS Asset Planning System
- APTUS is a software tool that streamlines the
Asset Planning process. - APTUS uses a discounted cash flow that recognizes
economic and financial methods to provide
decision support regarding capital and operating
investment decisions. It also addresses
non-financial issues using multiple account
analysis. - APTUS has the ability to analyze the value of a
portfolio of assets in a market context, and
hence the value added from asset enhancements or
risk reduction initiatives - Information from engineering assessments is
stored and used as input. - Report provide a ranking of projects based on
standard criteria NPV, PV of EVA, B-C and value
weighted non financial criteria. - Model has flexibility to interact with enterprise
software packages (PeopleSoft, SAP, JD Edwards
etc.) It can also be used on a stand alone basis.
38 Aptus Financial Model Overview
39Aptus Base Case Forecasting
Customer Classes Peak/Load Profile Growth
Forecasts Rate Forecasts Market Prices
Demand Forecast
Core
Base Case Business Model
Report Structure
Supply Forecast
Asset Classes Generation/Supply Profile
Expansion Forecasts Variable Cost
Forecasts Other Production Costs
40Aptus Scenario Planning Model
Financial Return Goals liquidity, activity,
return, coverage Supply Mix Objectives
hydro, fossil, renewable, etc. Other Triple
Bottom Line Goals
Financial Performance Goals
Framework
Scenario Planning Model
What if? What is the effect?
Report Structure
Macro Variable Changes demand, supply,
growth, price, etc. Micro Variables Changes
spending, discount rates, etc. Sensitivity
Analysis
Risk Opportunity
41Reports Menu
42Innovative Approaches to Modernizing Small Hydro
Plants
- Investment Risk Minimized
43Risk Management
- Strategic Objective (overall goal for each small
hydro project) - Project Objectives, covering safety, financial,
power quality, dependability, compliance, etc. - Risk Assessment of likelihood and consequences of
plant not meeting objectives - Risk Management includes measures to ensure
objectives met.
44Innovative Approaches to Modernizing Small Hydro
Plants
- Training
- The application of knowledge is a crucial part of
a change process. To learn and benefit from new
approaches to modernization, two initiatives are
available - Through a management consulting arrangement with
roll-out of a modernization plan on a specific
plant and hands on training for future work. - Classroom workshop simulation training to
promote understanding of the methodology.
45Innovative Approaches to Modernizing Small Hydro
Plants
- Summary
- Small Hydro plants age and eventually require
modernization - Present technical and business drivers can be
markedly different to original considerations. - Opportunities often available to increase value.
- Systematic processes lead to greatest gains
(asset management). - Innovative and new approaches can improve
modernization outcomes.