Title: Pacific University
1Pacific University
School of Engineering New Construction Design
Alternatives
Architecture Katie Kozarek
Engineering Christian Heimple
Construction Debbie Sit
Apprentice Christina Cho
Owner Peter Demian
2Presentation Outline
- General Project Information Introduction
- Discipline Constraints Goals
- Alternative 1-4 by Discipline
- Decision Matrix (Pros/Cons of each Alternative)
- Team Process Iteration Examples
- Team Dynamics
- Conclusion
3Pacific Team Project Information
- Engineering School of Pacific University in
Oregon - Location
- Beautiful valley site near Pacific Ocean
- Sunny Pond of about 3000 sq.ft.
- Preservation of existing footprint
- 10,000 sq.ft. per story (3)
- 60 assignable
4Project Constraints
- Total Budget PV 4.1 million
- Structural System Budget 330,000
- Completion Time 1 year, by September 30, 2012
- Occupancy for Lab Facility May 1, 2012
- Soil Condition Rippable Rock
5Design Considerations
- Rebuild a 3-story building for classroom, lab,
office, and auditorium - Design a facility for innovative courses taking a
team approach to engineering design - Put forth creative ideas considering
- Architectural sense of place
- Functional use by occupants
- Listen to team members knowledge-based
notifications to design issues
6 Topography map
- Site considerations
- Small community
- Steep topography
- Cliffs
- Sparse highway system
7 Site map
Small campus Nearby pond Overlooking cliff
8Site photographs
Considerations Cliff Pond
9Campus buildings
Note Brick skin Rectilinear forms
10Structural Engineering Requirements Conditions
- System Requirements
- Steel or concrete frame
- Cast-in-place, post-tensioned, or precast
concrete slab - Geometric Requirements
- Height of structure limited to 30
- Footprint of structure limited to existing
footprints
Pacific University School of Engineering
11Structural Engineering Load Considerations
- Live Loads
- Terrace, Atrium, Storage, Stairwells 100 psf
- Corridors 80 psf
- Auditorium Lobby 60 psf
- Classrooms Offices 50 psf
- Roof 20 psf
- Dead Loads
- Lightweight concrete floor 60 psf
- Metal deck 5 psf
- Flooring, ceiling, lights 12 psf
- Ductwork 5 psf
- Partitions 20 psf
- Exterior Cladding 30 psf
Pacific University School of Engineering
12Structural Engineering Load Considerations
- Seismic Considerations
- Moderate to high seismic activity Zone 3
- Occupancy category, I 1.0
- Rock subsurface
- Wind Considerations
- Design wind speed, V33 85 mph (38m/s)
Pacific University School of Engineering
13Equipment
Track-type Tractor
Hydraulic Crane
Ripper
14Site Plan L-shape
Site Boundary
Main Road Access
Site Main Entrance
Crane
Material Laydown
Material Storage
Office Trailer
Optional Site Entrance
Temporary Road Access
15Site Plan Double Square
Optional Site Entrance
Site Boundary
Main Site Entrance
Crane
Material Laydown
Material Storage
Office Trailer
16Alternative 1 - Architecture
Previous drawings restructured by engineer
Architectural redesign in Alternative 2
17Alternative 1
Previous Section Elevation
18Alternative 1 Option 1 Structural Proposal
- Steel moment resisting frame
- Composite concrete/steel deck (t 4.5)
Pacific University School of Engineering
19Alternative 1 Option 1 Structural Proposal
Pacific University School of Engineering
20Alternative 1 Option 1 Structural Proposal
- Second Floor Structural Plan
- Third Floor Structural Plan
Pacific University School of Engineering
21Alternative 1 Option 1 Structural Proposal
Pacific University School of Engineering
22Alternative 1 Option 1 Structural Proposal
Pacific University School of Engineering
23Alternative 1 Option 1 Structural Proposal
Pacific University School of Engineering
24Alternative 1 Option 2 Structural Proposal
- Cast-in-place concrete frame and two-way concrete
slab (t 6) - Shear walls (t 10)
- Goal To address cost cost concerns of CM
regarding rotunda
Pacific University School of Engineering
25Alternative 1 Option 2 Structural Proposal
Pacific University School of Engineering
26Alternative 1 Option 2 Structural Proposal
- Second Floor Structural Plan
- Foundation Plan
- Main columns have 5x5 spread footings
- Rotunda has 10 drilled piles
Pacific University School of Engineering
27Alternative 1 Option 3 Structural Proposal
- Eccentrically braced steel frame
- Composite steel/concrete deck (t 4.5)
- Goal To address cost and constructability
concerns of previous two options
Pacific University School of Engineering
28Alternative 1 Option 3 Structural Proposal
Pacific University School of Engineering
29Alternative 1 Option 3 Structural Proposal
- Third Floor Structural Plan
- Second Floor Structural Plan
Pacific University School of Engineering
30Alternative 1 Option 3 Structural Proposal
- Gravity load distribution
- Lateral load distribution
Pacific University School of Engineering
31Alternative 1 Construction Issues
- Space frame Construction Method
- Excavated cost for sunken auditorium (20,000 cy)
at about 400,000, 10 of Total Cost - Steel SMRF more labor-intensive then braced
frame Concrete requires CIP
32Alternative 1 Option 3 Schedule Estimate
Total 3.8 Million
Structural 420,000
33Alternative 2 - Parti
- Parti
- Redevelopment of last years idea
How can the design pattern laid above the space
be incorporated and brought into the
building? Can circulation systems become the
pattern? Can the pattern be highlighted with
structure? Can the structure reflect the
patterns form and in turn cause sunshadows to
develop in the interior spaces?
34Alternative 2 - Plans
More Finalized plans
35Alternative 2 Model Views
Auditorium space underground Pattern defined by
structure and pathways Structure filters and
captures sunlight
36Alternative 2
Section through building bringing truss down
through building above stairwells Question to
engineer? Can you make this a load bearing
element in your structural considerations?
37Alternative 2 Option 1 Structural Proposal
- Eccentrically braced steel frame
- Composite steel/concrete deck (t 4.5)
- Basement auditorium (steel space frame or
concrete dome roof) - Goal To meet architects challenge of a radial
layout with the structure integrated into the
north buildings radial hallways
Pacific University School of Engineering
38Alternative 2 Option 1 Structural Proposal
- Second Floor Structural Plan
Pacific University School of Engineering
39Alternative 2 Option 2 Structural Proposal
- Special moment resisting steel frame
- Composite steel/concrete deck (t 4.5)
- Basement auditorium (steel space frame or
concrete dome roof with compression ring) - Goal To eliminate structural conflicts with
architecture
Pacific University School of Engineering
40Alternative 2 Option 2 Structural Proposal
- Second Floor Structural Plan
Pacific University School of Engineering
41Alternative 2 Option 3 Structural Proposal
- Steel frame with shear walls
- Composite steel/concrete deck (t 4.5)
- Basement auditorium (steel space frame or
concrete dome roof with compression ring) - Goal To explore a shear wall alternative
Pacific University School of Engineering
42Alternative 2 Option 3 Structural Proposal
- Second Floor Structural Plan
Pacific University School of Engineering
43Alternative 2 Option 4 Structural Proposal
- North Building visible braced frames along main
corridors - South Building eccentrically braced frames on
exterior walls - Composite steel/concrete deck (t 4.5)
- Basement auditorium (steel space frame or
concrete dome roof) - Goal To integrate functional braced frames into
the north buildings hallways
Pacific University School of Engineering
44Alternative 2 Option 4 Structural Proposal
Pacific University School of Engineering
45Alternative 2 Construction Issues
- Building is separated into two parts
- Cost Consideration for duplication of MEP
systems - Connecting the two parts by 3rd floor skywalk
Potential savings 20 of total cost - Enclosed or Open Radial hallways Life-cycle
Costs - Constructability issues Curved Walls Angled
Connections
46Alternative 2 Schedule Estimate
Milestone 3 Project completion
Milestone 1 Structural System Erected
Milestone 2 Building enclosed
MEP .2.2 Million
Total 6.0 Million
Structural 590,000
47Alternative 2 Revised Estimate
MEP 1.1Million
Total 4.2 Million
Structural400,000
48Alternative 3
Organically growing plans and elevations moving
out from footprint representing natural growth
of coastal habitat provisions for experimental
growth
49Alternative 3 Puzzle Concept
- Option 1 First set of plans
50Alternative 3 Option 1
Changes include moving auditorium to first and
second floor instead of excavation
consequential redesign of some interior spaces
51Alternative 3 Elevation
52Alternative 3 Option 2
- Option 2 involves the L-shaped plan for the site
- It is still working with the puzzle concept
showing its versatility
53Material selection
Each block has own material skin Considered in
construction and structural process
Computer block brick to match surrounding
buildings Administration block wood Student
block wood Auditorium concrete Classroom block
concrete
54Alternative 3 Model
Suggestions made to construction manager and
engineer think about how can we think of this
design as being constructed in separate
functional blocks? Can prefabrication be an
option?
Classroom block Computer block Student
block Faculty block Auditorium
PUZZLE PIECE AS INTERCONNECTING BLOCKS
55Alternative 3 - Interior examples
how can elements from puzzle concept enter into
interior spaces?
56Alternative 3 - Exterior examples
- Isozaki/
- Kurokawa
- How can elements of form
- create interesting spaces?
- Can structure be pushed into
- stipulating form?
- Can functional blocks merge
- to create a whole?
57Alternative 3 Option 1 Structural Proposal
- Steel frame w/ shear walls (t 8)
- Composite steel/concrete deck (t 4.5)
Pacific University School of Engineering
58Alternative 3 Option 1 Structural Proposal
- Second Floor Structural Plan
Pacific University School of Engineering
59Alternative 3 Option 1 Structural Proposal
Pacific University School of Engineering
60Alternative 3 Option 2 Structural Proposal
- Concrete frame w/ shear walls (t 8)
- C-I-P two-way beam supported slab (t 5)
- Post-tensioned cantilever beams and slab
- Goal To explore concrete alternatives
Pacific University School of Engineering
61Alternative 3 Option 2 Structural Proposal
- Second Floor Structural Plan
Pacific University School of Engineering
62Alternative 3 Option 3 Structural Proposal
- Eccentrically braced steel frame
- Composite steel/concrete deck (t 4.5)
- Preferred option for Alternative 2
- Goal A cost and time efficient, constructible
alternative
Pacific University School of Engineering
63Alternative 3 Option 3 Structural Proposal
Pacific University School of Engineering
64Alternative 3 Option 3 Structural Proposal
- Second Floor Structural Plan
Pacific University School of Engineering
65Alternative 3
- Computer Room Instructional Lab located on
different floors Construction Sequence - Trailer rental costs 10,000 vs Late move-in
penalty 37,500 - Pre-cast concrete allows fast erection, yet
relatively expensive for small-scale projects
66Alternative 3 - Option 3 Schedule Estimate
Total 4.0 Million
Structural 460,000
67Alternative 4 - Architecture
- CAD model sent by structural engineer
68Alternative 4
- Breaking down massing
- to make for more usable interior
- spaces outside
- of auditorium
Working on unfolding building to consider
spatial issues
69Alternative 4
Creating circulation
70Alternative 4
How can floating column be replaced to show
load transfer?
- Conceptual plan how can this form fit into the
site? needs to be broken down
71Alternative 4 Option 1 Structural Proposal
- 60 Cable-stayed cantilever over ocean-side cliff
- Composite steel/concrete deck with eccentrically
braced frame
Pacific University School of Engineering
72Alternative 4 Option 1 Structural Proposal
- Structural Concept based on TWA hangar in
Philadelphia and American hangar at San Francisco
International - Design started with engineer to break out of A gt
E gt C pattern and to overcome prior structural
difficulties with previous alternatives
Pacific University School of Engineering
73Alternative 4 Option 1 Structural Proposal
- Cantilevered portion of structure
Pacific University School of Engineering
74Alternative 4 Option 1 Structural Proposal
- Eccentrically braced steel frame
- Composite steel/concrete deck (t 4.5)
Pacific University School of Engineering
75Alternative 4 Option 1 Structural Proposal
Pacific University School of Engineering
76Alternative 4 Option 2 Structural Proposal
- 60 Cable-stayed cantilever over ocean-side cliff
- Shear walls and post-tensioned slab (t 5)
- Cantilevered portions remain steel
- Goal Reduce mast height and reflect architects
revisions
Pacific University School of Engineering
77Alternative 4 Option 3 Structural Proposal
Northeast shoulder removed to accommodate
footprint constraint
Pacific University School of Engineering
78Alternative 4 Option 3 Structural Proposal
2nd Floor Structural Plan
Footprint
Pacific University School of Engineering
79Alternative 4
- Structurally very dynamic, yet repetition aids in
cutting construction costs - Cable-stayed system requires deep pile foundation
- 2nd and 3rd floor cantilever hanging over cliff
require temporary platform for efficient
construction of the exterior wall - Design still young construction input in
structure/materials/method can possibly drive
cost and schedule down
80Alternative 4 Schedule Estimate
81Cost Comparisons
82Decision Matrix AEC
PROS CONS
- Cantilevered walkway over atrium susceptible to
vibration and imposes large moments in connecting
column - Costly atrium space
- May not challenge engineer
- Long cantilevers may be susceptible to vibration
problems - No economies of scale with so many materials
- Circulation undeveloped
- Very irregular layout resulting in a large number
of angled connections - Expensive to construct (curved walls, angled
connections) - No relationship to site or context, lack of
spatial variation creating architectural
limitations - Exceeds height limit and footprint (under review)
- Deep piles require lots of time money, large
overhanging portion
1
- Dynamic, radial, curvilinear, sun pattern
- Semi-regular bays sizes and layout
- Easier to construct (regular layout, little
welding) - Most flexible puzzle piece parti
- material-functional block relationships
- Braced frames have dual purpose of backing
cantilevers lateral load support - Most dynamic interior spaces (auditorium),
sunpatterns, shadowplay - Structure integrated with architecture
- Design speaks to engineering and structure
- Extremely interesting structural system
- Regular structural patterns many common
components throughout
2
3
4
83Team Process Iteration Examples
- Alternative 1 A-gtE-gtC-gtA-gtE-gtC
- Predetermined, old architectural drawings
redesigned - Alternative 2 A-gtE-gtC
- Developed architecturally but needs more
structural and construction advice due to issues
of constructability - Alternative 3 A-gtE-gtC-gtE-gtA-gtC
- Redesign of Alternative 1
- EC advised architect against irregular, oblique
layout - Expensive, angled connections
- A challenges EC to integrate their systems into
the architecture (e.g. exposed structural system) - Alternative 4 E-gtA-gtC-gtA-gtE-gtC
- Design started with engineer
84Team Dynamics
- INTERACTION WITH OWNER
- Very understanding, sensitive, informative b/c
has engineering - Encouraging of ideas outside original scope
- INTERACTION WITH TEAM
- Initial lack of conceptual understanding of each
others fields and roles - Challenge to meet new expectations for next
semester by being informative and understanding
of different expectations and considerations in
the design process - Challenge to be more communicative and outspoken
during the design process
85Consideration of Alternative 4 Redesign as Final
Solution
- Challenging Structural Design
- Feasible in Time and Cost for Construction
without current considerations for material - Architecturally lacks spatial concept and
connection to context
86CONCLUSION
- Considering a fifth alternative
- that can challenge all fields equally