Project Control - PowerPoint PPT Presentation

About This Presentation
Title:

Project Control

Description:

Project Control Kathy S. Schwaig – PowerPoint PPT presentation

Number of Views:33
Avg rating:3.0/5.0
Slides: 14
Provided by: MikeSc55
Category:

less

Transcript and Presenter's Notes

Title: Project Control


1
Project Control
  • Kathy S. Schwaig

2
What is Project Control?
  • Project control is the continuous monitoring of
    the project for deviations from plan (time,
    cost,or quality) and the execution of corrective
    action
  • Project Control involves
  • Finding and solving problems
  • Updating the plan
  • Tracking actual resource usage and costs
  • Project control requires a comprehensive and
    credible (i.e., realistic and up-to-date) plan

3
Two Project Control Approaches
  • Continuously and immediately correct all
    deviations from plan
  • Periodically re-plan remainder of project
  • Which is the better approach?

4
Some Basic Principles of Effective Project Control
  • Completion orientation
  • Near term commitment
  • Preservation of slack
  • Mutual accountability

5
Project Control Meetings
  • Project Control Meetings
  • Frequency of meetings depends on project
    duration, complexity, and uncertainty
  • Provides a forum for activity mangers to report
    activity status information (actual start date,
    along with either actual finish date, remaining
    duration, or estimated finish date)
  • Communication is key
  • Problems need to be put on the table for
    discussion----problems need to be identified and
    diagnosed
  • Discussion/evaluation of courses and action

6
Outcome of Project Control Meetings
  • Select/commit to specific action
  • Analyze impact on project quality/schedule/budget/
    resource plan
  • Revise selected course of action as required
  • Reconfirm individual responsibilities (who is
    going to do what)
  • Project manager prepares updated project plan and
    report

7
Measures of Activity Progress
  • Actual start and finish dates
  • Estimated remaining duration
  • Estimated completion date
  • Percent complete
  • Which one would you choose?

8
Traffic Light Reporting
  • Team members are asked to estimate the likelihood
    of meeting the planned target date
  • One traffic light reporting scheme
  • Green signifies on target
  • Yellow signifies not on target but recoverable
  • Red signifies not on target and recoverable only
    with difficulty
  • Traffic light reporting highlights only the risk
    of non-achievement it is not an attempt to
    estimate work done or to quantify expected delays

9
Monitoring and Controlling Project Costs
  • Cost monitoring is one aspect of project control
  • Not only is it important to control project costs
  • Costs provide an indication of the effort that
    has gone into (or at least been charged to ) a
    project
  • A project might be on schedule but only because
    more money has been spent on activities than
    originally budgeted
  • A cumulative expenditure chart provides a simple
    way to compare actual vs. planned expenditure

10
Limitations of Looking at Project Costs
  • By themselves, project costs tell us little about
    project status
  • Cost charts become much more useful if we add
    projected future costs
  • Calculated by adding the estimated costs of
    uncompleted work to the costs already incurred

11
Earned Value Analysis
  • EVA, or budgeted cost of work performed, has
    become more popular in recent years and
    represents a refinement of cost monitoring
  • EVA is based on assigning a value to each task or
    work package based on the original expenditure
    forecasts
  • The assigned value is the original budgeted cost
    for the item and is known as the baseline budget
    or budgeted cost of work scheduled (BCWS)

12
Earned Value Analysis
  • A task that has not yet started is assigned the
    value of zero
  • When a task is completed, the project is credited
    with the value of the task
  • The total value credited to the project at any
    point is known as the earned value of budgeted
    cost of work performed (BCWP)
  • BCWP can be represented as a value or as a
    percentage of the budgeted cost of work scheduled
    (BCWS)

13
Earned Value Analysis Assigning Values to Tasks
  • Where tasks have been started but are not yet
    complete, some consistent method of assigning an
    earned value must be applied
  • The most conservative approach is to assign a
    value of zero until a task is completed, at which
    point it is assigned 100 of the budgeted value.
Write a Comment
User Comments (0)
About PowerShow.com