Title: Discharge of A Contract
1Discharge of A Contract
2Exam Relevance
3Discharge?
- To be discharged means that a contract is,
completed and no longer binding - Practical consequence is that it is sometimes
important to know when a contract or ones side
of a contract has been completed.
4Discharge by Performance - Summary
- We are really talking about when a party can be
deemed to have completed his obligations under
the contract such he is discharged from future
obligations. Also, in practical terms, it is
usually at this point he can claim the benefit
for which he was promised under the contract. - Two special circumstances
- Where courts view contact as entire or lump
need entire performance of all obligations save
those which are de minimus - Where courts have taken view that contract is
divisible, such that you are paid on Quantum
Meruit for what you have done to date. - Really talking about what it means to perform
ones obligations under a contract such that one
is discharged from obligations and can get the
promised benefit
5Entire Contracts
- The all or nothing rule
- Unless you perform your side exactly, you have
not performed and thus you cant claim your
benefit.
6Cutter v Powell (1795)
- Sailor was promised 30 guineas on completion of
journey died en route - Widow sought payment on QM proportionate to the
amount he had completed - Ct held that Ct was all or nothing ob to pay
only arose when performance complete - One factor the 30 guineas was quite high took
the view that this was essentially being paid by
way of the price for full performance.
7When is a contract entire?
- Question of fact for each case Nash Co v
Hartland (1840) - Vigers v Cook
- UT sued for money for carrying out funeral
- Coffin he used to mask smell burst body could
not be taken into church - UT sought on QM held was not entitled
contract to provide for a funeral was an entire
contract not capable of division into
sub-contracts (i.e. the coffin, the embalming
etc).
8Advice
- Look at nature of contract
- Did the parties intend it to be entire?
- Was it a all in one i.e. whereas constituting
many services, did one party sell himself as
offering it all? - Was there a premium offered for complete
performance?
9Building Contracts
- View where one is to be paid in lump sum, means
that you have to complete entirely before you get
it - Collem v Marum (1871) builder could not part
perform and seek part payment employer is not
bound to pay for half or a quarter of a house
10Sumpter v Hodges (1898)
- Lump sum building contract is an entire contract
i.e. payment depends on completion - Now, if one adopts a half house (i.e. accepts it)
where one has a choice in the matter court may
infer the existence of a new contract (i.e. to
pay for the half house) - Choice is key hereno choice, no inferred contract
11- This may all be a bit harsh
- Mitigated by doctrine of substantial compliance
12Hoenig v Isaacs (1952)
- Builder redecorates flat for 750 but didnt put
in a bookcase as he was supposed to - Cost of remedying was 55
- Held that defect was not substantial in terms of
overall contract entitled to 695 - Denning pointed out that substantial compliance
would usually be found unless breach went to root
of contract!!!!
13Bolton v Mahadeva (1972)
- Install central heating - 560 defective
installation - Cost 130 to fix
- The whole system didnt work held to be a
substantial defect court looked at percentage
cost of repair held substantial performance had
not taken place so not entitled to any payment
14Kincora Builders v Cronin (1973)
- Builder did not insulate ceiling of house
- No substantial performance of overall job
- Overall costs 6000
- Insulation probably around 350 and noted as
very small in proportion by Pringle J
15Discharge by Agreement
- 1. Termination through Accord and Satisfaction
- We agree to discharge (need consideration etc)
- Probably best to put it in writing
- Usually fine if executory, but really need watch
consideration if one side has already performed
16- 2. Variation
- Vary the contract to turn it into something else
- Consideration required
- NZ Antons Trawling v Smith (2003) variations
dont need consideration unless specific public
policy reasons say so - Formalities would apply where relevant
- 3. Waiver
- Waive one term or a contractual right
- Does not have to comply with statute
- Can waive by conduct
17Discharge by Breach
18- Breach does not terminate a contract
- May allow one party (wronged party) to bring
contract to an end - We know about warranties breach only entitle to
damages
19When is something a warranty?
- Where law says so
- Where parties say so
- Some law in relating to certain types of terms /
provisions
20- So, can end a contract where it has been breached
where the breach is a condition - You can also end a contract where either
- Fundamental breach occurs
- Breach of the fundamental term if breach is
fundamental (basically Hong Kong Firs) - E.g. Dundalk Shopping Centre v Roof Spray
- D treated roof of Ps premises so badly it leaked
- Such a breach, P could treat K at an end (ct
noted likelihood of recurrence here)
21Revision
- Discharge by Breach
- I.e. certain breaches allow one side to treat
contract as at end thus discharging their
obligations - E.g. hirer of ship has 5 years of payments to
make, but the ship after 1 year proves to be of
terrible quality. He may want to treat the
contract as ended (discharged) and thus not be
bound to pay the rest (subject to his right to
recover in damages)
22Three ways
- Breach of condition (where we know its a
condition) - Breach of fundamental term
- Fundamental breach
23Now one more way
- Repudiatory breach
- Where the other party has decided not to perform
its obligations under the contract. - Where one party has made a clear decision not to
perform its obligations, it cannot be fair to
expect the other party to perform its
obligations. In these circumstances, therefore,
the innocent party can treat the contract as
having come to an end.
24Athlone RDC v Campbell Son
- P carrying out excavation of a well dispute
arose, but P said they would carry on - D said he didnt want that
- P said this was a breach of K (i.e. the D has no
intention of paying us) - P could rely on this anticipatory repudiation of
the contract to bring it to an end - Practical consequence could sue for damages
without having to perform the contract itself!
25Two rules for Repud Breach to Occur
- 1. Rep Breach Must be Serious
- Decro Wall International v Practitioners in
Marketing - Consistent and deliberate late payment no
sufficiently serious when delay was ultimately
minor - 2. Breach must be deliberate
- Nottingham BS v Eurodynamics
- Refused to pay disputed invoices not a breach
since dispute was bona fide - Woodar Investment v Wimpey Construction
- Where one party believes in good faith that they
are abiding by contract, but, in fact, breaching
or announcing intention to breach it, no repud
breach will be made out. - Continental Oil v Moynihan same principle as
Woodar
26- Anticipating a Repudiation
- Situation A
- The breach actually occurs
- Situation B
- John tells Mick he has no intention of paying him
when Mick finishes the work he is doing Mick
therefore anticipates the breach can repudiate
the contract on that basis and sue for Damages
27But he doesnt have to
- If you anticipate a breach by the other side
i.e. they declare intention to breach you can
accept the declared intention, bring contract to
an end, and sue for damages - Or you can ignore it, and wait and see
- But you dont have to wait and see
28Hochester v De La Tour
- P hired as courier in April, was to start in June
- May D said he would not be required in June
- P sued, D said no breach had yet taken place
- Ct held was UnR to expect P to wait and see if
the intention would actually be carried out
could accept the breach as happening at the time
it was expressed
29Leeson v North British Oil
- D contracted to supply parafin oil to P
- Indicated could not do it because of a strike
- P sued
- Ct held he was entitled to sue i.e. intention
of breach had been communicated and he could then
treat the breach as complete
30Discharge by Frustration
31- Frustration is about acts that occur after
contract has been formed. This is crucial. - If it operates, it operates such that contract
ceases to have effect from date of frustration
onwardsno past effect - Teaching method do the cases, but study it in a
thematic manner
32Introduction - Definition
- External factors which so radically alter the
basic assumptions on which a contract is founded
such that its performance is impossible of futile
Friel (1995) - Also a good definition in Neville v Guardian Bros
and in Zuphen case (to follow)
33Old View
- Common law once very opposed
- Paradine v Jane (1647)
- Tenants occupation interrupted by lands
requisitioned by army during English Civil War - Still liable to pay his rent court said tenant
should have attempted to guard against this in
his lease laissez faire
34Gamble v Accident Assurance
- Insurance policy said insured need notify
insurance company of accident in 7 days - Died by drowning no notification
- Company did not have to pay said he should have
made arrangements in the policy to cover such
situations. - Not a Fr case but about laissez faire attitude
underlying hostility to frustration
35Taylor v Caldwell
- Shift begins music hall burns down shortly
before P to take lease - P sued for breach of K
- Failed held K subject to implied term that K
would be discharged if it became impossible to
perform. - Implied term theory is not really the basis of it
now. (but bear this in mind for recent Irish
Zuphen case)
36- Modern Case Law
- Thematic is Best (Suits Problem Questions)
37What Constitutes Frustration?
- Neville significantly changing the nature of
the outstanding contractual rights and
obligations from what the parties could
reasonably have contemplated at the time of the
contract's execution that it would be unjust to
hold them to its stipulations in the new
circumstances - Zuphen when something occurs after the
formation of the contract which renders it
impossible to fulfil the contract or transforms
the obligation to perform into a radically
different obligation from that undertaken at the
moment of entry into the contract.
38- General reluctance to apply liberally McGuill v
Aer Lingus (1983) saw McWilliam J talk about
strictly scrutinising claims of frustration
39- Advice Fr not made out simply where unforseen
consequences arise making contract less (or not)
profitable - Tsakirooglou Co v Noble and Thorl
- Suez canal closed made it impossible to ship
cargo at original costs needed now go around
the Cape of Good Hope - Not Fr extra costs was not enough would have
needed to show that the Canal closure meant
something very special for cargo i.e. it was
perishable etc.
40Davis Contractors v Foreham UDC
- Building Contract for 8 months 94K
- Took 2 years and costs 114K
- Labour probs and materials shortages were the
cause - HL held no frustration all that occurred were
that ordinary commercial risks materialised.
41Congimex v Tradax
- Goods to be shipped to country which stopped
issuing import licences - Donaldson MR no frustration
- Frustrated expectations and intentions of one
party to a contract do not necessarily or indeed
often lead to the frustration of that contract - (that case was about how certain goods could not
be purchased in Portugal without certain licences
those licences then stopped being issued so
purchase at Lisbon was not possible.)
42- What happens where contract can still be
performed, but reason for it has been lost? - Frustration of purpose?
- Krell v Henry
- R rented a flat to watch coronation procession of
Edward VII was cancelled - Could still rent the flat, but reason for it was
gone - Vaughan Williams LJ CA held that court had to
look at substance of what contract was for i.e.
to view the procession once that was gone, so
was the substance of the contract frustrated as
it could not be achieved
43Herne Bay Steam Boat v Hutton
- Chartered boat to watch naval review and sail
around it review cancelled, fleet remained - Held that the K was not simply to watch the
review, but to sail around the fleet hence not
Fr
44- Changes in the law may make a transaction illegal
- Reilly v R
- Said to be an elementary proposition that this
Frs a contract - Also applies where foreign law changes
- Rally Bros v Compania Naviera Soto Y Anzar
- Based on implied term theory term implied into
K that the thing to be done in other country is
not a violation of the law
45One major Rule
- Must be substantial and entire F not simply a
set back - National Carriers v Palapina
- Lease of 10 years for warehouse
- Street giving access closed for 2 years
- Not sufficiently substantial in terms of K to be
a Fr event - Similar holding in Congimex
- the fact that some minor aspect of performance
became impossible did not necessarily frustrate
the contract
46Whether Fr Events Are Foreseen by Parties?
- Has been said (see para 8-34) that if parties
foresee Fr event, it cannot operate see McGuill
v Aer Lingus per McWilliam J must be an
unexpected event - Claimed in that case that strike of employees was
a Fr event rejected because Ct held that the D
were aware of the possibility of a strike - Logic? What do you think?
47Just a note McWilliam J
- If one party anticipated or should have
anticipated the possibility of the event which is
alleged to cause the frustration and did not
incorporated a clause in the contract to deal
with it, he should not be permitted to rely on
the happening of the event as causing
frustration.
48- Zuphen v Kelly Technical Services
- P recruited by agency to work on a contract with
Eircom that was discontinued - Agency claims Ks with workers now frustrated
- Murphy J rejected held could have made their
contracts conditional on the contract, but they
didnt - Needed such a change in the significance of the
obligation that the thing undertaken would, if
performed, be a different thing than that
contracted for - Also note that D had continued to try and get
work for P so contract still capable of being
performed? - Note also
- The general agreement of the Defendant companies
with Eircom as to work being "allocated as the
need arises" points to the possibility of such
work not arising. It was certainly not so
unexpected as to be beyond the contemplation of
the parties, even as a possibility.
49But
- The Eugenia
- Risk that Suez was to be closed was obvious to
all parties actually discussed it here - When it was closed, Court still held that it
could frustrate in this case - Denning MR para 8-36 held it simply not the
case that the event must be unforeseen
50Better viewed as question of degree?
- The more foreseeable it is, the less likely a
claim in Fr will be - Neville and Sons v Guardian Builders - complex
51- SUPREME COURT Principles of Frustration
- Frustration of a contract takes place when a
supervening event occurs without the default of
either party and for which the contract makes no
sufficient provision. - This event must so significantly change the
nature of the outstanding contractual rights and
obligations from what the parties could
reasonably have contemplated at the time of the
contract's execution that it would be unjust to
hold them to its stipulations in the new
circumstances. - In such a case the law declares that both parties
be discharged from further performance of the
contract. The court has the power to declare the
contract at an end.
52- While various theories have been expressed to
justify the doctrine of frustration, it was now
part of the law of contract and like all
judicially evolved doctrines it should be
flexible and capable of new application.
53Neville - Facts
- Developers (D) own plot of land. To develop it
need access over plot owned by County Council. - Negotiations for transfer stumbled on certain
points (CC wanted D not to alter a particular
exit from a hotel car park) (compensation issues
also arose) - Thus it made Ds task in arranging access a bit
more difficult
54- It was clear that had the defendant completed its
agreements with the county council for the
acquisition of the strip of land it would have
been in a position to construct the access road
and therefore comply with its obligation to give
the plaintiff access to the development. - The only unexpected problem for the defendant was
that the county council insisted that the
position of the exit from the hotel car park
should not be altered. - This could not be termed a supervening event
which significantly changed the nature of the
defendant's obligation under the licence
agreement. - While it made the performance of the contract
more onerous, it was impossible to say that
performance had been frustrated.
55If Contract Deals with the Fr Event?
- So, how can you say its frustrating then?
- Brown v Mulligan Kenny J
- If its dealt with in the K cannot claim Fr if
it happens! - Claimed that contract with Dr was frustrated by
insufficient funds K itself said could give 3
months notice in such circsso no Fr
56But
- Jackson v Union Marine Insurance (1874)
- Ship to proceed with all possible speed from
Liverpool to Newport to pick up cargo to go to
San Franciso - K of carriage was to proceed with all possible
disptach dangers and accidents of navigation
excepted - Ship ran aground, docked for 6 months
- Argument was that delay was contemplated by the
contact - Question put to JURY simply whether delay was
so long as to put an end to the commercial sense
in the contract - Decision suggests that even if contract deals
with frustrating event, if that event changes the
nature of the contract, it can still frustrate.
57Metropolitan Water Board v Dick Kerr Co
- Reservoir to be built in 6 years subject to
extension of time for (see para 8-42) - WW1 occurs two years into it, they are told to
cease by Ministerial Order - Q was whether the clause operated
- Ct held was frustrated
- Interruption vitally and fundamentally changed
the conditions of the contract
58Self Induced Frustration
- Cannot rely on it
- Constantine Line v Imperial Smelting
- Neg of shipowners lead to ship sinking they
could not claim Fr, but the other party could - Herman v SS Vicia
- P were crew on ship going between US and England
owners did not have proper permits for them
pleaded it Fr the contract of employment - Their default, they could not plead it
59Per Murphy J in Zuphen - FAULT
- Notwithstanding the uncertainty as to its
theoretical basis, the doctrine itself is
straightforward. A contract may be discharged on
the grounds of frustration when something occurs
after the formation of the contract which renders
it impossible to fulfil the contract or
transforms the obligation to perform into a
radically different obligation from that
undertaken at the moment of entry into the
contract. The doctrine is subject to the
limitation that the frustrating circumstances
must arise without fault of either party
(Maritime National Fish Limited -v- Ocean
Trawlers 1935 AC 5 24 and Constantine Lion -v-
Imperial Smelting Corporation 1941 2 All ER
165.
60Effect of Frustration
- All past obs remain intact
- Frustration operates from event
- Means loss falls where lies on date of
Frustration - Krell v Henry
- Paid 25 upfront, with 50 on the day
- Could not get back the 25, but didnt have to pay
the 50
61Can be unfair
- If contract is entire its frustrated, no need
to pay even if goods handed over etc. - Appelby v Myers (1867)
- K to install and maintain machines total sum
agreed - Fire destroyed premises and machines
- P sought payment for machines and installing
- Could not ob to pay kicked in at future date
(when all obs had been performed)
62Restitution May have a Role
- If you could say that the consideration has
totally failed, you seek restitution for monies
paid out on foot of it (i.e. you gave over
monies, and got nothing you gave over goods,
and got nothing)
63Fibrosa v Fairbain Lawson Combe Barbour
- K to sell and deliver machines to Poland 4800,
with 1600 payable in advance - War fr
- Polish Co seeks the money it paid in advance back
refused said had carried out work in prepping
the machines - HL held P had obtained no tangible benefit under
the K even though D had spent money prepping the
machine P could get back