Title: FORMULATION
1 LECTURE 3
- FORMULATION PRESENTATION OF EOT CLAIMS
2CONTENT FOR FORMULATION PRESENTATION OF EOT
CLAIMS
- Practical completion
- Extension of Time L. D.
- Presentation of Extension of Time claim
- Delay within float time by Architect, but later
delay by the contractor - Delay not on the critical path
- Concurrent delay by both parties
- Concurrent delay followed by subsequent delay
- Delays after the Contract Completion Date
- Prevention, presentation assessment
- Summary on Extension of Time claims
- Recovery of loss and / or Expenses and / or
Damages
3DATE FOR / OF COMPLETION
Date for (Practical) Completion
- Specified completion date agreed at tender time
- Set at the outset of the contract
- The date calculated from the date of possession
including, if any, EOT granted
Date of (Practical) Completion
The actual date that the contractor completes
his work
4 IMPLICATION OF P.C.
- Relieve contractor from (further) L.D.
- Employer is entitled to take possession of the
site. - Employer to take out insurance
- D.L.P. commences
- Release half retention
- End of regular interim certificate
- Measurement period commences
- Arbitration can be opened
5 EXTENSION OF TIME
Delay not by fault nor responsibility
of the contractor
Extension of time
Relieve contractor from paying L.D.
to the Employer
6 EXTENSION OF TIME
Delay by Employer
No
Relevant clause in Contract for EOT
Architect cannot grant EOT
Yes
Time at large, i.e. complete within a reasonable
time
Architect grants EOT
7 TIME AT LARGE
??? Reasonable time ???
Reasonable time is equated to the amount of delay
Failure to complete within a reasonable time
Unliquidated Damages (U.D. not L.D.)
8 What is Liquidated Damage ?
- It is a kind of contractual provision in which a
specified sum of money is to be paid by one party
to the other, or the forfeiture of goods or other
property by that party to the other in event of
particular specified breaches of the contract
committed by the former party.
9 L.D. PENALTY
- L. D.
- Genuine pre-estimate of the loss
- Penalty
- Extravagant compared with the greatest possible
amount of loss - It does not matter whether the term used is L.D.
/ penalty - Non completion certificate needs to be issued
before deducting L.D.
10COULD THE EMPLOYER DEDUCT L.D. IF HE HAS NOT
SUFFERED ANY LOSS?
- As far as the L. D. amount is a genuine
pre-estimate of the possible loss, the L.D. is
enforceable. - They are recoverable whether or not the employer
can prove that he has in fact suffered loss or
even if, in the event, there is no loss at
all.case Clydebank Engineering Vs Castende.
11ARCHITECT ASSESSES EOT AT HIS BEST KNOWLEDGE
- If the contractor did not give notice of claim
or did not furnish full particulars of the EOT
claim, the Architect / Engineer must do his best
to estimate the EOT that can be granted to the
contractor. - Case Merton v. Leach
- However, the contractor cannot complain if the
EOT granted, based on the inadequate information
the Architect has, is not up to his desired
period.
12CAN THE ARCHITECT USE THE CONTRACTOR'S FLOAT TIME
?
- The float in the Contractor's program is for the
benefit of the contractor - Delay on the part of the Employer which reduces
that float may have to be taken into
consideration when considering the time required
for completion - However, if the subsequent delays are outside the
float of the non-critical activities, EOT is
entitled eventhough the delay event is a
non-qualifying event provided that sufficient
float is used up by a qualifying event before
13DELAY NOT ON CRITICAL PATH
- If delay occurs to activity not on the critical
path and the total delay to the activity does not
make it critical, then no extension of time will
be granted as there is no effect to the
completion date
Activity on non-critical path
No EOT for delay within this time limit
14CONCURRENT DELAYS
Delay by the Contractor
Delay by the Architect / within the control of
the Employer
- The contractor may not recover the loss
expense for the period delay by the Architect if
he has some contribution in the delay
15CONCURRENT DELAY - CRITICAL NON-CRITICAL
D1
D2
D1 D2 are concurrent, i.e. at the same time
- If D1 is a qualifying delay/ relevant event, D2
is not ?EOT can be granted. - If D2 is a qualifying delay / relevant event, D1
is not ?no EOT can be granted.
16CONCURRENT DELAY FOLLOWED BY SUBSEQUENT DELAY
- If the subsequent delays are still within the
float of the non-critical activities, then no EOT
would be entitled - If the subsequent delays are outside the float of
the non-critical activities, EOT is entitled
eventhough the delay event is a non-qualifying
event provided that sufficient float is used up
by a qualifying event
17 CULPABLE DELAY
A contractor is late and liquidated
damages are incurred
Client issues variations which will further
delay the completion date (culpable delay)
Time is set at large
Client's rights to deduct L.D. are forfeited
18DELAY AFTER THE CONTRACT COMPLETION DATE
- If extension of time has not been made for
previous qualifying delays, Architect has no
power to extend the time for completion for a new
qualifying event occur after 'any extended time
previously fixed ' - Therefore, EOT must be granted for all known
delays before the existing completion date has
passed, otherwise time will be at large and L. D.
cannot be enforced.
19Revised completion date
Unknown gas ?A.I.?reroute
Delay by Main Contractor (excavation for final
connections to the foul drainage)
EOT for only A.I. Works if it is on the critical
path
20Revised completion date
Architect instructs to cease work add manholes
Delay by Main Contractor (excavation for final
connections to the foul drainage)
Delay due to additional manholes
EOT for total delay as Architect should have
issued the instructions
21EOT AFTER DATE FOR COMPLETION
- Most contracts do not contain the essential
machinery to enable the employer to deduct L. D.
for the period when the contractor is in culpable
delay - The contractor's liability for L. D. may
evaporate if employer causes delay after the
extended completion date. However, the employer
has to prove Unliquidated Damages for deduction.
22DAMAGES
Substantial Damages
Actual loss / damage
Nominal Damages
No loss / damage at all
Exemplary (Punitive, vindictive) Damages
Not in contract, in tort only
General Damages
1. For loss presumed w/o proof 2. Loss incapable
of precise estimation, e.g. pain
Special Damages
1. For loss need to be proved 2. Out of pocket
expenses or earning loss
Liquidated Damages
Genuine pre-estimate of loss fixed by contracting
parties
Unliquidated Damages
Amount fixed by court
23 PREDOMINANT CAUSE OF DELAY
Ignored
Inclement weather
CONSTRUCTION PERIOD
Industrial relations problem
Works is stopped
FIRST OCCURING (PREDOMINANT) CAUSE
24 CONDITIONS PRECEDENT
Depends on the conditions (and special /
supplementary conditions, if applicable) of
contract, the following conditions are precedent
to granting EOT
- Notice
- Mitigate the delay
- Details must be given as soon as possible
- Within the time limit specified, if any.
- (time barred)
- The costs and expenses must not be
- duplicated in a variation.
25 PREVENTIVE MEASURES OF DELAY
- Improve and adhere to quality assurance programs
- Review the contract carefully
- Review the program of works carefully
- Establish an early warning system including
diaries, reports and concise filing systems - Be prompt in the request for variation orders
- Act quickly do not ignore the problem
- Recognise the responsibility in the project team,
work with the other professional members and
consultants. - Identify the dates when the work associated with
potential variations started and finished.
26PRESENTATION OF EOT INCLUDES
- Supporting records particulars
- activities status
- dates
- events
- Narrative of the events
- Effects on progress
- No. of days requested to be granted for extension
- Cause of delay
- Contractual ground
- Delay commencement
- Delay period
- Notice of delay
- effects of the delay
- estimated delay
- Program before delay
- Program after delay
27EOT CLAIMS ASSESSMENT
- Delay due to weather must be considered in
relation to the work being carried out by the
contractor at the time of the delay and not by
referencing to the work which could or should
have been happening in accordance with the
Contractor's program of operations. - If it is not possible to avoid delay due to the
fact that neither party had realised sufficiently
in advance that the information was necessary,
the contractor is not entitled to an extension of
time. - Architect has no obligation to provide
information to enable the contractor to move
faster than envisaged.
28SUMMARY ON EOT CLAIMS
- Keep accurate up to the minute records
- Accept a fair settlement, mitigate losses at all
times if appropriate - Maintain an as built construction program
- Keep accurate site progress sheets
- Keep notes of discussions held, contractors or
COW reports - Keep a record of weather conditions
- Record the current workforce and equipment levels
- Identify the status of documented progress to
which the variation or daywork items should
relate - Regular progress photographs also provide good
records especially when the date and time is
recorded on the plate.
29 EOT AND COSTS
Granting EOT does not automatically allow
contractor for loss and expense, etc.
Loss expenses claims will be dealt with in
Lecture 4