FORMULATION - PowerPoint PPT Presentation

About This Presentation
Title:

FORMULATION

Description:

Title: claims03 Author: cheng chi wah Last modified by: cheng chi wah Created Date: 3/25/2000 1:01:50 AM Document presentation format: – PowerPoint PPT presentation

Number of Views:92
Avg rating:3.0/5.0
Slides: 30
Provided by: cheng156
Category:

less

Transcript and Presenter's Notes

Title: FORMULATION


1
LECTURE 3
  • FORMULATION PRESENTATION OF EOT CLAIMS

2
CONTENT FOR FORMULATION PRESENTATION OF EOT
CLAIMS
  • Practical completion
  • Extension of Time L. D.
  • Presentation of Extension of Time claim
  • Delay within float time by Architect, but later
    delay by the contractor
  • Delay not on the critical path
  • Concurrent delay by both parties
  • Concurrent delay followed by subsequent delay
  • Delays after the Contract Completion Date
  • Prevention, presentation assessment
  • Summary on Extension of Time claims
  • Recovery of loss and / or Expenses and / or
    Damages

3
DATE FOR / OF COMPLETION
Date for (Practical) Completion
  • Specified completion date agreed at tender time
  • Set at the outset of the contract
  • The date calculated from the date of possession
    including, if any, EOT granted

Date of (Practical) Completion
The actual date that the contractor completes
his work
4
IMPLICATION OF P.C.
  • Relieve contractor from (further) L.D.
  • Employer is entitled to take possession of the
    site.
  • Employer to take out insurance
  • D.L.P. commences
  • Release half retention
  • End of regular interim certificate
  • Measurement period commences
  • Arbitration can be opened

5
EXTENSION OF TIME
Delay not by fault nor responsibility
of the contractor
Extension of time
Relieve contractor from paying L.D.
to the Employer
6
EXTENSION OF TIME
Delay by Employer
No
Relevant clause in Contract for EOT
Architect cannot grant EOT
Yes
Time at large, i.e. complete within a reasonable
time
Architect grants EOT
7
TIME AT LARGE
??? Reasonable time ???
Reasonable time is equated to the amount of delay
Failure to complete within a reasonable time
Unliquidated Damages (U.D. not L.D.)
8
What is Liquidated Damage ?
  • It is a kind of contractual provision in which a
    specified sum of money is to be paid by one party
    to the other, or the forfeiture of goods or other
    property by that party to the other in event of
    particular specified breaches of the contract
    committed by the former party.

9
L.D. PENALTY
  • L. D.
  • Genuine pre-estimate of the loss
  • Penalty
  • Extravagant compared with the greatest possible
    amount of loss
  • It does not matter whether the term used is L.D.
    / penalty
  • Non completion certificate needs to be issued
    before deducting L.D.

10
COULD THE EMPLOYER DEDUCT L.D. IF HE HAS NOT
SUFFERED ANY LOSS?
  • As far as the L. D. amount is a genuine
    pre-estimate of the possible loss, the L.D. is
    enforceable.
  • They are recoverable whether or not the employer
    can prove that he has in fact suffered loss or
    even if, in the event, there is no loss at
    all.case Clydebank Engineering Vs Castende.

11
ARCHITECT ASSESSES EOT AT HIS BEST KNOWLEDGE
  • If the contractor did not give notice of claim
    or did not furnish full particulars of the EOT
    claim, the Architect / Engineer must do his best
    to estimate the EOT that can be granted to the
    contractor.
  • Case Merton v. Leach
  • However, the contractor cannot complain if the
    EOT granted, based on the inadequate information
    the Architect has, is not up to his desired
    period.

12
CAN THE ARCHITECT USE THE CONTRACTOR'S FLOAT TIME
?
  • The float in the Contractor's program is for the
    benefit of the contractor
  • Delay on the part of the Employer which reduces
    that float may have to be taken into
    consideration when considering the time required
    for completion
  • However, if the subsequent delays are outside the
    float of the non-critical activities, EOT is
    entitled eventhough the delay event is a
    non-qualifying event provided that sufficient
    float is used up by a qualifying event before

13
DELAY NOT ON CRITICAL PATH
  • If delay occurs to activity not on the critical
    path and the total delay to the activity does not
    make it critical, then no extension of time will
    be granted as there is no effect to the
    completion date

Activity on non-critical path
No EOT for delay within this time limit
14
CONCURRENT DELAYS
Delay by the Contractor
Delay by the Architect / within the control of
the Employer
  • The contractor may not recover the loss
    expense for the period delay by the Architect if
    he has some contribution in the delay

15
CONCURRENT DELAY - CRITICAL NON-CRITICAL
D1
D2
D1 D2 are concurrent, i.e. at the same time
  • If D1 is a qualifying delay/ relevant event, D2
    is not ?EOT can be granted.
  • If D2 is a qualifying delay / relevant event, D1
    is not ?no EOT can be granted.

16
CONCURRENT DELAY FOLLOWED BY SUBSEQUENT DELAY
  • If the subsequent delays are still within the
    float of the non-critical activities, then no EOT
    would be entitled
  • If the subsequent delays are outside the float of
    the non-critical activities, EOT is entitled
    eventhough the delay event is a non-qualifying
    event provided that sufficient float is used up
    by a qualifying event

17
CULPABLE DELAY
  • IN THEORY

A contractor is late and liquidated
damages are incurred
Client issues variations which will further
delay the completion date (culpable delay)
Time is set at large
Client's rights to deduct L.D. are forfeited
18
DELAY AFTER THE CONTRACT COMPLETION DATE
  • If extension of time has not been made for
    previous qualifying delays, Architect has no
    power to extend the time for completion for a new
    qualifying event occur after 'any extended time
    previously fixed '
  • Therefore, EOT must be granted for all known
    delays before the existing completion date has
    passed, otherwise time will be at large and L. D.
    cannot be enforced.

19
Revised completion date
Unknown gas ?A.I.?reroute
Delay by Main Contractor (excavation for final
connections to the foul drainage)
EOT for only A.I. Works if it is on the critical
path
20
Revised completion date
Architect instructs to cease work add manholes
Delay by Main Contractor (excavation for final
connections to the foul drainage)
Delay due to additional manholes
EOT for total delay as Architect should have
issued the instructions
21
EOT AFTER DATE FOR COMPLETION
  • Most contracts do not contain the essential
    machinery to enable the employer to deduct L. D.
    for the period when the contractor is in culpable
    delay
  • The contractor's liability for L. D. may
    evaporate if employer causes delay after the
    extended completion date. However, the employer
    has to prove Unliquidated Damages for deduction.

22
DAMAGES
Substantial Damages
Actual loss / damage
Nominal Damages
No loss / damage at all
Exemplary (Punitive, vindictive) Damages
Not in contract, in tort only
General Damages
1. For loss presumed w/o proof 2. Loss incapable
of precise estimation, e.g. pain
Special Damages
1. For loss need to be proved 2. Out of pocket
expenses or earning loss
Liquidated Damages
Genuine pre-estimate of loss fixed by contracting
parties
Unliquidated Damages
Amount fixed by court
23
PREDOMINANT CAUSE OF DELAY
Ignored
Inclement weather
CONSTRUCTION PERIOD
Industrial relations problem
Works is stopped
FIRST OCCURING (PREDOMINANT) CAUSE
24
CONDITIONS PRECEDENT
Depends on the conditions (and special /
supplementary conditions, if applicable) of
contract, the following conditions are precedent
to granting EOT
  • Notice
  • Mitigate the delay
  • Details must be given as soon as possible
  • Within the time limit specified, if any.
  • (time barred)
  • The costs and expenses must not be
  • duplicated in a variation.

25
PREVENTIVE MEASURES OF DELAY
  • Improve and adhere to quality assurance programs
  • Review the contract carefully
  • Review the program of works carefully
  • Establish an early warning system including
    diaries, reports and concise filing systems
  • Be prompt in the request for variation orders
  • Act quickly do not ignore the problem
  • Recognise the responsibility in the project team,
    work with the other professional members and
    consultants.
  • Identify the dates when the work associated with
    potential variations started and finished.

26
PRESENTATION OF EOT INCLUDES
  • Supporting records particulars
  • activities status
  • dates
  • events
  • Narrative of the events
  • Effects on progress
  • No. of days requested to be granted for extension
  • Cause of delay
  • Contractual ground
  • Delay commencement
  • Delay period
  • Notice of delay
  • effects of the delay
  • estimated delay
  • Program before delay
  • Program after delay

27
EOT CLAIMS ASSESSMENT
  • Delay due to weather must be considered in
    relation to the work being carried out by the
    contractor at the time of the delay and not by
    referencing to the work which could or should
    have been happening in accordance with the
    Contractor's program of operations.
  • If it is not possible to avoid delay due to the
    fact that neither party had realised sufficiently
    in advance that the information was necessary,
    the contractor is not entitled to an extension of
    time.
  • Architect has no obligation to provide
    information to enable the contractor to move
    faster than envisaged.

28
SUMMARY ON EOT CLAIMS
  • Keep accurate up to the minute records
  • Accept a fair settlement, mitigate losses at all
    times if appropriate
  • Maintain an as built construction program
  • Keep accurate site progress sheets
  • Keep notes of discussions held, contractors or
    COW reports
  • Keep a record of weather conditions
  • Record the current workforce and equipment levels
  • Identify the status of documented progress to
    which the variation or daywork items should
    relate
  • Regular progress photographs also provide good
    records especially when the date and time is
    recorded on the plate.

29
EOT AND COSTS
Granting EOT does not automatically allow
contractor for loss and expense, etc.
Loss expenses claims will be dealt with in
Lecture 4
Write a Comment
User Comments (0)
About PowerShow.com