1Management of supplier partnership
2Scope of workshop
Focus and actual processes of Supplier
management List of selected manufacturers
Presenter Mr. David Sojka
Necessary developments on the actual
process On-line pre-qualification HSE requirements
Supplier management in SRM 5.0 system
2
3Introduction of SHS Supplier Management
Shared Services Supplier Management Team
10000
MOL-Group has more than
active suppliers!
The Supplier Management teams main objective are
to keep the contact with them additionally
managing and evaluate their supply ability, MOL
Group point of view!
The Supplier Management team in MOL Groups
Purchasing department
Ágnes Jenei
MOL NyRt.
Slovnaft
TVK
Zsolt Bársony Klára Pataki (US P)
Piroska Ferkó
David Sojka
We also cooperate and provide services for Gas,
LUB, ISSC
4Procurement Supplier evaluation
Determination of requirements
Invoicing / Payment
Continuous evaluation
Suppliers selection - prequalification
Procurement
Tendering
Goods receipt / Service acceptance
PO processing
5Supplier management processes
Maintenance of ERP Suppliers database 3
different ERPs within MOL Group SAP, Oracle and
BPCS
Supplier evaluation and classification
- Prequalification process (new supplier) common
process and common prequalification questionnaire - Continuous evaluation (contracted supplier)
common criteria but different methodology and
different IT tools - Classification common grades (A, B, C, D) based
on evaluation score
Consequential processes
- Rationalization of supplier master database in
ERPs common process - On site audit at supplier common process
- Suppliers Block List common process and list
- List of Selected Manufacturers in progress to
be common process - Create the possibility to meet our suppliers in
scope of the yearly Supplier forums - KPIs and Reporting shall be implemented and
developed to common process
6Potential partner or suppliers pre-qualification
- When a supplier pre-qualification?
- New supplier
- 3 years non active supplier
- Unblocking supplier
- Company data or activity update
- Pre-qualification requirements?
- Pre-qualification questionnaire
- Tax office certification
- Custom and finance certification
- Signed questionnaire confirmation
- Technical documentation (catalogue)
- ISO certification, if available
- Data input to database - BMR?
- Registry court data of company
- Contact data of company
- Pre-qualified activities
- Qualification grade (A, B, C, D)
- ISO certification data
- Questionnaire uploading
7Potential partner or suppliers pre-qualification
(Actual process)
YES
Notify supplier
Supplier management
Qgt95?
Qgt55?
NO
Incoming PQ
NO
YES
Is further assessment needed?
Satisfactory
YES
Onsite audit/ First sample/ Piloting
YES
NO
YES
Proposal for New supplier (market research)
Send PQ to new supplier
NO
Purchaser
Upload into database
Load assessment report Into database
Load Assessment report Into database
System- BMR
Prequalification questionnaire
Completed PQ, Prequalification Documents, Certific
ation sheet
BLOCK LIST
ASSESMENT REPORT
Document
8Supply performance evaluation
- When a supplier continuous evaluation
- Every closed order after goods receipt /
service acceptance
- The edge of satisfaction
- C satisfactory supplier corrective actions
must be applied - C supplier within two consecutive quarters
D unsatisfied supplier - D unsatisfied supplier proposal for Blocking
Evaluated supplier is quarterly informed about
its evaluation by scorecard
D
Blocked quarterly Less than 50 points
C
Keep in database just in special
cases, improvements or be blocked Evaluation
Score 50 - 74
A/B
A 90 100 B 75 - 89
9Evaluation scorecard of suppliers performance
evaluation
Price
Customer satisfaction
- Active cooperation
- Flexibility
- E-procurement
- Price
- Payment terms
- Suppliers efficiency
Evaluated by Requestor (Services)
by Purchaser (Material)
Evaluated by Purchaser
Supply ability
Quality
- Meeting deadlines
- Meeting ordered quantity
- Packaging
- Quality performance
- Quality Management System
- HSE system
Evaluated by Requestor (Services)
by Warehouse (Material) by Supplier management
Evaluated by Requestor (Services)
by Purchaser (Material) by Warehouse
10Current cooperation of IT SM tools in MOL Group
Pre-qualification questionnaire
ORACLE database
BMR in MOL Group (Generally used for
Pre-qualification at all affiliates)
SAP database
SEM -gtSN
Supplier
BPCS database
Supplier
Issofice -gtTVK
BMR -gtMOL Rt, MOL LUB, ISSC, MOL Romania
Supplier
11Blocking of suppliers
- Supplier can be blocked
- Based on prequalification questionnaire, if MOL
Group requirements not reached - Based on serious findings during the external
audit, or not fulfillment of requirements for
improvements identified within audit - Based on poor performance of services, breach of
ethical behavior or HSE requirements, repeated
low quality of product, etc. - Company is in liquidation or bankruptcy process
- Blocking period of suppliers can be from 1 year
to forever in serious cases based on Executive
Board decision
11
12List of Selected Manufacturers (LSM)
- Unified Electric equipment, Instrumentation and
Mechanical Equipment (Rotary machines and
Stationary equipment) company standards - LSM implementation to prequalification process
- Just to be a MANUFACTURER, registered on the
List of suppliers and meeting with - production scope in comparison with
manufacturers from the Lists, - technical and metrological parameters of relevant
products in comparison with manufacturers
product from the Lists, - fulfillment of valid legislation requirements and
valid standards for relevant products, - fulfillment of relevant product (special)
requirements - requirements which manufacturers
from List are not able to fulfill, - manufacturers quantity in List from the
unification point of view, - manufacturers quantity in List from the
competition during selection process point of
view.
LSM
To identify the manufacturers for Electric,
Instrumentation and Mechanical machines,
equipment and their spare parts.
Technical specifications (company standards) for
relevant equipment.
List of suppliers
To identify satisfactory suppliers, their contact
and commodity information
Worldwide companies and entities
Potential suppliers base
13Supplier Management
Questions and Comments
13
14Scope of workshop
Focus and actual processes of Supplier
management List of selected manufacturers.
(Vendor list)
Presenter Mr. David Sojka
Necessary developments on the actual
process On-line pre-qualification HSE requirements
Presenter Mr. Zsolt Bársony
Supplier management in SRM 5.0 system
14
15Opportunities of the actual and the on-line
systems
- BMR system
- Advantages
- Controlled supplier registration
- Automatic score calculation in the questionnaire
- Disadvantages
- Multilanguage problem due to
- supplier pre-qualification at activity
classification - Uneasily manual registration
- Missing automatic up-to-date possibility at
- Suppliers main data (i.e. attention, name etc.)
- Supplier can not check the result of their own
- quarterly evaluation
- On-Line pre-qualification
- Advantages
- - Solved multilanguage problem due to
- supplier pre-qualification at activity
classification - Automatic registration, and activity
classification - Supplier can up-to date the company details
- due to an controlled process
- Up to dated supplier master database in ERP
- systems
- - HSE requuirements can be published
- Disadvantages
- - Manually controll required due to registraion
15
16Proposed developments for the optimization
- Required developments on GIP portal
- Connection between BMR and GIP
- Define pre-qualification categories at
registration part of the web page - Made this categories changeable by lead-buyers
- Possibility to send negative feedback to supplier
in case of declined registration - HSE requirement in refinery and its plant
releated activities will be presented. - Plant shutdown releated activities will be
implemented to the pre-qualification
questionnaire. - List of Selected manufacturers process
- Required developments in BMR
- Connection between BMR and GIP
- Automatic upload possibility of exported file
from GIP
16
17On-line pre-qualification process
Passwrod for SUPPLIER
Supplier management
Export the accepted questionnaire from GIP
Import the CSV file into the BMR system
Inform the Lead-buyer
Is the Database increasement required?
YES
Password to supplier
Proposal for New supplier (market research)
Purchaser
NO
Request for On-line pre-qualification
On line pre-qualification with the
same process like to original
Supplier
The pre-qualification controlled via GIP portal
The pre-qualification controlled via GIP portal
BMR system data impoprt interface
System
Prequalification questionnaire
Positive note to Supplier With the user rights
Exported CSV file
Informative note to the Lead-buyer of the
Pre-qualification result
Negative note to Supplier that the
refistration not required
Document
17
18Required developments in the actual system
Proposal for connection between BMR and GIP
Brief logical shame for safe connection
19On-line pre qualification test system
- Supplier registration
- In case of potential
- supplier registration
- Supplier is able to get
- authorization to pre-qualify
- itself on the GIP portal by
- e-mail and providing
- basic company data
20On-line pre qualification test system
- - Controll on registration
- - Due to the pre-qualification
- the relevant partners must
- accept the relevant HSE
- requirements!
- The Suppliers will able to review
- Its pre-qualification and evaluation
- Results.
- There will be the possibility to
- update its company master data.
21Scope of workshop
Focus and actual processes of Supplier
management List of selected manufacturers.
(Vendor list)
Presenter Mr. David Sojka
Necessary developments on the actual
process On-line pre-qualification HSE requirements
Presenter Mr. Zsolt Bársony
Supplier management in SRM 5.0 system
Presenter Ms. Ágnes Jenei / Mr. Zsolt Bársony
21
22The Three Pillars of the Procurement
Transformation
- 1. Reorganization of Group Procurement
(create competent specialists in
strategic sourcing, contracting and transactional
sourcing in all cost categories) - 2. Implementation of an IT solution
(Group Spend Management
System-GSMS that is capable of synthesizing all
necessary purchasing information out of the
different ERP solutions is key to really
integrated purchasing operations) - 3. Professional knowledge, competency and
capability building (ensure realization of
efficiency improvement potential supported by the
new organizational set-up and the proposed IT
solution)
23NON-HC PROCUREMENT organisation
Group Corporate Services
Group Procurement
Local Coordinators
Shared Services
US Procurement
International Procurement
Central-European Procurement
Maintenance Materials Services
Engineering Construction
General Services
Energy
Production Materials
General Materials Communication Services
- Public procurement of investment projects
- RD, Upstream Laboratory services procurement,
surface services (public) procurement - Small projects (COP) procurement, well-site
logistics, oil-gas related services - Field operation related service (public)
procurement
- Electricity
- Natural Gas
- Other utilities
- Biofuels
- Refining Catalyst
- Petchem Catalysts and Technological materials
- Refining Additives
- Petchem Additives Chemicals
- Chemicals and water treatment
- Packaging Laboratory Materials
- General Material I. "White
- General Material II. "Blue
- General Material III. Corporate Communication
materials services - General Material IV. Marketing Communication
materials services
- Russia procurement
- Oman procurement
- Pakistan procurement procurement control
- Kazakhstan procurement procurement control,
Yemen procurement
- Mechanical Services
- Technology Operation Maintenance
- Electrical Services
- Pipes, fittings, pipe bundles, hoses
- Electric materials, protective materials
- Compressors other rotating equipment
- Mechanical materials fittings
- Mechanical equipment
- Architectural work
- EPC / Refining
- EPC / Logistics
- Retail
- Process control instrumentation
- Basic design licence
- Technological work
- Gas business
- Logistics
- HSE Petchem
- HSE Refining Upstream
- Telecomm. Services
- IT / Consulting other services
- IT / Software, licences and maintenance
- IT / Materials assets
- HR services
- Security Services
- Facility Management
- Financial Insurance services
24System-Independent Holistic Business Model - Used
for the SRM Concept
25Projects of the GSMS Program (SAP SRM
implementation)
New Organization structure and category management
I. Phase
III. Phase
MOL
Subsidiaries
Roll out new processes to subsidiaries
Operative strategic processes, service
procurement, contract management
Extending new processes to materials and
implementing new functions
II. Phase
3S non-CH project
GSMS project
3S SAP Standard Solution, Non-CH team
GSMS Group Spend Management Solution
GSMS PROGRAM
26Main Development Areas Group Level instead of
Corporate Level
27Main Development Areas Electronic Channels
instead of Paper
28Main Development Areas Supply Base instead of
Suppliers
29Supplier identification
Register
Registration
Send Questionnaire(s)
Web Survey
Response
Create
SupplierDatabase
Approval
Send Bid Invitation
RFQ/Auction
Send Bid
Change Vendor Data
Self Editing
30Details of Supplier Identification
- Supplier Identification
- Ability to complete Web-based registration
process for new potetnial partners - Customizable registration forms
- Flexible, customizable questionnaires with Web
survey tool from SAP - Category-dependent and category-independent
questionnaires - Supplier prescreening for accepting newly
registered suppliers - Monitoring of supply base changes
- New suppliers created in SAP Enterprise Buyer
(mySAP SRM) (via OPI or manually) - Supplier data change in via SAP supplier
self-services or mySAP SRM - Blocked suppliers
- Supplier Identification closes the loop between
the initial search and qualification and the
operational use of suppliers
31mySAP SRM SAP Supplier Self-Service
- WEB based, hosted application for Suppliers where
the supplier can connect to procurers
purchsasing modul (SRM, MM). - Ensure functions for suppliers to set up
purchasing documents in a close system Together
with procurer. The possibility of overview,
modification and set up purchsasing documents
expanded to both operative and strategical
processes - Purchse Order (PO)
- SA release orders
- Advise Note (ASN)
- Confirmation
- Invoice
- Credit Note
- Invitation to Bid
- Bid
- The connection to SRM ensured by SAP Exchange
Infrastructure (SAP XI) - Supports the suppliers to manage and maintain
its relevant Master data - System user management from Supplier side
- Supplier cataloge
- Supplier master data (IBAN code, SWIFT code, VAT
number etc.)
32Supplier Self-Services advantages
- Easy to use, customizable surface for Suppliers
- User management for suppliers Communication due
purchseing documents (i.e. Purchase Order, Goods
Receipt) - Allerting function, special workplace for open
tasks
33SAP Supplier Self-Service Start-Page
34MOL Group Business expectation Invoicing
Financial transaction requirement
- Purchase Order issue can be covered by only
orders or contracts where the SAP/SRM (partely
from MM system) uniqe ID implemented on the
documents in case purchasement of undertaking,
material, tool and services.
- Therefore those partners dont indicate the above
detailed relevant IDs on their invoices should
calculate that these - invoices will be sent back without processing.
- The received invoices must fit with legally
required forms and contents additionally the
proof of delivery must be attached to - the invoices. The Purchase Orders SAP/SRM/MM
identification number must be implemented on the
invoice!
- The relevant Purchase Order ID shoud be
implemented in the delivery note and each goods
receipt documents also. The - delivered goods must be listed according the item
numbers of the purchase order. Without these
information the not identificable - Invoices (w/o order orcontract ID) the Procurer
is going to handling as a false document and it
will be sent back without - compensation. In this case the agreed peyment
term begins when the missing information
completely corrected.
If a Partner of us accomplish without receipt of
relevant Purchase Order it is doable only its
own RISK!
35Strategial partnership by SRM
Traditional way
by SRM
36Thank you for your attention!