Title: STANDING COMMITTEE ON APPROPRIATIONS
1STANDING COMMITTEE ON APPROPRIATIONS
Briefing by Department of Water Affairs on the
management of the Internal Construction Unit.
- Presentation byZandile Mathe
- Deputy Director General NWRI11 February 2014
1
2CONTENTS
- Purpose
- Background
- Progress
3PURPOSE
Briefing by Department of Water Affairs on the
management of the Internal Construction Unit.
3
4Background
5(No Transcript)
6(No Transcript)
7Overview branch structure
8Construction Management Unit
Construction Management The purpose of the
Construction management is to construct new
water resources infrastructure and rehabilitate
existing infrastructure to meet social water
needs and to facilitate economic growth and
development.
DIRECTORATE PURPOSE
Construction Support Is responsible for the construction of new water resources infrastructure . They also supply administrative, Human Resources, Financial Human Relations support and Safety and Security for the 5 Construction Units
Construction Equipment They manufacture and refurbish mechanical equipment. It also ensures the procurement, operation, maintenance, rebuilding and disposal of construction equipment
9Progress
10Governance
- Construction unit would execute and project
managed the same project. This affected the
segregation of duties between construction
management unit and Infrastructure development
unit. - Construction units were guaranteed internal
construction jobs without competing with the
external service providers. This affected the
total project costs as costs were not benchmarked
with the market.
- The construction unit is now employed as a
contractor by the Infrastructure development unit
and the independent project managers are
appointed from infrastructure development unit. - Construction unit gets requested to submit the
proposal to execute the project before the job
can be awarded to them. The approval to award is
based on price, quality and ability to deliver.
11Governance
- The progress on the projects were not easily
available to Top Management. This is due to the
fact that there were no proper reporting
structure. - There was no proper project methodology in place.
This impacted on projects monitoring as Gantt
charts and project plans were not easily
available.
- The appointed project managers are expected to
report the progress on projects on monthly basis
or as when required. - The project methodology is now enforced. The
project plans and Gantt charts are prepared and
projects progress are monitored on the regular
basis.
12Financial Management
- The budget for new infrastructure, Dam Safety
Rehabilitation Programme (DSRP) and Water
Services resided within the control of the
construction units. This model resulted in the
allocation of budget being done without
consulting financial expects. - The total projects costing were done without
looking at the activities on bill of quantities
as the bill of quantities were not easily
available. This resulted in under/over costing of
the projects.
- The allocation of budget is managed from the
office of the Chief Financial Officer (CFO) and
the budget reside with the infrastructure unit
instead of construction unit. Construction unit
is paid based on the work done. - The projects are now being costed at an activity
level based on the bill of quantities.
13Financial ManagementCont
- The costing unit did not exit within Water
Trading Entity. - The actual project cost were overstated due to
the fact that construction unit was making profit
on the internal projects. - The was no separation between operational
expenditure and capital expenditure.
- The Water Trading Entity is in the process of
appointing quantity surveyors to assist in
project costing. - The internal profit made by construction is
identified and adjustment are made to ensure that
there is compliance with accounting standard. - The internal order system was implemented as a
temporary measure to separate operational
expenditure and capital expenditure
14System
- There was no system in place to cater for the
project costing on the ERP system. The monthly
projects cost are available after 4-6 weeks due
to delays in projects cost allocation. - There was no system of managing the flee that
construction unit has. - There was no proper project management system in
place.
- WTE is in the process upgrading the current ERP
system to include the following modules that will
cater for construction environment - Project system (PS)
- Fleet management (FM)
- Portfolio and Project Management (PPM)
- Plant Maintenance (PM)
- The implementation of the above modules will
ensure that project cost are real time.
15Audit Opinion
- In 2011/12 the construction unit obtained a
disclaimer opinion. The issues raised were as
follows - No policy in place to manage abnormal costs.
- Lack of proper costing system in place.
- Lack of segregation of duties.
- Construction making internal profit.
- Discrepancies on accounting and costing
depreciation. - Inability to separate operating and capital
expenditure.
- In 2012/13 the construction unit was unqualified
with matters of emphasis. The following were put
in place - Abnormal cost policy.
- Internal profit were eliminated.
- The accounting depreciation policy was aligned to
the construction costing policies. - Internal order project was implemented to
account for capital expenditure.
16THANK YOU