Title: Lecture 14 Power Flow
1ECE 476POWER SYSTEM ANALYSIS
- Lecture 14Power Flow
- Professor Tom Overbye
- Department of Electrical andComputer Engineering
2Announcements
- Homework 7 is 6.46, 6.49, 6.52, 11.19, 11.21,
11.27 due date is October 30 - Potential spring courses ECE 431 and ECE 398RES
(Renewable Electric Energy Systems) - If interested you can still sign up for a power
lunch.
3The N-R Power Flow 5-bus Example
Single-line diagram
4The N-R Power Flow 5-bus Example
Table 1. Bus input data
Table 2. Line input data
5The N-R Power Flow 5-bus Example
Table 3. Transformer input data
Table 4. Input data and unknowns
6Time to Close the Hood Let the Computer Do the
Math! (Ybus Shown)
7Ybus Details
8Here are the Initial Bus Mismatches
9And the Initial Power Flow Jacobian
10And the Hand Calculation Details!
11Five Bus Power System Solved
1237 Bus Example Design Case
This is Design Case 2 From Chapter 6
13Good Power System Operation
- Good power system operation requires that there
be no reliability violations for either the
current condition or in the event of
statistically likely contingencies - Reliability requires as a minimum that there be
no transmission line/transformer limit violations
and that bus voltages be within acceptable limits
(perhaps 0.95 to 1.08) - Example contingencies are the loss of any single
device. This is known as n-1 reliability. - North American Electric Reliability Corporation
now has legal authority to enforce reliability
standards (and there are now lots of them). See
http//www.nerc.com for details (click on
Standards)
14Looking at the Impact of Line Outages
Opening one line (Tim69-Hannah69) causes an
overload. This would not be allowed
15Contingency Analysis
Contingencyanalysis providesan automaticway of
lookingat all the statisticallylikely
contingencies. Inthis example thecontingency
set Is all the single line/transformeroutages
16Power Flow And Design
- One common usage of the power flow is to
determine how the system should be modified to
remove contingencies problems or serve new load - In an operational context this requires working
with the existing electric grid - In a planning context additions to the grid can
be considered - In the next example we look at how to remove the
existing contingency violations while serving new
load.
17An Unreliable Solution
Case now has nine separate contingencies with
reliability violations
18A Reliable Solution
Previous case was augmented with the addition of
a 138 kV Transmission Line
19Generation Changes and The Slack Bus
- The power flow is a steady-state analysis tool,
so the assumption is total load plus losses is
always equal to total generation - Generation mismatch is made up at the slack bus
- When doing generation change power flow studies
one always needs to be cognizant of where the
generation is being made up - Common options include system slack, distributed
across multiple generators by participation
factors or by economics
20Generation Change Example 1
Display shows Difference Flows between original
37 bus case, and case with a BLT138 generation
outage note all the power change is picked up
at the slack
21Generation Change Example 2
Display repeats previous case except now the
change in generation is picked up by other
generators using a participation factor approach
22Voltage Regulation Example 37 Buses
Display shows voltage contour of the power
system, demo will show the impact of generator
voltage set point, reactive power limits, and
switched capacitors
23Real-sized Power Flow Cases
- Real power flow studies are usually done with
cases with many thousands of buses - Buses are usually group in to various balancing
authority areas, with each area doing its own
interchange control - Cases also model a variety of different automatic
control devices, such as generator reactive power
limits, load tap changing transformers, phase
shifting transformers, switched capacitors, HVDC
transmission lines, and (potentially) FACTS
devices
24Sparse Matrices and Large Systems
- Since for realistic power systems the model sizes
are quite large, this means the Ybus and Jacobian
matrices are also large. - However, most elements in these matrices are
zero, therefore special techniques, known as
sparse matrix/vector methods, can be used to
store the values and solve the power flow - Without these techniques large systems would be
essentially unsolvable.
25Eastern Interconnect Example
Example, which models the Eastern
Interconnectcontains about 43,000 buses.
26Solution Log for 1200 MW Gen Outage
In this example wesimulated the lossof a 1200
MWgenerator in NorthernIllinois. This caused
a generation imbalancein the associated
balancing authorityarea, which wascorrected by
a redispatch of localgeneration.
27DC Power Flow
- The DC power flow makes the most severe
approximations - completely ignore reactive power, assume all the
voltages are always 1.0 per unit, ignore line
conductance - This makes the power flow a linear set of
equations, which can be solved directly
28Power System Control
- A major problem with power system operation is
the limited capacity of the transmission system - lines/transformers have limits (usually thermal)
- no direct way of controlling flow down a
transmission line (e.g., there are no valves to
close to limit flow) - open transmission system access associated with
industry restructuring is stressing the system in
new ways - We need to indirectly control transmission line
flow by changing the generator outputs
29DC Power Flow Example
30DC Power Flow 5 Bus Example
Notice with the dc power flow all of the voltage
magnitudes are 1 per unit.
31Indirect Transmission Line Control
What we would like to determine is how a change
in generation at bus k affects the power flow on
a line from bus i to bus j.
The assumption is that the change in generation
is absorbed by the slack bus
32Power Flow Simulation - Before
- One way to determine the impact of a generator
change is to compare a before/after power flow. - For example below is a three bus case with an
overload
33Power Flow Simulation - After
Increasing the generation at bus 3 by 95 MW (and
hence decreasing it at bus 1 by a corresponding
amount), results in a 31.3 drop in the MW flow on
the line from bus 1 to 2.
34Analytic Calculation of Sensitivities
- Calculating control sensitivities by repeat power
flow solutions is tedious and would require many
power flow solutions. An alternative approach is
to analytically calculate these values
35Analytic Sensitivities
36Three Bus Sensitivity Example
37Balancing Authority Areas
- An balancing authority area (use to be called
operating areas) has traditionally represented
the portion of the interconnected electric grid
operated by a single utility - Transmission lines that join two areas are known
as tie-lines. - The net power out of an area is the sum of the
flow on its tie-lines. - The flow out of an area is equal to total gen -
total load - total losses tie-flow
38Area Control Error (ACE)
- The area control error (ace) is the difference
between the actual flow out of an area and the
scheduled flow, plus a frequency component - Ideally the ACE should always be zero.
- Because the load is constantly changing, each
utility must constantly change its generation to
chase the ACE.
39Automatic Generation Control
- Most utilities use automatic generation control
(AGC) to automatically change their generation to
keep their ACE close to zero. - Usually the utility control center calculates ACE
based upon tie-line flows then the AGC module
sends control signals out to the generators every
couple seconds.
40Power Transactions
- Power transactions are contracts between
generators and loads to do power transactions. - Contracts can be for any amount of time at any
price for any amount of power. - Scheduled power transactions are implemented by
modifying the value of Psched used in the ACE
calculation
41PTDFs
- Power transfer distribution factors (PTDFs) show
the linear impact of a transfer of power. - PTDFs calculated using the fast decoupled power
flow B matrix
42Nine Bus PTDF Example
Figure shows initial flows for a nine bus power
system
43Nine Bus PTDF Example, cont'd
Figure now shows percentage PTDF flows from A to I
44Nine Bus PTDF Example, cont'd
Figure now shows percentage PTDF flows from G to F
45WE to TVA PTDFs
46Line Outage Distribution Factors (LODFS)
- LODFs are used to approximate the change in the
flow on one line caused by the outage of a second
line - typically they are only used to determine the
change in the MW flow - LODFs are used extensively in real-time
operations - LODFs are state-independent but do dependent on
the assumed network topology
47Flowgates
- The real-time loading of the power grid is
accessed via flowgates - A flowgate flow is the real power flow on one
or more transmission element for either base case
conditions or a single contingency - contingent flows are determined using LODFs
- Flowgates are used as proxies for other types of
limits, such as voltage or stability limits - Flowgates are calculated using a spreadsheet
48NERC Regional Reliability Councils
NERCis theNorthAmericanElectricReliabilityCo
uncil
49NERC Reliability Coordinators