Lecture 14 Power Flow - PowerPoint PPT Presentation

1 / 48
About This Presentation
Title:

Lecture 14 Power Flow

Description:

Potential spring courses: ECE 431 and ECE 398RES (Renewable Electric Energy Systems) ... QL. per. unit. QGmax. per. unit. QGmin. per. unit. 1. Swing. 1.0. 0. 0 ... – PowerPoint PPT presentation

Number of Views:220
Avg rating:3.0/5.0
Slides: 49
Provided by: ecepubli
Category:

less

Transcript and Presenter's Notes

Title: Lecture 14 Power Flow


1
ECE 476POWER SYSTEM ANALYSIS
  • Lecture 14Power Flow
  • Professor Tom Overbye
  • Department of Electrical andComputer Engineering

2
Announcements
  • Homework 7 is 6.46, 6.49, 6.52, 11.19, 11.21,
    11.27 due date is October 30
  • Potential spring courses ECE 431 and ECE 398RES
    (Renewable Electric Energy Systems)
  • If interested you can still sign up for a power
    lunch.

3
The N-R Power Flow 5-bus Example
Single-line diagram
4
The N-R Power Flow 5-bus Example
Table 1. Bus input data
Table 2. Line input data
5
The N-R Power Flow 5-bus Example
Table 3. Transformer input data
Table 4. Input data and unknowns
6
Time to Close the Hood Let the Computer Do the
Math! (Ybus Shown)
7
Ybus Details
8
Here are the Initial Bus Mismatches
9
And the Initial Power Flow Jacobian
10
And the Hand Calculation Details!
11
Five Bus Power System Solved
12
37 Bus Example Design Case
This is Design Case 2 From Chapter 6
13
Good Power System Operation
  • Good power system operation requires that there
    be no reliability violations for either the
    current condition or in the event of
    statistically likely contingencies
  • Reliability requires as a minimum that there be
    no transmission line/transformer limit violations
    and that bus voltages be within acceptable limits
    (perhaps 0.95 to 1.08)
  • Example contingencies are the loss of any single
    device. This is known as n-1 reliability.
  • North American Electric Reliability Corporation
    now has legal authority to enforce reliability
    standards (and there are now lots of them). See
    http//www.nerc.com for details (click on
    Standards)

14
Looking at the Impact of Line Outages
Opening one line (Tim69-Hannah69) causes an
overload. This would not be allowed
15
Contingency Analysis
Contingencyanalysis providesan automaticway of
lookingat all the statisticallylikely
contingencies. Inthis example thecontingency
set Is all the single line/transformeroutages
16
Power Flow And Design
  • One common usage of the power flow is to
    determine how the system should be modified to
    remove contingencies problems or serve new load
  • In an operational context this requires working
    with the existing electric grid
  • In a planning context additions to the grid can
    be considered
  • In the next example we look at how to remove the
    existing contingency violations while serving new
    load.

17
An Unreliable Solution
Case now has nine separate contingencies with
reliability violations
18
A Reliable Solution
Previous case was augmented with the addition of
a 138 kV Transmission Line
19
Generation Changes and The Slack Bus
  • The power flow is a steady-state analysis tool,
    so the assumption is total load plus losses is
    always equal to total generation
  • Generation mismatch is made up at the slack bus
  • When doing generation change power flow studies
    one always needs to be cognizant of where the
    generation is being made up
  • Common options include system slack, distributed
    across multiple generators by participation
    factors or by economics

20
Generation Change Example 1
Display shows Difference Flows between original
37 bus case, and case with a BLT138 generation
outage note all the power change is picked up
at the slack
21
Generation Change Example 2
Display repeats previous case except now the
change in generation is picked up by other
generators using a participation factor approach
22
Voltage Regulation Example 37 Buses
Display shows voltage contour of the power
system, demo will show the impact of generator
voltage set point, reactive power limits, and
switched capacitors
23
Real-sized Power Flow Cases
  • Real power flow studies are usually done with
    cases with many thousands of buses
  • Buses are usually group in to various balancing
    authority areas, with each area doing its own
    interchange control
  • Cases also model a variety of different automatic
    control devices, such as generator reactive power
    limits, load tap changing transformers, phase
    shifting transformers, switched capacitors, HVDC
    transmission lines, and (potentially) FACTS
    devices

24
Sparse Matrices and Large Systems
  • Since for realistic power systems the model sizes
    are quite large, this means the Ybus and Jacobian
    matrices are also large.
  • However, most elements in these matrices are
    zero, therefore special techniques, known as
    sparse matrix/vector methods, can be used to
    store the values and solve the power flow
  • Without these techniques large systems would be
    essentially unsolvable.

25
Eastern Interconnect Example
Example, which models the Eastern
Interconnectcontains about 43,000 buses.
26
Solution Log for 1200 MW Gen Outage
In this example wesimulated the lossof a 1200
MWgenerator in NorthernIllinois. This caused
a generation imbalancein the associated
balancing authorityarea, which wascorrected by
a redispatch of localgeneration.
27
DC Power Flow
  • The DC power flow makes the most severe
    approximations
  • completely ignore reactive power, assume all the
    voltages are always 1.0 per unit, ignore line
    conductance
  • This makes the power flow a linear set of
    equations, which can be solved directly

28
Power System Control
  • A major problem with power system operation is
    the limited capacity of the transmission system
  • lines/transformers have limits (usually thermal)
  • no direct way of controlling flow down a
    transmission line (e.g., there are no valves to
    close to limit flow)
  • open transmission system access associated with
    industry restructuring is stressing the system in
    new ways
  • We need to indirectly control transmission line
    flow by changing the generator outputs

29
DC Power Flow Example
30
DC Power Flow 5 Bus Example
Notice with the dc power flow all of the voltage
magnitudes are 1 per unit.
31
Indirect Transmission Line Control
What we would like to determine is how a change
in generation at bus k affects the power flow on
a line from bus i to bus j.
The assumption is that the change in generation
is absorbed by the slack bus
32
Power Flow Simulation - Before
  • One way to determine the impact of a generator
    change is to compare a before/after power flow.
  • For example below is a three bus case with an
    overload

33
Power Flow Simulation - After
Increasing the generation at bus 3 by 95 MW (and
hence decreasing it at bus 1 by a corresponding
amount), results in a 31.3 drop in the MW flow on
the line from bus 1 to 2.
34
Analytic Calculation of Sensitivities
  • Calculating control sensitivities by repeat power
    flow solutions is tedious and would require many
    power flow solutions. An alternative approach is
    to analytically calculate these values

35
Analytic Sensitivities
36
Three Bus Sensitivity Example
37
Balancing Authority Areas
  • An balancing authority area (use to be called
    operating areas) has traditionally represented
    the portion of the interconnected electric grid
    operated by a single utility
  • Transmission lines that join two areas are known
    as tie-lines.
  • The net power out of an area is the sum of the
    flow on its tie-lines.
  • The flow out of an area is equal to total gen -
    total load - total losses tie-flow

38
Area Control Error (ACE)
  • The area control error (ace) is the difference
    between the actual flow out of an area and the
    scheduled flow, plus a frequency component
  • Ideally the ACE should always be zero.
  • Because the load is constantly changing, each
    utility must constantly change its generation to
    chase the ACE.

39
Automatic Generation Control
  • Most utilities use automatic generation control
    (AGC) to automatically change their generation to
    keep their ACE close to zero.
  • Usually the utility control center calculates ACE
    based upon tie-line flows then the AGC module
    sends control signals out to the generators every
    couple seconds.

40
Power Transactions
  • Power transactions are contracts between
    generators and loads to do power transactions.
  • Contracts can be for any amount of time at any
    price for any amount of power.
  • Scheduled power transactions are implemented by
    modifying the value of Psched used in the ACE
    calculation

41
PTDFs
  • Power transfer distribution factors (PTDFs) show
    the linear impact of a transfer of power.
  • PTDFs calculated using the fast decoupled power
    flow B matrix

42
Nine Bus PTDF Example
Figure shows initial flows for a nine bus power
system
43
Nine Bus PTDF Example, cont'd
Figure now shows percentage PTDF flows from A to I
44
Nine Bus PTDF Example, cont'd
Figure now shows percentage PTDF flows from G to F
45
WE to TVA PTDFs
46
Line Outage Distribution Factors (LODFS)
  • LODFs are used to approximate the change in the
    flow on one line caused by the outage of a second
    line
  • typically they are only used to determine the
    change in the MW flow
  • LODFs are used extensively in real-time
    operations
  • LODFs are state-independent but do dependent on
    the assumed network topology

47
Flowgates
  • The real-time loading of the power grid is
    accessed via flowgates
  • A flowgate flow is the real power flow on one
    or more transmission element for either base case
    conditions or a single contingency
  • contingent flows are determined using LODFs
  • Flowgates are used as proxies for other types of
    limits, such as voltage or stability limits
  • Flowgates are calculated using a spreadsheet

48
NERC Regional Reliability Councils
NERCis theNorthAmericanElectricReliabilityCo
uncil
49
NERC Reliability Coordinators
Write a Comment
User Comments (0)
About PowerShow.com