Week 3 - PowerPoint PPT Presentation

About This Presentation
Title:

Week 3

Description:

Week 3 ... Week 3 – PowerPoint PPT presentation

Number of Views:57
Avg rating:3.0/5.0
Slides: 16
Provided by: wol143
Category:
Tags: detectors | week

less

Transcript and Presenter's Notes

Title: Week 3


1
Week 3
2
Electrical
  • Code
  • 1. all electrical outlets run off a pigtail from
    main line
  • 2. Each Circuit is wired directly into circuit
    panel - no junction boxes
  • 3. Bathrooms must have GFCI either at panel or
    first outlet must be GFCI

3
  • 4. In rooms must have outlet
  • a) on any wall longer than 2
  • b) no more than 6 from any door
  • c) no more than 12 feet apart along wall
  • d) less than 18 off floor

4
  • 5. Kitchen
  • a) Refridgerator on own circuit
  • b) at least two circuits for outlets
  • c) must have outlet on island if more than 6 sq
    ft
  • d) outlets within 6 feet of sink must be GFCI
  • e) all countertops must have a wall outlet

5
  • 6. Must have at least 1 outside outlet - GFCI
  • 7. Dont forget furnace
  • 8. Fire detectors must be hard wired into a
    circuit with lights

6
  • 9. Separate circuits for Clothes Dryer, Electric
    Range, Electric Ovens, Electric Hot Water Heater,
    Gas Range, Electric baseboard heaters
  • 10. Must fill all holes between floors with a
    fire stop caulk
  • Know local code - does all wiring have to be in
    conduits?

7
Plumbing
  • 1. All drain pipes must be vented
  • 2. Sewer pipe must be PVC Schedule 40 or better -
    can use cast iron pipe
  • 3. All sewer pipe joints must be welded
  • 4. Minimum 3 pipe for toilets and main runs

8
  • 5. Minimum 1-1/4 pipe for sink drains
  • 6. 1/2 pipe minimum for water pipes type L
    copper
  • 7. 3/4 copper pipe for baseboard heat

9
  • 8. Gas is piped through Black Iron pipe and
    fittings or rolled copper tube
  • 9. boilers and hot water heaters must have a
    pressure relief valve and piping to floor
  • 10. Rough in plumbing includes setting tubs and
    showers - need to insulate outside walls before
    they are installed

10
Large Projects
  • Estimated differently than other projects
  • Many involve several separate construction
    projects
  • May be large area
  • Roadway
  • Super Walmart
  • Large housing development
  • Have to look at project to do estimate correctly

11
  • May break project into quadrants or sections to
    facilitate scheduling (allows faster completion)
  • Need to estimate each section to get correct
    quantities
  • Wont be the same quantities as if doing 1
    estimate

12
Contingencies
  • What is it?
  • Risk factor
  • Allows contractor to factor in the unknown
  • The less that is known about project higher the
    contingency
  • Design Build has a high contingency at start of
    project
  • decreases as project is built

13
  • Why do you want to minimize it?
  • Part of bid
  • Drives up final price
  • Need a good estimate
  • Contingency never equals zero
  • Always something that is not known
  • Price fluctuation
  • Weather
  • Labor

14
Mobilization
  • How much does a piece of equipment cost
  • Need to include getting it to/from site
  • Need a truck to haul each way
  • Each time equipment is brought on site cost money
  • Want to minimize how
  • What is cost?
  • Truck, driver, setup, inspection
  • May need equipment to set up

15
Unit price bid
  • We have been talking about a lump sum estimate
  • Unit Price estimate gives price per unit to do
    work
  • Multiply units by price to get cost
  • Still need a good estimate to find errors
  • Includes all costs associated with item
  • Mob/Demob, material cost, labor cost
Write a Comment
User Comments (0)
About PowerShow.com