Title: Progress with DDIA30


1
Progress with DDIA-30
  • Mark Rivers
  • Yanbin Wang
  • Clayton Pullins

2
Overview
  • 2005
  • Jun - proposal presented at COMPRES annual
    meeting
  • Oct proposal submitted, eight PIs Wang,
    Lesher, Green, Fei, Shen, Agee, Durham, Manghnani
  • 2006
  • Feb proposal granted
  • Oct - fund arrived to Univ. Chicago
  • 2007
  • Design and drafting
  • Jun design presented at annual meeting with
    PIs feedback
  • Design work continued
  • 2008
  • Apr bids obtained
  • May vendor selection completed
  • Oct/Nov expected delivery

3
(No Transcript)
4
(No Transcript)
5
Bidding summary
6
Rockland Research Module
  • PO placed end of April, 2008
  • 40 deposit at PO, May, 2008
  • 38,898.80
  • 60 balance 10 days after user acceptance Oct,
    2008
  • 58348.20
  • Initial meeting on site, May 12, 2008
  • Week 1-13 machining parts
  • Week 14 2nd visit, inspect guide blocks,
    assembled parts
  • Week 15-21 resolve any assembly conflicts
  • Week 21 3rd visit, test assembly prior to
    shipping
  • Week 23 Uncrate assembly at APS

7
Budget
  • Funds
  • COMPRES 68,000
  • GSECARS 68,000
  • DDIA-30 module cost 97,500
  • Balance of 38,500
  • Design and build differential ram controllers and
    DDIA-30 transport table
  • Modify 1000 ton press module transport table

8
Additional design and modification
  • Design and build
  • Two differential ram pressure controllers
  • Each with 200 cc capacity, 30,000 psi
  • Transport table for DDIA-30 module (500 kg)
  • Electronics and software
  • Modify
  • 1000 ton transport table
  • Replace ball-bearing table top with rails/turn
    table

9
Estimated schedule
  • DDIA-30 Transport table
  • Design done in July
  • Construction complete in Oct
  • 1000 ton press table
  • Design done in July/Aug
  • Construction complete in Nov
  • DDIA-30 module
  • Delivered Oct/Nov
  • Test end of Nov or beginning of Dec, through Jan,
    09
  • System ready for community Feb/Mar 2009