Title: Section 9 Subsystem Status
1Section 9 Subsystem Status
2Attitude Control System
. . . Paul Sanneman ACS Lead
3Changes Since S/C Thermal Vacuum
- ACS Components
- AST removed and X-rayed subsequent
removal/replacement of EMI Filter with additional
clearance between part and PWB (1/00) - Debris found under EMI Filter and removed during
repair - AST removed and opened for addition of stiffener
on the lid of Interpoint DC/DC converter (5/00)
reintegrated in flight orientation (6/00) - Removed IRU to prevent helium exposure during MAP
testing (2/00) re-integrated with upgraded purge
(5/00) - ACE Software
- ACE RSN SW update to A/D conversion
implementation (3/00?) - ACE RSN SW update for IRAM2 checksum protection
and removal of high rate event message (6/00)
4Changes Since S/C Thermal Vacuum (continued)
- ACS Software
- Ephemeris epoch time changes from MET to UT to
improve navigation propagation accuracy (M5 clock
drift) (12/99) - Modified Warm restart logic to ensure consistent
recovery time (3/00) - ACS table parameters updated via STOL procedures
(5/00) - Table 78 X-band Theta angle limit increase from
60 to 65 deg - Table 90 Disable autonomous re-entry into Delta-V
mode - Table 53 Increase pitch attitude FDC count from
30 to 80 sec - Table 87 Adjust solar array FDC limits to avoid
trips during normal slew maneuver operations
5ACS Summary
- Trending data to be collected using same
procedure as T/V I - ACS trends from T/V I available for reference
- IRU PDV has remained stable
- RWA runup/rundown in vacuum to be measured
- Open Problem Reports
- 468-20-4 IRU Parametric Drive Voltage
- Star Tracker temperature trends to be
monitored/controlled closely with thermal
engineering as in T/V I - Thermal limits in database have been reviewed
- Special ACS steps during T/V II have been
coordinated - RWA Overspeed, AST TEC, ACE MTB Pwr Supply, GPS
Ant feeds
6IRU PDV Processed Trend
7IRU PDV Data Trend
8ACS
- Coarse Sun Sensors 1, 2 and 3 remain in
non-flight configuration of the SAD test bracket
until after T/V II test
Attitude Control Subsystem is ready for T/V II
test.
9Attitude Control Determination Subsystem (ACDS)
. . . Philip Luers GSFC ACDS Lead
. . . Steve Schumacher Swales ACDS Lead
10ACDS Readiness
- ACDS hardware is in Final Flight Configuration
- Hardware modification since last T/V test
- Stiffeners added to Interpoint power converters
on ACE I/O and CDH LVPC boards - Ceramic barrels on 1773 bulkhead connectors
replaced with Phosphor-Bronze - Powered vibration (workmanship) performed on 1
axis - Re-integration was nominal
- No Open Problem Reports
11ACDS Plans
- Trending Plans (exactly like last T/V test)
- 4 voltages, 4 currents, 4 temperatures recorded
every 5 minutes, graphed and analyzed for
correlation with temperature - Confirm oscillator drift measurements made during
last T/V test - Correlates spacecraft time adjustments with
temperature - No work required before pump down
- Critical limits in database confirmed
- Procedures have been reviewed
12Power
. . . Allan Billings Power System Lead
13Status of Flight Hardware/Software
- PSE in Final Configuration including Software
- Changes since Thermal Vacuum
- SOFTWARE The new PSE version ( "8.00" ) was
loaded, with the 8 wait states modified A/D
read routine. NO significant increases in the
execution time of the control loop was
observable, i.e, execution time 1.6 msec. - SOFTWARE All PSE RSN Commands verified
- HARDWARE LVPC switched service 9 abandoned due
to damage caused by short during last thermal
vacuum test. Added new thermal wiring and
rerouted. - HARDWARE Fuse plugs added to all PSE LVPC
outputs (non-essential services)
14Status of Flight Hardware/Software
- Battery---In Storage, Ready for Flight
- Solar Array---After Integration of Solar Array to
the Spacecraft, the Solar Array Will Be in Final
Flight Configuration - Changes since last thermal vacuum
- LAPSS Test performed on Array at Goddard at
beginning of this year---Measured string current
agreed with Tecstar values within 4. Open
circuit voltage of strings agreed with Tecstar
values within 100mV. All string V/I curves were
smooth.
15Open Problem Reports
- PR837-20-1 (RFA 33 4/12)
- Anomaly---
- PLVPCLDI2 telemetry went to FF (Maximum value)
with no active spacecraft activity. PLVPCLDI2
reports the total load current magnitude for the
PSE LVPC. FF would correspond to 19.275A. - This anomaly never occurred before and never
happened again. - The anomaly lasted only for one sample. If this
was a valid out of tolerance current indication,
the pulse width lasted less than 533uS since the
anomaly did not trip the LVPC over current
protection circuit. - The spacecraft configuration was set to load the
software into the housekeeping RSN. It is
possible that something in this configuration
contributed to this anomaly (unknown at this
time). This configuration is a ground
configuration and will not be used in flight.
16Open Problem Reports
- Investigations
- Analyzed PSE LVPC timing as a possible source of
the Anomaly. If one assumes worst case timing for
all the individual ICs we still have positive
margin from the time the LVPC places data on the
bus until the RSN reads the data. However the
margin appeared to be less than adequate and the
MAP ETU PSE LVPC was tested to measure actual
(not theoretical) timing margin. The margin
measured on MAP was adequate. - The spacecraft harness was examined by quality
control (EO1-WOA-963) and found to pass visual
inspection. - The FEDS data system was analyzed to determine if
it was the source of the anomaly. The conclusion
was that the telemetry (PLVPCLDI2)reported down
from the spacecraft had FF. This was not a FEDS
problem.
17Open Problem Reports
- Disposition
- A fault tree analysis was performed as a result
of RFA 4/12 and no credible source of the failure
other than the spacecraft configuration was
found. It is speculated that the spacecraft
configuration may have been responsible and this
configuration will not be used in flight. - If a similar (benign) anomaly is generated on
orbit (PLVPCLDI2FF for one sample) a red limit
violation would occur and this would be observed
in ground data. No other spacecraft consequences
would accrue. - We will continue to monitor for this anomaly
throughout all spacecraft testing.
18Trending Plans/Critical Limits/Additional Work
before Pump down
- Trending Plans
- Trending requirements passed on to MOC
- MOC is utilizing a heritage data collection and
trending system from TRACE (DTAS) - Trending procedures are currently being
implemented. Completion expected soon after
Thermal Vacuum Test. - Critical Limits
- Critical Limits have been placed in ASIST work
stations. All other limits undergoing thorough
review. - Additional Work Before Thermal Vacuum
- The test battery will be reconditioned before
Thermal Vacuum
19RF Communications
. . . Bill Jupin / Pete Young / Ken Perko EO-1 RF
Comm Team
20RF Communications
- Entire Subsystem in Final Flight Configuration
- X-Band Hat Coupler repaired
- No Open Problem Reports
- Automatic Trending Script has been updated
- No further work required before Pump Down
- Helping with GPS GSE Configuration and Setup
- Critical limits in the ASIST Database are being
reviewed - Procedures almost identical to TVAC 1
- Only remaining item to verify during TVAC 2
- Must see X-Band Antenna Track and Dump Data to
Various Ground Stations During Orbits. Want to
Witness Entire Process During TVAC (ACS
commanding, Phase Shifters Changing State in
Antenna, RF Activation, etc).
21Wideband Advanced Recorder Processor (WARP)
. . . Terry Smith WARP Lead Engineer
22Status
- Hardware is in its final flight configuration
- Software is in its final flight configuration
- There are no open problem reports
- No work is required before pump down
23Changes Since Last Thermal Vacuum Test
- A voltage reference part failed (open) on the
WARP LVPC on 1/4/00 - The failure produced a high voltage within the
LVPC - Numerous parts were over-stressed
- The entire LVPC piggyback card was replaced
- The WARP successfully completed an extensive
re-qualification program - The WARP was operated over 400 hours prior to
re-integration on the S/C
24Trending Plans
- The following parameters will be monitored each
day - Mode of operation
- Primary input power voltage
- All secondary voltages
- The temperature of the front and back of every
card - RF Exciter Power Output
25Critical Limits Procedures
- The Processor Card Mongoose V Temperature
sometimes reaches the yellow limit during the hot
plateau - The heater mode procedure must be run prior to a
memory card cold start. If the WARP fails to
power up the memory cards, no harm is done.
26Flight Software
. . . Ray Whitley EO-1 Flight Software Systems
Manager
27Flight Software Readiness
- No T/V II Concerns/Liens
- There are no know leans against or issues with
the flight software at this time. (What a
difference 7 months makes!) - Code Walk-throughs have been conducted for the
HSK and X-Band RSNs since TV-I - Code 300 ran code analyzer s/w against most of
EO-1s FSW with very positive results - FSW testbed has been re-located to GSFC from
Swales an ACE ETU fabrication is in progress - Thanks to Tom Feild Emory Stagmer, all TSMs
RTSs are incorporated and tested at the
spacecraft - ESN A/D converter wait state timing issues
understood resolved (compliments of MAP h/w and
s/w engineers). EO-1 fix installed and tested - 1773 Bus Controller s/w hardened against possible
failure mode
28Flight Software Readiness
- No T/V II Concerns/Liens
- There are no open software PTRs that require
software change in any of the flight processors.
EO-1 PTRs generated over the last year have been
analyzed for severity, and the results indicate a
very positive trend toward zero(0) make-play
changes. - PTRs have been cross-checked against the MAP
problem database - There are no open PARs/PRs in the S/C IT
database that require software change in any of
the flight processors
29Flight Software Readiness
- Have Been Ready To Go for Several Months
30Reaction Control System
. . . Mike McCullough RCS Lead Engineer
31Reaction Control System
- Configuration for Test
- Pressurized to 40 PSIG w/ GN2 (Long Term Leak
Check) - Enable Plug Test Set (EPTS) Installed
- Thrusters Valves Will Not Be Actuated
- Components Functions to be Tested
- Thruster Drive Voltage Recorded on Strip Chard
via EPTS - Catalyst Bed Heaters Enabled via EPTS
- Thermal Control Heaters (Primary Redundant)
- Pressure Transducer Temperature Telemetry
- Latch Valve Function (Part of CPT5)
32Reaction Control System
- Additional Testing for T/V II
- RCS Secondary Heaters Will Be Exercised
- Primary Heaters Function Sizing Verified During
T/V I - Secondary Heaters Will Control System 12-18C
- No Open Problem Records
- RCS is ready for Thermal Vacuum testing
33Mechanical
. . . Pete Alea Mechanical Systems Engineer
34Satellite Support Stand
35EO-1 Satellite Test Configuration
Chamber 225
36Chamber Configuration
Chamber 225
Satellite Test Stand
37Test Readiness
- Two open problem records - WOA 1028, Event 50
80 - Insufficient gas flow rate from purge cart to
support both IRU and SI - Purge cart modifications in progress to replace
regulator and flow meter to provide increase flow
rate. MIT/LL has approved required changes - Test fixture and support hardware has been
completed and is ready to support T/V test - Satellite handling procedures ready and WOA is in
place - There are no outstanding mechanical PRs or liens
against the S/C which may delay testing
38Global Positioning System
. . . David Quinn GPS Lead
39Global Positioning System
- Entire Subsystem in Final Flight Configuration
- Stiffener hat added to PCU Interpoint DC/DC
Converter - 1-axis Vibration
- Successfully Reintegrated into S/C
- Ground System Command Interfaces Online
- RF GSE Upgraded from TVAC-1
- Hat Coupler Gaps Reduced
- Noisy RG-142 RF Cables Removed
- Rooftop Antenna Relocated
- Low Noise Belden 9913 Cable Runs - Reduced in
Length Over TVAC-1 - No Open Problem Reports
- Temperature Trends to be Monitored as Part of
TVAC-2 - RF GSE Testing Required Before Pump Down
- Limits Reviewed Prior to TVAC-1 - Valid and
Unchanged. - Procedures Almost Identical to TVAC-1
- More Attention Given to Signal Levels From All
Four Antennas
40TVAC II Setup