Title: Thermal Control System TCS status report
1Thermal Control System (TCS)status report
- Joseph Burger (MIT)
- Christian Vettore, Massimiliano Olivier, Marco
Molina (CGS)
2Topics
- Main radiators
- Crates/xPD/MLI bonding
- Heater architecture design and wiring
- CAB TCS status
- MLI status and next steps
- CRYO TCS status
3CRATES/XPDs bonding issue
- Bonding issue was brought-up at the last TIM.
Taking advantage of having the crates / jigs
installed on the USS, it was agreed that with
the obstructions posed by additional hardware and
cabling, the bonding strap fixation would result
quite difficult. Â Getting access for the tools to
torque the fasteners would be the most difficult
part. - Because of this, the grounding philosophy has
been revisited all over these three months thru a
discussion involving JS/AMS Collaboration people
and CGS.
4AS IT WAS
5(No Transcript)
6BONDING REQUIREMENT CONSOLIDATION
- Bonding class
- Class H (0.1 ohm for powered electronics) / Class
S (1.0 ohm for dumb metal / blankets) are the
only safety requirements imposed by NASA and they
can be easily met with wire. - Class R (RF bonding). Shortest possible (aspect
ratio 5/1), fat braid to earth (chassis, etc) on
each subsystem reducing the probability of a
subsystem acting like an antenna. The DC portion
of the Class R (2.5 mOhm). The RF bonding is a
mission assurance EMI requirement. - Number of bonding (number of straps per crate)
and class type - CRATES/xPDs do not need QTY 2 class R (RF) bonds.
They need to respect safety req. (class H) and a
as close as possible to RF bond for EMI reasons. - For class H it was decided to rely on the
conduction of the alodined links to make the
crate assy one entity electrically . This means
the crate assembly is one large, electrically
conductive structural piece. - For class R dedicated short flat braids were
defined. - RESULT All interior - hard to reach - ground
straps can and have been removed. The external,
reachable straps are the RF straps. - The Class H requirement is met by electrical
conduction provided by links
7(No Transcript)
8Crates/XPD RF bonding strap
- Flat copper braid Nickel plated
- Copper nickel-plated terminals
- Aspect ratio 51
- STRAPS HAVE BEEN ORDERED
9SHV BONDING REQUIREMENTS
- SHV has no links that connect the box to the
other structures. We have ONLY ONE bonding pad on
the SHV. That was aligned with the original
request. - This has been OK, after meeting between Tim Urban
and EMEP representative (16thJune) a single
(one) Class R is OK for these boxes. Or as near
to R as possible. No need for a second bond. - The use of a bonding wire (AWG16-12 with 2
eyelet) meets Class H, which is the absolutely
mandatory safety requirement. Â However, it is
very strongly preferred that a single Class R
bond should be used for EMI reduction.Â
10- PICTURE WITH THE BONDING PAD
11What makes SHV discussion different ?
- The SHV1 (RAM) and SHV0 (WAKE) have been 180deg
rotated wrt. its original position. In turns the
bonding insert should have been moved but this
would have caused a delay in the panel
manufacturing. In order to cope with that it was
decided to replace the bonding strap with a
bonding wire (AWG16-12 with 2 eyelet). - In any case none of the foreseen bonding inserts
on the radiator is used for bonding (neither for
lower not for upper-rotated SHVs). Same issue
previously mentioned about reaching the straps
once the radiator is mounted. - In taking decisions for the bonding it shall be
considered that once the radiator jig is removed
the SHV boxes have to be kept in place someway
12(No Transcript)
13TSPD-main wall left
GP_SHV1
GP1
GP6
14UPD0
TSPD1
GP4
GP_SHV0
SHV-0
15Galvanic corrosion prevention
- Any bond location, even if it does not involve
dissimilar metals (i.e. alodined Al to alodined
Al at links) needs to have Super Koropan applied
along the edge to prevent corrosion in moist
atmosphere on ground. Â The fact that it is an
electrical bond implies some small current, which
creates the same galvanic corrosion cause by
dissimilar metals. Â This must be done for - links (when crates laid out flat)
- exterior straps
- blanket terminals
- The SuperK is applied around the periphery of
the joint - after assembly, and it is not inside
or between layers of the joint.
16Main Radiator heater architecture and wiring
- All the RAM/WAKE Electrical and Thermal H/W to
complete the heater bus installation is in our
hands - RAM Heater connector bracket and Terminal blocks
H/W clamps manufacturing started at CERN. - Paper documentation (i.e. wiring table ,
procedures) are in progress. - Crimping test to qualify the process is on-going
and it will be finished by the arrival of the
main RAM and WAKE radiators
17(No Transcript)
18(No Transcript)
19MAIN RADIATOR INTEGRATION FLOW NOTE
CGS THERMAL HARDWARE INSTALLATION ON PANEL
RAM PANEL INSTALLATION ON GEMINI
RAM PANEL _at_CERN
RAM PANEL STORAGE
CGS THERMAL HARDWARE INSTALLATION ON PANEL
WAKE PANEL _at_CERN
WAKE PANEL STORAGE
CAB LHP INSTALLATION ON WAKE RADIATOR
CAB REINSTALL AND LHP CONNECTION TO CAB
WAKE PANELCAB LHP INSTALLATION ON GEMINI
WAKE PANELCAB LHP STORAGE
CAB REMOVAL
20SCHEDULE
- MAIN RADIATORS (CGS) THERMAL H/W INSTALLATION
not later than October 23th 2008 - AVAILABILITY IN CERN CLEAN ROOM OF MAIN
RADIATORS AND SUITABLE HANDLING JIG NOT LATER
THAN September 23th 2008
21 22CAB TCS parts
23CAB TCS update
- CAB LHP Design consolidation
- Routing finalized (two minor modifications
introduced) - Flexibility test performed
- USS heat pipes design consolidation
- Manufacturing and procurement status
24CAB LHP design update 1\
- The saddle design has been modified and the long
saddles have been replaced by shorter pieces to
meet the required planarity.
25(No Transcript)
26CAB TCS design update 1\
- SAMPLES OF SADDLES HAVE BEEN MANUFACTURED.
TESTING IS IN PROGRESS TO VERIFY FINAL PLANARITY
OF SADDLES WHEN LHP TUBES ARE SOLDERED.
27CAB LHP design update 2\
- The compensation chamber size has been modified
and the current compensation chamber is 12mm
longer.
28CAB LHP design update 2\
Being the external envelope not affected by the
change , the verification of the integration
sequence doesnt need to be repeated
29USS heat pipes
30(No Transcript)
31(No Transcript)
32(No Transcript)
33(No Transcript)
34(No Transcript)
35CAB LHP flexibility
- At the last TIM the CAB LHP system was considered
suitable for manufacturing authorization but a
minimum flexibility was required. A flexibility
of 12deg/-1 is required between the evaporator
and the condenser to allow the CAB LHP/WAKE rad
insertion - Two options
- Add pig-tails to match the requested/needed
flexibility in the plumbing - Make a test of the plumbing w/o pig-tails
36CAB LHP flexibility
37CAB TCS LINES FLEXIBILITY TEST SAMPLE
38CAB TCS LINES FLEXIBILITY TEST RESULTS
NO PLASTIC DEFORMATION FOR ANGLES lt 14deg, MINOR
YELDING UP TO 20 deg
39(No Transcript)
40CAB TCS (LHP excluded) parts procurement and
manufacturing status
- Heaters Ordered.
- Circular connector delivered.
- Circular connector bracket under manufacturing.
- Silver Teflon Tape delivered.
- Thermostats delivered.
- MLI on zenith and nadir faces of the CAB to be
designed and produced. - Choterm for LHP evaporator interface USS
interface CAB heat pipes interface to be
ordered. - CAB /USS heat pipes ordered.
- Glue for the fixation of the heat pipes ton the
USS ordered. - USS heat pipes Clamps under manufacturing.
- Fasteners for thermostats, connectors, heat
pipes , brackets - ordered
41LHP Manufacturing status
- CAB valve assembly complete
- CAB evaporator saddle complete
- CAB transport line bending tools under
- production
42CAB TCS schedule
- CAB LHP Delivery at CERN December 19th 2008
- Other CAB TCS H/W Installation on CAB FM not
later than September 25th 2008
43 44MLI design and manufacturing process
- A discussion took place on Monday this week
between CGS/AMS Coll representative/NASA to
review all the MLI design and installation
process. - The complete MLI production schedule, proposed by
CGS, has been presented - The main conclusions of the meeting have been
- NASA has asked to improve the MLI design approval
process suggesting to have at the beginning of
the design phase concept design sketch to
immediately get an idea how the blanket is
conceived. No details, just hardware sections
with envelope lines and attachment methods. - This conceptual design shall be reviewed in a few
days by NASA and shall be the starting point for
the blanket detail design that shall be anyway at
the end reviewed by NASA and authorized for
production. - Tight blankets shall be avoided. MLI blankets
shall be fluffy. Build bigger blankets. This
under the assumption that the final fine
tailoring of the blankets to fit late hardware
features not foreseen shall be done on-site by
NASA personnel.
45MLI production plan
- After the review of the plan, most blankets CGS
proposed delivery dates and fit-check are
adequate for AMS integration planning considering
also availability of NASA personnel for late
modifications where needed. - For some blankets different dates considering
the general integration flow are needed. They
seem to fit with the supplier MLI manufacturing
capability CGS shall check and confirm asap.
46MLI next steps
- Since last April TIM an MLI integration slot has
been planned for 04-08 August 2008 - (11) blankets manufactured and delivered to CERN
(XPD-crates INTERNAL MLI). - (12) After April fit-check RICH SYS blankets have
been authorized and are under manufacturing - (4) RICH LATERAL MLI - delivery_at_CERN 12/09/08
- (4) LTOF MLI - delivery_at_CERN 12/09/08
- (4) ECAL CORNER ZN MLI - delivery_at_CERN 12/09/08
- (TBD gt20) blankets design in-progress (XPD-crates
EXTERNAL MLI)
47These 12 blankets are under manufacturing
- LTOF MLI fit-check (4 blankets)
- RICH LAT MLI fit-check (4 blankets)
- ECAL CORNER (ZN) MLI fit-check (4 blankets)
48MLI next steps
- A further Integration slot had been planned for
September 08 at CERN for dedicate second
fit-check of support rings blanket with MAGNET
H/W or suitable mock-ups. - CGS is evaluating the possibility of removing
this second fit-check delivering larger blankets
to be tailored in place by NASA to compress
delivery schedule.
49XPD-crates INTERNAL MLI Ram side (6) blankets
Internal blankets
50XPD-crates INTERNAL MLI ram side grounding
51TSPD-main wall left
GP_SHV1
GP1
GP6
52XPD-crates INTERNAL MLI wake side (5) blankets
Internal blankets
53XPD-crates INTERNAL MLI wake side grounding
54XPD-crates IN-EXTERNAL MLI side fixation method
on XPD
Velcro for IF with INTERNAL blanket
Velcro for blanket fixation on the unit
INTERNAL blanket
XPD
cables
radiator
55XPD-crates IN-EXTERNAL MLI side fixation method
on crates
56MLI PLANNING 04/08-08/08 activities
5704/08-08/08 INTEGRATION SEQUENCE for XPD-crates
INTERNAL MLI
- Bonding of MLI attachments (Velcros, Tie mounts)
according to the standard procedure in
QSTD-MPRC-3054-AAE. Positions according bonding
drawings included in the ADP. - After the 24hr of curing time the adhesive is
dry for a careful usage of the MLI attachments. - 2) Integrate the FM MLI blankets according to
paragraph 8 of QSTD-MPRC-3054-AAE and the
assembly sketch in the ADP - Routing of structural bonding leads - fixation by
Kapton tape. - Connect the grounding wires according to
paragraph 8 QSTD-MPRC-3054-AAE. And record the
hardware used to fasten the wire, the torque
wrench calibration data, the torque applied to
the screws - Measure with a calibrated Ohmmeter (attach the
calibration data sheet to this ATS) the total
resistance and record the values in the ADP
section
58Up-coming integration steps Internal/External
MLI
- Jig Horizontal
- 1\ install SHV MLI SHV bond strap (SHV side -
 this is shared with one of the two  MLI grounds)
covered by MLI ATS - 2\ install internal MLI blankets and
corresponding bonding point to crate/xPD side
covered by MLI ATS - 3\Install straps as soon as we can even if they
are the exterior ones - 4\ Install if really needed the internal
straps that might be difficult later - Jig Vertical
- 5\ install external blankets when the radiator
jig is vertical . The MLI bond at the radiator
side (where applicable) remains floating till the
radiator comes. Crates bonds need to be done
later when radiator is in position. Only the
crate side of the bond might be fixed. Fix it! In
any case the blankets shall not prevent crates
from running. - 5\A Another possibility is to install external
blankets while the USS is in the PSS with the
Jigs on. Waiting for the magnet.
5921-24 April 2008 MLI Integration slot
VC Upper Skirt MLI
USR MLI
LSR MLI