Thermal Control System TCS status report - PowerPoint PPT Presentation

1 / 56
About This Presentation
Title:

Thermal Control System TCS status report

Description:

Thermal Control System TCS status report – PowerPoint PPT presentation

Number of Views:103
Avg rating:3.0/5.0
Slides: 57
Provided by: mmol6
Category:

less

Transcript and Presenter's Notes

Title: Thermal Control System TCS status report


1
Thermal Control System (TCS)status report
  • Joseph Burger (MIT)
  • Christian Vettore, Massimiliano Olivier, Marco
    Molina (CGS)

2
Topics
  • Main radiators
  • Crates/xPD/MLI bonding
  • Heater architecture design and wiring
  • CAB TCS status
  • MLI status and next steps
  • CRYO TCS status

3
CRATES/XPDs bonding issue
  • Bonding issue was brought-up at the last TIM.
    Taking advantage of having the crates / jigs
    installed on the USS, it was agreed that with
    the obstructions posed by additional hardware and
    cabling, the bonding strap fixation would result
    quite difficult.  Getting access for the tools to
    torque the fasteners would be the most difficult
    part.
  • Because of this, the grounding philosophy has
    been revisited all over these three months thru a
    discussion involving JS/AMS Collaboration people
    and CGS.

4
AS IT WAS
5
(No Transcript)
6
BONDING REQUIREMENT CONSOLIDATION
  • Bonding class
  • Class H (0.1 ohm for powered electronics) / Class
    S (1.0 ohm for dumb metal / blankets) are the
    only safety requirements imposed by NASA and they
    can be easily met with wire.
  • Class R (RF bonding). Shortest possible (aspect
    ratio 5/1), fat braid to earth (chassis, etc) on
    each subsystem reducing the probability of a
    subsystem acting like an antenna. The DC portion
    of the Class R (2.5 mOhm). The RF bonding is a
    mission assurance EMI requirement.
  • Number of bonding (number of straps per crate)
    and class type
  • CRATES/xPDs do not need QTY 2 class R (RF) bonds.
    They need to respect safety req. (class H) and a
    as close as possible to RF bond for EMI reasons.
  • For class H it was decided to rely on the
    conduction of the alodined links to make the
    crate assy one entity electrically . This means
    the crate assembly is one large, electrically
    conductive structural piece.
  • For class R dedicated short flat braids were
    defined.
  • RESULT All interior - hard to reach - ground
    straps can and have been removed. The external,
    reachable straps are the RF straps.
  • The Class H requirement is met by electrical
    conduction provided by links

7
(No Transcript)
8
Crates/XPD RF bonding strap
  • Flat copper braid Nickel plated
  • Copper nickel-plated terminals
  • Aspect ratio 51
  • STRAPS HAVE BEEN ORDERED

9
SHV BONDING REQUIREMENTS
  • SHV has no links that connect the box to the
    other structures. We have ONLY ONE bonding pad on
    the SHV. That was aligned with the original
    request.
  • This has been OK, after meeting between Tim Urban
    and EMEP representative (16thJune) a single
    (one) Class R is OK for these boxes. Or as near
    to R as possible. No need for a second bond.
  • The use of a bonding wire (AWG16-12 with 2
    eyelet) meets Class H, which is the absolutely
    mandatory safety requirement.  However, it is
    very strongly preferred that a single Class R
    bond should be used for EMI reduction. 

10
  • PICTURE WITH THE BONDING PAD

11
What makes SHV discussion different ?
  • The SHV1 (RAM) and SHV0 (WAKE) have been 180deg
    rotated wrt. its original position. In turns the
    bonding insert should have been moved but this
    would have caused a delay in the panel
    manufacturing. In order to cope with that it was
    decided to replace the bonding strap with a
    bonding wire (AWG16-12 with 2 eyelet).
  • In any case none of the foreseen bonding inserts
    on the radiator is used for bonding (neither for
    lower not for upper-rotated SHVs). Same issue
    previously mentioned about reaching the straps
    once the radiator is mounted.
  • In taking decisions for the bonding it shall be
    considered that once the radiator jig is removed
    the SHV boxes have to be kept in place someway

12
(No Transcript)
13
TSPD-main wall left
GP_SHV1
GP1
GP6
14
UPD0
TSPD1
GP4
GP_SHV0
SHV-0
15
Galvanic corrosion prevention
  • Any bond location, even if it does not involve
    dissimilar metals (i.e. alodined Al to alodined
    Al at links) needs to have Super Koropan applied
    along the edge to prevent corrosion in moist
    atmosphere on ground.  The fact that it is an
    electrical bond implies some small current, which
    creates the same galvanic corrosion cause by
    dissimilar metals.  This must be done for
  • links (when crates laid out flat)
  • exterior straps
  • blanket terminals
  • The SuperK is applied around the periphery of
    the joint - after assembly, and it is not inside
    or between layers of the joint.

16
Main Radiator heater architecture and wiring
  • All the RAM/WAKE Electrical and Thermal H/W to
    complete the heater bus installation is in our
    hands
  • RAM Heater connector bracket and Terminal blocks
    H/W clamps manufacturing started at CERN.
  • Paper documentation (i.e. wiring table ,
    procedures) are in progress.
  • Crimping test to qualify the process is on-going
    and it will be finished by the arrival of the
    main RAM and WAKE radiators

17
(No Transcript)
18
(No Transcript)
19
MAIN RADIATOR INTEGRATION FLOW NOTE
CGS THERMAL HARDWARE INSTALLATION ON PANEL
RAM PANEL INSTALLATION ON GEMINI
RAM PANEL _at_CERN
RAM PANEL STORAGE
CGS THERMAL HARDWARE INSTALLATION ON PANEL
WAKE PANEL _at_CERN
WAKE PANEL STORAGE
CAB LHP INSTALLATION ON WAKE RADIATOR
CAB REINSTALL AND LHP CONNECTION TO CAB
WAKE PANELCAB LHP INSTALLATION ON GEMINI
WAKE PANELCAB LHP STORAGE
CAB REMOVAL
20
SCHEDULE
  • MAIN RADIATORS (CGS) THERMAL H/W INSTALLATION
    not later than October 23th 2008
  • AVAILABILITY IN CERN CLEAN ROOM OF MAIN
    RADIATORS AND SUITABLE HANDLING JIG NOT LATER
    THAN September 23th 2008

21
  • CAB TCS status

22
CAB TCS parts
23
CAB TCS update
  • CAB LHP Design consolidation
  • Routing finalized (two minor modifications
    introduced)
  • Flexibility test performed
  • USS heat pipes design consolidation
  • Manufacturing and procurement status

24
CAB LHP design update 1\
  • The saddle design has been modified and the long
    saddles have been replaced by shorter pieces to
    meet the required planarity.

25
(No Transcript)
26
CAB TCS design update 1\
  • SAMPLES OF SADDLES HAVE BEEN MANUFACTURED.
    TESTING IS IN PROGRESS TO VERIFY FINAL PLANARITY
    OF SADDLES WHEN LHP TUBES ARE SOLDERED.

27
CAB LHP design update 2\
  • The compensation chamber size has been modified
    and the current compensation chamber is 12mm
    longer.

28
CAB LHP design update 2\
Being the external envelope not affected by the
change , the verification of the integration
sequence doesnt need to be repeated
29
USS heat pipes
30
(No Transcript)
31
(No Transcript)
32
(No Transcript)
33
(No Transcript)
34
(No Transcript)
35
CAB LHP flexibility
  • At the last TIM the CAB LHP system was considered
    suitable for manufacturing authorization but a
    minimum flexibility was required. A flexibility
    of 12deg/-1 is required between the evaporator
    and the condenser to allow the CAB LHP/WAKE rad
    insertion
  • Two options
  • Add pig-tails to match the requested/needed
    flexibility in the plumbing
  • Make a test of the plumbing w/o pig-tails

36
CAB LHP flexibility
37
CAB TCS LINES FLEXIBILITY TEST SAMPLE
38
CAB TCS LINES FLEXIBILITY TEST RESULTS
NO PLASTIC DEFORMATION FOR ANGLES lt 14deg, MINOR
YELDING UP TO 20 deg
39
(No Transcript)
40
CAB TCS (LHP excluded) parts procurement and
manufacturing status
  • Heaters Ordered.
  • Circular connector delivered.
  • Circular connector bracket under manufacturing.
  • Silver Teflon Tape delivered.
  • Thermostats delivered.
  • MLI on zenith and nadir faces of the CAB to be
    designed and produced.
  • Choterm for LHP evaporator interface USS
    interface CAB heat pipes interface to be
    ordered.
  • CAB /USS heat pipes ordered.
  • Glue for the fixation of the heat pipes ton the
    USS ordered.
  • USS heat pipes Clamps under manufacturing.
  • Fasteners for thermostats, connectors, heat
    pipes , brackets - ordered

41
LHP Manufacturing status
  • CAB valve assembly complete
  • CAB evaporator saddle complete
  • CAB transport line bending tools under
  • production

42
CAB TCS schedule
  • CAB LHP Delivery at CERN December 19th 2008
  • Other CAB TCS H/W Installation on CAB FM not
    later than September 25th 2008

43
  • MLI status

44
MLI design and manufacturing process
  • A discussion took place on Monday this week
    between CGS/AMS Coll representative/NASA to
    review all the MLI design and installation
    process.
  • The complete MLI production schedule, proposed by
    CGS, has been presented
  • The main conclusions of the meeting have been
  • NASA has asked to improve the MLI design approval
    process suggesting to have at the beginning of
    the design phase concept design sketch to
    immediately get an idea how the blanket is
    conceived. No details, just hardware sections
    with envelope lines and attachment methods.
  • This conceptual design shall be reviewed in a few
    days by NASA and shall be the starting point for
    the blanket detail design that shall be anyway at
    the end reviewed by NASA and authorized for
    production.
  • Tight blankets shall be avoided. MLI blankets
    shall be fluffy. Build bigger blankets. This
    under the assumption that the final fine
    tailoring of the blankets to fit late hardware
    features not foreseen shall be done on-site by
    NASA personnel.

45
MLI production plan
  • After the review of the plan, most blankets CGS
    proposed delivery dates and fit-check are
    adequate for AMS integration planning considering
    also availability of NASA personnel for late
    modifications where needed.
  • For some blankets different dates considering
    the general integration flow are needed. They
    seem to fit with the supplier MLI manufacturing
    capability CGS shall check and confirm asap.

46
MLI next steps
  • Since last April TIM an MLI integration slot has
    been planned for 04-08 August 2008
  • (11) blankets manufactured and delivered to CERN
    (XPD-crates INTERNAL MLI).
  • (12) After April fit-check RICH SYS blankets have
    been authorized and are under manufacturing
  • (4) RICH LATERAL MLI - delivery_at_CERN 12/09/08
  • (4) LTOF MLI - delivery_at_CERN 12/09/08
  • (4) ECAL CORNER ZN MLI - delivery_at_CERN 12/09/08
  • (TBD gt20) blankets design in-progress (XPD-crates
    EXTERNAL MLI)

47
These 12 blankets are under manufacturing
  • LTOF MLI fit-check (4 blankets)
  • RICH LAT MLI fit-check (4 blankets)
  • ECAL CORNER (ZN) MLI fit-check (4 blankets)

48
MLI next steps
  • A further Integration slot had been planned for
    September 08 at CERN for dedicate second
    fit-check of support rings blanket with MAGNET
    H/W or suitable mock-ups.
  • CGS is evaluating the possibility of removing
    this second fit-check delivering larger blankets
    to be tailored in place by NASA to compress
    delivery schedule.

49
XPD-crates INTERNAL MLI Ram side (6) blankets
Internal blankets
50
XPD-crates INTERNAL MLI ram side grounding
51
TSPD-main wall left
GP_SHV1
GP1
GP6
52
XPD-crates INTERNAL MLI wake side (5) blankets
Internal blankets
53
XPD-crates INTERNAL MLI wake side grounding
54
XPD-crates IN-EXTERNAL MLI side fixation method
on XPD
Velcro for IF with INTERNAL blanket
Velcro for blanket fixation on the unit
INTERNAL blanket
XPD
cables
radiator
55
XPD-crates IN-EXTERNAL MLI side fixation method
on crates
56
MLI PLANNING 04/08-08/08 activities
57
04/08-08/08 INTEGRATION SEQUENCE for XPD-crates
INTERNAL MLI
  • Bonding of MLI attachments (Velcros, Tie mounts)
    according to the standard procedure in
    QSTD-MPRC-3054-AAE. Positions according bonding
    drawings included in the ADP.
  • After the 24hr of curing time the adhesive is
    dry for a careful usage of the MLI attachments.
  • 2) Integrate the FM MLI blankets according to
    paragraph 8 of QSTD-MPRC-3054-AAE and the
    assembly sketch in the ADP
  • Routing of structural bonding leads - fixation by
    Kapton tape.
  • Connect the grounding wires according to
    paragraph 8 QSTD-MPRC-3054-AAE. And record the
    hardware used to fasten the wire, the torque
    wrench calibration data, the torque applied to
    the screws
  • Measure with a calibrated Ohmmeter (attach the
    calibration data sheet to this ATS) the total
    resistance and record the values in the ADP
    section

58
Up-coming integration steps Internal/External
MLI
  • Jig Horizontal
  • 1\ install SHV MLI SHV bond strap (SHV side -
     this is shared with one of the two  MLI grounds)
    covered by MLI ATS
  • 2\ install internal MLI blankets and
    corresponding bonding point to crate/xPD side
    covered by MLI ATS
  • 3\Install straps as soon as we can even if they
    are the exterior ones
  • 4\ Install if really needed the internal
    straps that might be difficult later
  • Jig Vertical
  • 5\ install external blankets when the radiator
    jig is vertical . The MLI bond at the radiator
    side (where applicable) remains floating till the
    radiator comes. Crates bonds need to be done
    later when radiator is in position. Only the
    crate side of the bond might be fixed. Fix it! In
    any case the blankets shall not prevent crates
    from running.
  • 5\A Another possibility is to install external
    blankets while the USS is in the PSS with the
    Jigs on. Waiting for the magnet.

59
21-24 April 2008 MLI Integration slot
VC Upper Skirt MLI
USR MLI
LSR MLI
Write a Comment
User Comments (0)
About PowerShow.com