Title: Warmte en kracht produktie vanaf biomassa


1
Warmte en kracht produktie vanaf biomassa
Vakgroep Toegepaste Mechanica Faculteit
Toegepaste Wetenschappen J. De Ruyck jdruyck_at_vub.a
c.be
2
Best use of biomass ??
  • As construction material ?
  • For pure heat production ?
  • For combined heat and power production ?
  • For electric power production only ?
  • For transport (liquid fuels) ?
  • Which technology ?

3

4
Candidate technologies ?
  • Extensive search for hard projects
  • Below 2 MWe only cogeneration, heat driven
  • Investment cost per kW thermal major criterion
    600-700 euro per kWth
  • Global efficiency major criterion 90-110 LHV
  • Electric efficiencies 12-25

5
Candidate technologies ?
  • Collected data for 65 sites/projects
  • Start year
  • Type of fuel
  • Power output
  • Electric/thermal efficiency
  • Total investment cost
  • CO,SOx, NOx, dust emissions

6
Candidate technologies cost ?
7
Candidate technologies efficiency ?
8
Candidate technologies emissions versus cost ?
9
Candidate technologies ?
  • Selected systems
  • Stirling engine, 5-30 kWe range
  • Fixed bed gasifier/piston engine, 300-600 kWe
  • Organic Rankine Cycle, 500-1500 kWe
  • Conventional steam cycle, gt 1000 kWe

10
Selected systems investigation
  • Extended questionnaires, site visits
  • More detailed information about
  • Technology
  • Costs
  • Grid connection
  • Fuel handling
  • Part load conditions
  • Lifetime
  • Residues, noise, size

11
Stirling engine (Harz, Austria)
  • S

12
Stirling engine (Harz, Austria)
  • Not yet commercially available, but several
    promising demonstrations units
  • Problems mainly fouling and vibration, noise
  • 25 engine efficiency (from engine heat to power)
  • 12 electric, 86 total efficiency
  • Asynchronous, no transformer, 380V direct on grid
  • Startup times 1 to 5 hours
  • Ability for load following unknown, not enough
    experience

13
Fixed bed gasifier (Xylowatt REGAL unit, Belgium)
14
Fixed bed gasifier (Xylowatt REGAL unit, Belgium)
  • Commercially available, 5 plants in preserial use
  • Problems unknown..
  • 25 electric 75 total efficiency
  • Asynchronous, no transformer, 220V direct on grid
  • Startup times 5-20 minutes !
  • Ability for load following none, no part load
    operation

15
ORC (Turboden TIRANO Italy)
16
ORC (Turboden TIRANO Italy)
17
ORC (Turboden TIRANO Italy)
  • Succesfull commercial operation, total of more
    than 50 000 hours operation
  • High availability (ORC 98), minor problems with
    boiler, pumps,..
  • 15 electric near 100 total efficiency
    (condensing boiler !)
  • Asynchronous, no transformer, 400V direct on grid
  • No gear box direct turbine connection (not
    possible with synchronous generator)
  • Startup times 2 hours to 5 days (due to
    refractory lining)
  • Good part load behaviour (turndown ratio 30)

18
ORC (Turboden TIRANO Italy)
19
ORC (Turboden TIRANO Italy)
20
Conventional steam cycle (Puulaakso, Finland, 1
MWe)
21
Conventional steam cycle (Puulaakso, Finland, 1
MWe)
  • Succesfull commercial operation, most common
    technology
  • High availability, no information about problems
  • 10 electric near 87 total efficiency
  • Synchronous, grid connected, stand alone possible
  • Startup times ½ hour to ½ days (refractory)
  • Good part load behaviour (turndown ratio 30)

22
?