Title: Progress on the Undulator Module System Test
1Progress on the Undulator Module System Test
- Marion M. White
- ANL-ASD-LCLS
2Outline
- Test Scope and Deliverables
- Components
- Setup
- Progress
- Documentation, Requirements
- Continued Plans
- Schedule
- Summary
3Test Scope
- Resolve remaining design questions on the
support/mover and fixed support systems fill in
details and make improvements as needed - Provide critical input to S/M system design
reviews. - Stability
- Repeatability
- Control and motion
- Robust
- Are the support/mover and fixed support systems
ready for production?
4Deliverables
- Measurement of girder and rollaway motions
- Precision, reproducibility, and independence of
motions, including start and stop - Check for interference
- Calibration
- Measurement of vibration damping.
- Measurement of position stability and temperature
dependence of components and subcomponents.
5Requirements
- Quadrupole Motion Positioning Repeatability 7
µm - Short-Term (1 h) BPM / Quad Stability 2 µm
- Long-Term (24 h) BPM / Quad Stability 5 µm
- Horiz. Segment Pos. Repeat. in Roll-Away
Cycle 10 µm - Vert. Segment Pos. Repeat. in Roll-Away
Cycle 5 µm - Quad Transverse Position Change in Roll-Out 25
µm - Quad Position Reproducibility after Roll-Away
Cycle 2 µm - BPM Transverse Position Change in Roll-Out 25
µm - BPM Position Reproducibility after Roll-Out
Cycle 2 µm
6Goals to Demonstrate
- Precision and repeatability of the cam-shaft
system vertically and transversely, measured _at_
undulator ends, for pitch and yaw motion as well.
- Goal is 5µ specification 7µ
- Precision and repeatability of 80-mm transverse
travel on the linear stages. - Goal is 10µ
- Precision of the K-value adjustment using
transverse linear stages. - Goal is 10µ
- Short term stability (10 hours) of the girder and
undulator. - Goal is 5µ specification 5µ
7Components
- Prototype undulator, or the substitute, or a 1st
article if one is available and measured. - Prototype support/mover system Girder, CAM
movers, Rollaway system, controls software and
hardware - Quadrupole Ersatz with fiducialization surfaces
- BPM Ersatz with fiducialization surfaces
- Vacuum Chamber Ersatz
- WPM, HLS, BLM sensors or Ersatz
- Prototype Fixed Support
- Earthquake protection bracing early prototype
8Preparation _at_ ANL
- Tests are done in the APS Magnet Measurement
Area, MM1 - Temperature regulated
- May need a plastic tent to improve thermal
regulation - Clean area
- Adequate space
- Experienced People
- Well-known floor and mechanically stable area
9A lot of work is done
- A lot of work was already done using the
breadboard girder, setting up the whole system,
installing and learning to use the monitoring
equipment, making improvements and design
modifications, and writing control and monitoring
software. - The results were surprisingly good, even for the
rudimentary breadboard girder, so even better
performance is expected in the real prototype. - Most designs are done, and most parts are on
order or in-house for the test.
10Prototype undulator at ANL on breadboard
support/mover system
11Prototype Girder
- Two rigid steel prototype girders are now being
fabricated at Lynn Machine, near OHare airport
in Chicago. - One will be used for the integrated undulator
test, and the other will be used for mechanical
measurements without disturbing the undulator
testing activities. - The girders will be delivered to ANL by early
November.
12Improvements to the CAMs
- Improvements were made to the CAMs as a result of
information gained in the setup and learning
phase. - Split bearing, hardness changed, spherical
bearing, v-plate, more gear ratio, no brakes,
13Single CAM-shaft Mover
- New gear box with ratio 2501 is installed.
- Calculations show this ratio is enough to hold
the undulator and girder in place without a
brake. - Less complexity.
14Double CAM-shaft Mover
The same changes were implemented in this unit as
in the single cam-shaft.
15Double CAM-shaft Mover (detail)
Hardness of the rings on the ball-bearings was
increased from 30-34 Rc to 50-55 Rc
16Single CAM-shaft Mover working w/ V pad
The flat pad is replaced by one with a V shape
- 16? angle. A double bearing is installed
instead of the single bearing Its purpose is to
replace sliding friction by rolling friction.
17Single CAM-shaft Mover
18Parts in-house by end of November
- Undulator substitute unit
- expected 11/15
- New cam-shaft movers with new gear boxes
- expected 11/25
- Modified transverse stages with 4 travel
- in-house
- Motors (in-house) and 90? gear boxes for stages
- expected 10/31
- Transition plates, wedges and supporting parts
- expected 11/25
19Controls hardware software
- Position settability and monitoring
- Verification of motion, repeatability
- Verification of limits
- Reproducibility and smoothness of start and stop
- Temperature monitoring
20Controls/Monitoring Working
21Case 1 X-Translation /- 1.5 mm Cyclic Motion
Repeatability
Target Repeatability lt /- 7.0 µm
22Fixed Support
- ANL assumed the Fixed Support scope a prototype
will be designed, constructed, instrumented, and
ready for evaluation as a part of this test. - The FDR will address the entire support/motion
system, including the fixed supports.
23Fixed Support Design
- 18 Support Tube
- 1½ Support Plates
- Sand Filled
- 3 Wool Fiber Insulation
- 1½ Anchor Bolts
24Installation Alignment
- Design for fixed supports takes alignment and
installation into account integration of
alignment philosophy with SLAC is ongoing.
25Module Layout for Integrated Test
26Designs are well underway Undulator on the
girder (left end)
27Designs undulator on the girder (right end)
28Use Ersatz Units as Needed
- The quadrupole, BPM, and vacuum chamber are
fiducialized Ersatz units with the right size and
weight. Some real units are planned - Pumping crosses and pumps
- Cabling, supports, and junctions
- Magnet water piping
- WPM, HLS, BLM sensors
- Some kind of Earthquake bracing will be
determined in collaboration with the SLAC safety
committee, and will be incorporated it may not
be final
29layout in short breakcartoon stages and stands
30Earthquake bracing
31Schedule
- Design/procuring vacuum/diagnostic components
- Developing detailed plan and refining engineering
specifications. - Controls HW/SW demonstrated debug/improve
- Prepare/fabricate test stand and components
August thru November 2005 On track to have many
of the components by December 2005. - Assemble early CY-06
- Short term test March 2006 leads to FDR with
longer-term 2-month test continuing after that.
32Schedule
33Summary
- An undulator module test will be carried out at
ANL in Winter 05-06 using prototype and
substitute components. - The test will provide critical data for the
support/mover system final design review prior to
production. - Much work was already done in Fall 05, leading to
improvements in system design, choice of
components, and control. - Many parts are either in-house or on order.
- Controls and monitoring software was written and
already demonstrated and debugged. Calibration in
progress. - Remaining hardware is expected in time.
34(No Transcript)