Title: Chapter 8: Sensitivity and Breakeven Analysis
1Chapter 8 Sensitivity and Breakeven Analysis
- Analyzing project risks by making mechanical
trial and error changes to forecast values of
selected variables.
2Introduction
- Analyzing the risks of investment projects, by
changing the values of forecasted variables. - Finding the values of particular variables which
give the project a Breakeven NPV of zero.
3Process of Analysis
- Identification of those variables which will
have significant impacts on the NPV, if their
future values vary around the forecast values. - The variables having significant impacts on the
NPV are known as sensitive variables. - The variables are ranked in the order of their
monetary impact on the NPV. - The most sensitive variables are further
investigated by management.
4Management Use of Sensitivity and Breakeven
Analysis
Using Sensitivity
- Sensitive variables are investigated and managed
in two ways - (1) Ex ante in the planning phase more effort
is used to create better forecasts of future
values. If management decides the project is too
risky, it is abandoned at this stage.
5Management Use of Sensitivity and Breakeven
Analysis
Using Sensitivity
Sensitive variables are investigated and managed
in two ways
- (2) Ex post in the project execution phase
management monitors the forecasted values. If the
project is performing poorly, it is abandoned or
sold off prior to its planned termination.
6Management Use of Sensitivity and Breakeven
Analysis
Using Breakeven
- Forecasted calculated Breakeven values of
variables are continuously compared against
actual outcomes during the execution phase.
7Terminology Within the Analysis
- Sensitivity and Breakeven analyses are also known
as scenario analysis, and what-if analysis. - Point values of forecasts are known as
optimistic, most likely, and pessimistic. - Respective calculated NPVs are known as best
case, base case and worst case. - Variables giving a breakeven value, return an
NPV of zero for the project.
8Selection Criteria For Variables in the Analysis
- Degree of management control.
- Management's confidence in the forecasts.
- Amount of management experience in assessing
projects. - Extrinsic variables more problematic than
intrinsic variables. - Time and cost of analysis.
9Real Life Examplesof Forecast Errors
- Large blowouts in initial construction costs for
Sydney Opera House, Montreal Olympic Stadium. - Big budget films are shunned by critics and
public alike e.g Waterworld whilst cheap
films become classics eg.Easy Rider. - High failure rate of rockets used to launch
commercial satellites.
10Developing Optimistic and Pessimistic Forecasts
- (a) Use forecasting error information from the
forecasting methods eg - upper and lower bounds
prediction interval expert opinion physical
constraints, are applied to the variables. - This method is formalized, but arguable, slow
and expensive.
11Developing Optimistic and Pessimistic Forecasts
- (b) Use ad hoc percentage changes a fixed
percentage, such as 20,or 30, is added to and
subtracted from the most likely forecast value.
This method is vague and informal, but fast,
popular, and cheap.
20
?
-20
12Outputs and Uses
- Each forecast value is entered into the model,and
one solution is given. - Solutions can be summarized automatically, or
individually by hand. - Variables are ranked in order of the monetary
range of calculated NPVs. - Management investigates the sensitive variables.
- More forecasting is done, or the project is
accepted or rejected as is.
13Strengths and Weaknesses of Analysis
- Easy to understand.
- Forces planning discipline.
- Helps to highlight risky variables.
- Relatively cheap.
- --------- --------- ---------
- Relatively unsophisticated.
- May not capture all information.
- Limited to one variable at a time.
- Ignores interdependencies.