Title: Engineering Economic Analysis Canadian Edition
1Engineering Economic AnalysisCanadian Edition
- Chapter 16 Economic Analysis in the Public Sector
2Chapter 16. . .
- distinguishes the unique objective and viewpoint
of public decisions. - explains methods for determining the interest
rates for evaluating public projects. - applies the benefit-cost ratio to projects.
- conventional
- modified
3- uses incremental benefit-cost for mutually
exclusive projects. - discusses the impact of financing, duration and
politics in public project decisions.
4Introduction
- Several factors complicate the economic analysis
by public organizations - Purpose of the investment, Financing sources,
Expected duration, Political effects, Project
beneficiaries - Public and private sectors have the same mission
- To make prudent investment decisions
5Investment Objective
- Private-sector companies seek to increase their
wealth and economic stability - Beneficiaries ? owners
- Public-sector organizations
- Overall concern is an increase in the general
welfare, not the identification of winners and
losers - Purpose of investment decisions is sometimes
ambiguous - Difficult to identify investments that promote
general welfare
6- Would the construction of a dam promote general
welfare? - Benefits water, electricity, flood control,
recreational facilities - Land losses farm land, woodlands for protected
species - Possible adverse effects on the water supply of
downstream communities
Conflicting aspects are common to many public
sector projects
7Viewpoint for Analysis
- Public-sector viewpoint
- includes those who pay the costs and those who
receive the benefits - Town, city, region, province, national
- Industry viewpoint
- firms costs and benefits
- costs and benefits external to the firm have been
generally ignored in the past - broader perspective on costs and benefits today
- firms will internalize some externalities
8Selecting an Interest Rate
- Private-sector
- consistent with the goal of wealth maximization
- Public-sector
- less clear-cut than private sector because the
goal is to promote general welfare (benefits
outweigh costs) - several interest rate alternatives
9Public Sector Interest Rate
- No time-value-of-money
- Set rate to 0 because there is no (short) lag
between collecting and spending tax money - Cost of capital
- Set rate equal to the cost of borrowed funds
10- Opportunity cost (Government and Taxpayer)
- Government set rate equal to that of the best
project forgone (for which funding is not
available) - Taxpayer set rate equal to the return that would
have been earned by the taxpayer in the absence
of taxation
11Recommended Public Sector Interest Rate
- Select the largest of
- Cost of capital
- Government opportunity cost
- Taxpayer opportunity cost
12Sample Public Sector Interest Rates
- The Treasury Board of Canada recommends the use
of a 10 interest rate for benefit-cost analyses - 5 and 15 for sensitivity analyses
- Some Canadian provinces recommend 7.
13- In the United States
- Armed forces 4
- Federal agency for highway transportation safety
3 - City school board 6.5
- State waterway commission 5
14B/C Ratios
- Any of the equivalent worth methods (present,
future, and annual) can be used to calculate a
B/C ratio - Produce identical results
- Decision rule
- If B/C ratio is gt 1.0, invest in project
- If B/C ratio is lt 1.0, do not invest in project
- If B/C ratio 1.0, breakeven point (need more
information and/or analysis to decide on course
of action)
15Some B/C applications
- Replace ferry by bridge or tunnel?
- Nuclear, solar, or wind-tunnel power generation?
- Four- or five-day school week?
- Bridge two-lanes now versus three-lanes later?
- Portable versus regular school classrooms?
- Residential water metering
16B/C Ratios
17B/C Ratio PW, FW, and AW
Example 16 - 2
18(No Transcript)
19B/C Ratios Conventional
20B/C Ratios Modified
OM Operating and maintenance costs
21Examples of Benefits and Disbenefits for Public
Investment
22Incremental B/C Ratio
- For the IRR and the B/C ratio methods, it is
inappropriate to select the best (mutually
exclusive) project on the basis of individual
project IRRs or B/C ratios - an incremental approach must be used
23B/C Criteria
For the IRR and the B/C ratio methods, an
incremental approach must be used to select the
best mutually exclusive project.
24Which Alternative is Better?
25Which Alternative is Better?(Conventional B/C
Ratio)
- Conventional B/C Ratios
- Project A
- B/C ratio 110/200(A/P,10,5) 40 - 30(A/F,
10,5) - 1.3 gt 1 ? Project A is acceptable
- Project B
- B/C ratio 175/350(A/P,10,10) 60
- 1.5 gt 1 ? Project B is acceptable
-
If A and B are independent, select both (capital
rationing may be a consideration). If A and B are
mutually exclusive, use the incremental approach.
26Which alternative is better?(Conventional B/C
Ratio)
- (?B(B-A) /?C(B-A) ) (BB BA)/( CB CA)
- (?B/?C) (175 110)/(117 87.9)
- 65/29.1
- 2.2 gt 1
- Select the project B
27Elements of the Incremental B/C Ratio Approach
- Identify all alternatives
- Calculate the B/C ratio for each project.
(Eliminate projects with B/C ratios lt 1.) - Rank order the projects using the denominator of
B/C ratio - Identify the increment under consideration
28- Use the incremental B/C ratio to make a decision
between the two projects - Iterate to Step 4 until all increments (projects
have been considered - Select the best alternative from the set of
mutually exclusive competing.
29Incremental B/C Ratios
Example 16 - 4
30Best Alternative
- If the four projects were independent
- projects I, II, and IV would be implemented in
the absence of capital rationing - B/C ratios gt 1
- If the four projects were mutually exclusive
- project II would be selected using the
incremental B/C approach.
31Conventional B/C Ratios
32- If Projects A, B, C, D, and E are independent and
capital rationing is not an issue, select all
projects (B/C ratios gt 1). - If A, B, C, D, and E are mutually exclusive,
select project D. - Compare A and B ?B/?C 1.5 select project B
- Compare B and C ?B/?C 1.2 select project C
- Compare C and D ?B/?C 1.3 select project D
- Compare D and E ?B/?C 0.9 select project D