Title: Engineering Economic Analysis Canadian Edition
1Engineering Economic AnalysisCanadian Edition
- Chapter 10 Uncertainty in Future Events
2Chapter 10
- uses estimated variables to evaluate a project.
- describes possible outcomes with probability
distributions. - combines probability distributions for individual
variables for joint probability distributions.
3- uses expected values for economic decision
making. - measures and uses risk in decision making.
- uses simulations for decision making.
4Precise Estimates Are Still Only Estimates
- All estimates are inherently variable and future
estimates are often more variable than present
estimates. - Minor changes in any estimate(s) may alter the
results of the economic analysis.
14-1 Clicking on the Excel icon will open a
spreadsheet.
5- Using breakeven and sensitivity analysis allows
an understanding of how changes in variables will
affect the economic analysis.
6Decision-Making and theVariability of Future
Consequences
- In the left box, PW(A) gt PW(B)
- In right box, Bs cash flow estimates are not
fully realized - Now, PW(B) gt PW(A)
7Sensitivity of Decision-Makingto Cash Flow
Changes
- In upper box, PW(A) gt PW(B)
- In lower box, by how much should Bs 4th year
cash flow grow - PW(A) PW(B) Breakeven
- Let PW(A) PW(B) 243.43 and Bs 4th year cash
flow x - PW (B) 700(P/A,10,3) x(P/F,10,4)
- x 736
8(No Transcript)
9Sensitivity of Decision-Makingto Cash Flow
ChangesBreakeven Analysis
- Helps to examine the variability of estimates on
outcomes - By how and in what direction will a summary
measure (e.g., PW, EAW, IRR) be affected by the
variability in estimates? - Does not take the inherent variability of
parameters into account in an economic analysis - Need to consider a range of estimates
10A Range of Estimates
- Usually three scenarios
- Pessimistic
- Optimistic
- Most likely
- Compute the rate of return for each scenario
- Compare MARR and each rate of return
- Each scenario has a ROR gt MARR in previous slide
11- What if MARR gt ROR for one or more scenarios?
- Are scenarios equally important?
- Need weighting scheme.
- Assigning weights
- Assign weight to each of the three scenarios
- Largest weight for the most likely scenario
- Pessimistic and optimistic may have or unequal
equal weights
12- Calculate the mean value from the weighted
average of the summary measure (e.g., ROR) for
each scenario. - Calculate a summary measure (e.g., ROR) from the
mean for each parameter (annual benefit and cost
first cost salvage value).
13- There is often a range of possible values for a
parameter instead of a single value - Optimistic
- Most likely (multiply by 4)
- Pessimistic
The expected value E(x) (O 4ML P)/6
Example 14-3 4
14- PW and other calculations for all sets of
scenarios are useful in understanding the impact
of future consequences. - If several variables are uncertain
- Unlikely that ALL variables will be optimistic or
pessimistic or most likely - Calculate average or mean values for each
parameter (e.g., mean first cost) based on
scenario weights
15- Upper box
- Minimal variability in the parameters among the
three scenarios - Lower box
- Considerable variability in the parameters of the
three scenarios - Conclusion
- Increased parameter variability ? large
differences between mean values
16(No Transcript)
17Probability and Risk
- Probabilities of future events can be based on
data, judgment, or a combination of both. - Weather and climate data expert judgment on
events - Most data has some level of uncertainty.
- Small uncertainties are often ignored
- Variables can be known with certainty
(deterministic) or with much uncertainty (random
or stochastic).
18- 0 Probability 1
- The sum of probabilities for all possible
outcomes 1 or 100. - Common in engineering economy to use 2 to 5
outcomes with discrete probabilities. - Expert judgment limits the number of outcomes.
- Each outcome requires more analysis.
19- Probability can be considered as the long-run
relative frequency of an outcomes occurrence.
Odds on drawing a card.
Odds on rolling dice.
20Joint Probability Distributions
- Random variables are assumed statistically
independent. - project life and annual benefit
- Project criteria depend on all input probability
distributions. - (e.g., PW, ROR)
- We need joint probability distributions of
different combinations of parameters.
21- If A and B are independent
- ? P(A) and P(B) P(A) x P(B)
- Three values and probabilities for the annual
benefit and two values and probabilities for the
life. - Six possible combinations that represent the
broader set of probabilities than the three
scenarios, most likely, pessimistic and
optimistic.
22- Joint probability distributions are burdensome to
construct when there a large number of variables
or outcomes
23- Project first cost 25,000 MARR 10.
- Calculate PWs if benefits and life are unrelated
Example 10-6
24Expected Value
- Weighted average of the random variable based on
the probabilities of occurrence of different
values of the variable - EX µ Spjxj for all j
- p probabilities x discrete value of the
variable - The expected value is the centre of the
probability mass.
25- An expected value (mean) may be determined in a
situation where two or more possible outcomes are
known and the probability associated with each
outcome is also known
26 27- If we know that the expected value (payout) on a
horse race is less than the money bet (the track
needs to have an income), then why do so many
individuals bet?
Example 14-8 The horse race.
28Expected Value PW(EV) ? EV(PW)
29- EV(Benefits)
- 5000(0.3) 8000(0.6) 10,000(0.1)
- 7300
- EV(Life)
- 6(0.67) 9(0.33)
- 7 years
30- EV(PW)
- -3224(20) 9842(40)
- 18553(6.7) 3795(10)
- 21072(20) 32590(3.3)
- 10,209
31- EV(PW)
- Use joint probabilities distribution for benefit
and life and the resulting probability
distribution for PW - See previous graph
- Add individual PW and joint probability products
32Expected Value
Example 10-9
33Decision Tree Analysis
- A decision tree is a logical structure of a
problem in terms of the sequence of decisions and
outcomes of chance events. - Demand for a new household product will depend on
the availability and quality of substitutes,
household incomes, etc.
34- Decisions depending on the outcomes of random
events force decision makers to anticipate what
those outcomes might be as part of the process of
analysis. - This analysis is particularly suited to decisions
and events that have a natural sequence in time
or space.
35- A decision tree grows from left to right and
usually begins with a decision node - Represents a decision required by the decision
maker ? - Branches extending from the decision node
represent decision options available to the
decision maker. - A chance node (circles ) represents events
whose outcomes are uncertain.
36Decision Tree Analysis Procedure
- Develop decision tree.
- Execute the rollback procedure on the decision
tree from right to left - Compute Expected Value (EV) of possible outcomes
at each chance node. - Select option with best EV.
- Continue rollback process until the leftmost node
is reached. - Select expected value associated with the final
node.
37Decision Tree Analysis
New Product
380
New Product
39Distribution of Outcomes
- Various standard distributions of outcomes have
been classified. The text describes two of these
distributions - Uniform
- Normal
- To understand the simulation of economic
problems, one must understand how a random sample
is drawn from a distribution.
40Generating a ProbabilityDistribution Using Excel
- RAND() returns anevenly distributedrandom
numbergreater than orequal to 0 andless than
1(changes on recalculation).
41Sample and Population Statistics
- Four common types of normal distribution
- Mean
- Average value of a set of values.
- Standard deviation
- A measure of the deviation of the values in a set
from the mean. - Maximum
- Largest value in a set of values.
- Minimum
- Smallest value in a set of values.
42Example 14-11
43Creating a Sample Using Random Normal Numbers
- In Excel, use Tool gt Data analysis gt Random
number generator gt Select your distribution.
44Simulation
- Simulation is the repetitive analysis of a
mathematical model.
Example 14-12
45Monte Carlo Simulation
- Attempts to construct the probability
distribution of an outcome performance measure of
a project (e.g. NPW, IRR) by repeating sampling
from the input random variable probability
distributions. - The sample frequency distribution generated can
be a good estimate for the probability
distribution of the event outcomes.
46- The probability distributions of the individual
random variables are known in advance. - By randomly sampling values from the random
variables from the probability distributions, a
sample of the overall performance measure of a
project is produced. - The process is seen as imitating the randomness
in the performance measure because of the
randomness of the project variables or inputs.
47(No Transcript)
48 49(No Transcript)
50(No Transcript)
51(No Transcript)