MONTHLY PROGRAM STATUS REVIEW - PowerPoint PPT Presentation

1 / 9
About This Presentation
Title:

MONTHLY PROGRAM STATUS REVIEW

Description:

Residual Risk is that risk remaining at launch after all mitigation efforts have ... 3 tools in a complementary abbreviated application to evaluate the likelihood of ... – PowerPoint PPT presentation

Number of Views:61
Avg rating:3.0/5.0
Slides: 10
Provided by: bryant4
Category:

less

Transcript and Presenter's Notes

Title: MONTHLY PROGRAM STATUS REVIEW


1
Section 1 Background
. . . Bryant Cramer EO-1 Mission Implementation
Manager
2
Residual Risk
  • Residual Risk is that risk remaining at launch
    after all mitigation efforts have been completed
  • The Red Team is charged to ascertain and
    document all residual risks, judged to be any
    level higher than low, that are remaining in the
    mission
  • NASA Administrator has asked that 3 system
    engineering tools be used to estimate the
    likelihood of occurrence and the overall mission
    risk associated with the predominant failure
    modes as identified by
  • Failure Modes and Effects Analyses
  • Fault Tree Analysis
  • Probabilistic Risk Analysis
  • Red Team Charter focuses on single-point failure
    mechanisms as a major source of residual risk

3
Three System Engineering Tools
  • NASA Administrator has asked that we evaluate
    residual risk through the use of
  • Failure Modes and Effects Analyses (FMEA)
  • Failure Tree Analysis (FTA)
  • Probabilistic Risk Analysis (PRA)
  • These are normally used during design definition
    to support the system engineering process
  • These tools were not used to develop the EO-1
    design
  • Single string design by policy
  • Hard cost cap and lots of schedule pressure
  • Redundancy was largely out-of-bounds -- by
    policy, by budget, by schedule, and by available
    staff
  • We utilized selective redundancy within the
    existing constraints as best we could
  • We propose to use these 3 tools in a
    complementary abbreviated application to evaluate
    the likelihood of successfully completing the
    EO-1 Minimal Mission

4
EO-1 Minimal Mission
  • Described in EO-1 Mission Success Criteria
  • Our evaluation will focus only on the EO-1
    Minimal Mission

5
EO-1 Residual Risk Assessment
  • Fault-Tree Analysis
  • Failure of the Minimal Mission
  • Includes all mission segments
  • Product is mission element failures that disable
    the Minimal Mission
  • FMEA
  • Down to box, board or service level, as
    appropriate
  • Used to survey single-point failures
  • Product is all single-point board failures
    disabling the Minimal Mission
  • Probability Risk Assessment
  • Classified by similarity
  • Reliability Block Diagram
  • Product is probability of single-point failures
    that disable Minimal Mission

Fault Tree Analysis of Minimal Mission
Single-Point Failures of Minimal Mission within
each Mission Element
Probabilistic Classification of Single-Point
Failures by Similarity
Reliability Block Diagram for Minimal Mission
Strategies for Mitigating More Probable Single-Poi
nt Failures
Residual Risk Assessment of EO-1 Minimal Mission
6
Failure Mode and Effects Analysis
  • Independently developed for the following
    segments
  • Flight
  • Ground System
  • Mission-Unique Launch Equipment
  • Developed in parallel with the FTA
  • All FMEAs are completed
  • By combining the FTA with the FMEAs, we can
    identify all of the potential single-point
    failures in each Mission Element that lead to the
    loss of the EO-1 Minimal Mission

7
Fault Tree Analysis
  • Developed for the EO-1 Minimal Mission
  • Advanced Land Imager (ALI)
  • Multispectral Imaging Technology
  • Wide Field Reflective Optics
  • Silicon Carbide Optics
  • Wideband Advanced Recorder / Processor (WARP)
  • Spacecraft performance adequate to flight
    validate the ALI
  • To include the following segments
  • Flight
  • Ground System
  • Launch (mission unique)
  • Proceeds to subsystem level or to board level in
    some cases
  • Serves to identify the loss of functionality that
    singularly and independently results in the loss
    of the EO-1 Minimal Mission
  • Serves to validate the FMEAs

8
Probabilistic Risk Assessment
  • A reliability estimate will be prepared for the
    single-point failures causing the loss of the
    EO-1 Minimal Mission
  • These estimates normally involve lengthy
    calculations based on failure rates of individual
    parts
  • Time does not allow us to pursue this traditional
    approach
  • Our estimates will be done at the box or board
    level based on similarity with earlier projects
    where detailed reliability calculations already
    exist
  • These will be integrated into a Reliability Block
    Diagram identifying the predominant modes of
    failure for the EO-1 Minimal Mission
  • Prioritized flight validation requirements will
    be organized against the calculated probability
    of completing the EO-1 Minimal Mission
  • This strategy will better mitigate the likelihood
    of the predominant failure modes

9
Reliability vs. Mission Success Criteria
Write a Comment
User Comments (0)
About PowerShow.com